Title: LCLS Photon Systems ETC and Methodology


1
LCLS Photon Systems ETC and Methodology
John Arthur LCLS Photon Systems Manager
  • LCLS Photon Systems
  • Continuing Resolution effects
  • The new ETC
  • Risks

2
LCLS Photon Systems Responsibilities
  • XTOD
  • Transport the x-ray beam, in vacuum, to
    experimental stations
  • Condition the x-ray beam, with attenuators and
    apertures
  • Analyze the x-ray beam, with sophisticated
    diagnostics
  • XES
  • Provide basic infrastructure required for
    experimenters
  • Build instrument for Atomic Physics experiments
  • Advanced x-ray detector RD
  • Laser
  • Coordinate laser design and acquisition
    throughout LCLS

3
XTOD Status
  • Design phase ending
  • Layout details almost complete
  • Nearly all technical components through
    Preliminary Design Review phase
  • Procurements have begun
  • LLNL team is working well with SLAC

4
XES Status
  • Now in design phase
  • AMO instrument design going well
  • 2-d detector development going well
  • Controls area much improved
  • PPS stopper design through PDR

5
Effects of the CR
  • CR caused delays and inefficiencies in FY07
  • Design reviews were delayed due to uncertain
    scope, schedule and busy managers
  • XTOD procurements were delayed in FY07

6
The New Plan Big Picture
  • Phased approach to X-ray beamline delivery
  • NEH in FY09, FEH in FY10
  • Diagnostics ready for first light in May 2009
  • Do first AMO experiments in FY2009
  • Instrumentation ready by end of July 2009
  • Delay as much work as possible until FY09-FY10
  • Within the constraints given above

7
The New Plan Details
  • Delay many AMO procurements until FY09
  • Pushes AMO instrument availability to 7-09
  • Delay some FEE work until FY09
  • Deliver light to NEH 7-09
  • Puts this XTOD work on the project critical path
  • BUT get FEE diagnostics ready for first light
    (5-09)
  • Requires some procurements in FY08

8
The New Plan Details 2
  • Ready to support LUSI in NEH in late FY09
  • Hard X-ray line to Hutch 3 will be complete
  • Get authority to begin exptl operations
  • Experiments in NEH in FY09
  • AMO and LUSI experiments

9
XTOD near milestones (Level 3)
  • Award High-Energy mirror PO 12-2007
  • First instrument ready to ship to SLAC 3-2008
  • Start FEE installation 7-2008

10
XES near milestones (Level 3)
  • AMO Preliminary Design Review 11-2007
  • 2D detector review 11-2007
  • Award Laser system PO 11-2008
  • Start installation in NEH 1-2009

11
(No Transcript)
12
Photon Systems New ETC
  • Increases
  • Extended schedule adds manpower cost (2000k)
  • Revised controls/DAQ plan shows increases (2400k)
  • Decreases
  • Savings in technical system costs (-900k)
  • Savings in transition to operations (-1500k)
  • Net TEC increase of about 3M

13
Photon Systems New ETC detail
14
Risks
  • FY08 budget crunch - some XTOD work might be
    delayed further (from FY08 to FY09)
  • One could delay some FEE and NEH controls work
    (300k total)
  • This would add slight cost risk and significant
    schedule risk for experimental work in FY09
  • XTOD and XES work is fund-rate limited

15
Risks 2
  • Offset mirror system
  • Mirrors are long-lead procurements (schedule
    risk)
  • Precision mirror controls still in development
    (cost and schedule risk)

16
Risks 3
  • Radiation Physics may require late changes
  • Novel source presents novel safety hazards,
    requires much analysis which is not yet finished
  • Additional shielding may be required (cost and
    schedule risk)

17
Preparation for good news Possible X-ray
speedups
If more FY08 funds become available, one could
  • Speed up controls and stands for FEE (1000k)
  • Speed up X-ray monitors in FEE (300k)
  • Speed up NEH controls and motors (450k)
  • Speed up XES laser system (340k)
  • Speed up AMO focusing mirrors (115k)

18
Summary
  • XTOD and XES have suffered delays due to CR
  • XTOD is in procurement phase, XES still in design
  • New plan allows recovery with extended project,
    phased completion
  • Should be ready for early occupancy of exptl
    areas