June 27 July 2: Remove Vacuum pipe spool pieces. July 3: Pull East Poletip ... Sept. 6 18: Beam Pipe Bakeout. Sept. 11th: STAR in IR with utilities connected. ... – PowerPoint PPT presentation

Number of Views:75
Avg rating:3.0/5.0
Slides: 3
Provided by: chri2
Category:
Tags: 27july2 | days | june | pipe | remove | riggers | shield | wall

less

Transcript and Presenter's Notes

Title: June 27July2: Remove Shield Wall 3.5 days, Riggers


1
  • June 27-July2 Remove Shield Wall (3.5 days,
    Riggers)
  • June 27 July 2 Remove Vacuum pipe spool
    pieces.
  • July 3 Pull East Poletip
  • July 5 Pull West Poletip. Install scaffolding
    EW. (Charlie Steve)
  • June 27 July 13 Remove SVT RDOs, extender
    cables, and cabling back to the Racks. Remove
    EEMC Trigger Cables.
  • June 27 July 18 Install Rollers and disconnect
    utilities, and roll STAR to AB and connect
    utilities.
  • July 20 Aug. 24 EEMC electronics maintenance.
  • July 19 27 Install SVT platform, FTPC West
    platform, and disconnect end of cone cables,
    remove FTPCs, and extract cone to platform.
  • July 30 Aug. 14 Remove SSD, SVT, all
    utilities on cone, and reassemble cone.
  • Aug. 1 15 Install new BEMC PMT comm./controls
    system.
  • Aug. 16-21 Reinstall cone, reinstall FTPCs,
    remove rails. Remove installation platform.
  • Aug. 22 27 Disconnect utilities.
  • Aug. 28 - 29 Roll STAR back into IR.
  • Aug. 30 Sept. 10 Install Utilities.

Draft STAR Shutdown Schedule/Plan
July 2007
August 2007
Summer Sunday
2
September 2007
  • Sept. 6 18 Beam Pipe Bakeout
  • Sept. 11th STAR in IR with utilities connected.
  • Sept. 11 Oct. 12 TPC Electronics maintenance.
  • October 1st TOF Trays arrive at BNL for
    installation.
  • Oct. 15 18 SGIS Certification.
  • Oct. 17th West Poletip installed.
  • Oct. 24 East Poletip installed.
  • Oct. 25 30 Magnet testing.
  • Nov. 1st Collider Cooldown Begins.
  • Nov. 1 2 Install BBCs.
  • Nov. 7th Lose access to IR for Collider
    Commissioning.
  • Still Open
  • When/where best to install TOF trays? Best
    locations 2, 4, 7, 1000.
  • Details/plan for the TOF water system?

October 2007
Collider Cooldown Begins