Title: Project Report
1Project Report
2Contents
- Schedule phase 1
- Phase 1 Milestones
- Progress to date
- Review plans
- Schedule phase 2
- Various things
- Things to be aware of
- design changes
- TRD updates
3Schedule Phase 1
- MICE Gantt chart are available on the web
- Critical path
4Target
- Prototype assembled and tested by end March
- Beam test in June
- Ready before end of May
- target unit
- upgraded power supply
- working readout electronics
- For long term
- metal bonded ceramic to replace indium seals
- Improvements can easily be incorporated
5Beam line
- To do
- Review the optics design
- Build in three stages
- Pion capture (synchrotron) area ?
- design complete Mid-May
- engineering complete end Aug
- Muon solenoid (breaches shield) ?
- test stand
- commission with cryogenics
- plinth rail system
- D2 and Matching section
- D2 stand and rail system
- triplet stands Q4-6 (rails) Q7-9 (static)
6Hall preparation
- Drilling
- Painting floor
- Structural support for shielding
- Fire escape and Mezzanine
- Front end shielding and solenoid plinth
- Solenoid shielding
- MICE plinth
- MICE platform services, esp. RF
In discussion
In design
In design
In design
7Infrastructure, Plant Services
- Electricity
- Available
- 1.25 MW
- 1 MW Average max, to allow for peaks
- Cooling water air conditioning
- Current (incomplete estimate)
- Need lt 800 kW for MICE to stage VI
- Distribution plan
- 3 phase, normal
- Demin/Hi purity, air, tap water
8Instrumentation
- Tracker
- Tracker review imminent light o/p
- TOF
- Size 40x40
- Prototype
- CKOV
- us concept
- ds funding
- Front end electronics DAQ
- Hardware software choices to be made
- Spectrometer Solenoid
- Tender spec being updated following review
9Installation
- Pre-shutdown
- Drilling Painting
- Structural work I
- Decay solenoid cryogenics
- Shutdown
- Beam line elements in synchrotron hall
- Shielding I
- Solenoid platform rails
- Solenoid into place
- Shielding II
- Remaining beam line elements
- Shielding III
- Post shutdown
- Commissioning
- ToF
- Tracker
- Solenoid
Fire escape, trench Mezzanine Plinth Platform,
cellar
10Time
Task-Milestones
11Phase 1 Milestones
Weighted by e.g. cost, the gap may look different!
Aug03
Jul08
12Design Reviews
- Today in plenary
- Yury
- Friday pm Technical Board semi-open
- Review the hall layout
- Paper copies of layout for TB
- Round table discussion
- Task leaders nominees to be present
- Questions raised to be documented
13Design review road map
14Schedule Phase 2
- Depends on delivery of (to state the obvious)
- solenoid II
- AFC modules I
- Cavity module I AFC module II
- AFC module III Cavity module II
- Schedule depends on Funding
- MICE stage V by ?
- MICE stage VI by ?
MICE note 137
15Various things
- Just starting to look at
- Interlocks and access document
- Control and monitoring infrastructure
16Change control
Change Request raises an awareness X is not
adequate because This is what we have in
mind This is what we will do
Response from technical board The TB
agrees/disagrees The TB request that the
following is also done
Other views
Review
Finally, TB accepts the changes Change Request
? Change Note New baseline issued through TRD
17Things to be aware of
- Changes to the baseline
- Cryo cooler choice (again!)
- Design of the tracker solenoid
- Tracker volume change
- Diffuser mechanism
- Hall Layout review Yury today, TB Friday
- Shielding of scintillation detectors
18Office space
- Space is difficult to find at RAL
- Senior management aware
- Initial request
- 4 offices
- 12 persons 3 rooms
- Meeting/secretarial/project office
- Followup on experience of demand
19Training
- ISIS User Office
- Procedures for training
- General level aimed at short experiments
- Services
- Transport bookings
- Finding hotels
- Badges (radiation) Passports
- Issue of MICE/RAL access badges
- Specific MICE training
- Magnetic fields
- RF, HT, Hydrogen (what is safe, what is not)
- Authorisation (who/what) rules