Project Report - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Project Report

Description:

plinth & rail system. D2 and Matching section. D2 stand and rail system ... Plinth. Platform, cellar.? paul drumm ? CM14 ? Feb/March 2006: 10. Task-Milestones. Time ... – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 20
Provided by: pauld102
Category:
Tags: plinth | project | report

less

Transcript and Presenter's Notes

Title: Project Report


1
Project Report
  • Paul Drumm
  • RAL, ISIS

2
Contents
  • Schedule phase 1
  • Phase 1 Milestones
  • Progress to date
  • Review plans
  • Schedule phase 2
  • Various things
  • Things to be aware of
  • design changes
  • TRD updates

3
Schedule Phase 1
  • MICE Gantt chart are available on the web
  • Critical path

4
Target
  • Prototype assembled and tested by end March
  • Beam test in June
  • Ready before end of May
  • target unit
  • upgraded power supply
  • working readout electronics
  • For long term
  • metal bonded ceramic to replace indium seals
  • Improvements can easily be incorporated

5
Beam line
  • To do
  • Review the optics design
  • Build in three stages
  • Pion capture (synchrotron) area ?
  • design complete Mid-May
  • engineering complete end Aug
  • Muon solenoid (breaches shield) ?
  • test stand
  • commission with cryogenics
  • plinth rail system
  • D2 and Matching section
  • D2 stand and rail system
  • triplet stands Q4-6 (rails) Q7-9 (static)

6
Hall preparation
  • Drilling
  • Painting floor
  • Structural support for shielding
  • Fire escape and Mezzanine
  • Front end shielding and solenoid plinth
  • Solenoid shielding
  • MICE plinth
  • MICE platform services, esp. RF

In discussion
In design
In design
In design
7
Infrastructure, Plant Services
  • Electricity
  • Available
  • 1.25 MW
  • 1 MW Average max, to allow for peaks
  • Cooling water air conditioning
  • Current (incomplete estimate)
  • Need lt 800 kW for MICE to stage VI
  • Distribution plan
  • 3 phase, normal
  • Demin/Hi purity, air, tap water

8
Instrumentation
  • Tracker
  • Tracker review imminent light o/p
  • TOF
  • Size 40x40
  • Prototype
  • CKOV
  • us concept
  • ds funding
  • Front end electronics DAQ
  • Hardware software choices to be made
  • Spectrometer Solenoid
  • Tender spec being updated following review

9
Installation
  • Pre-shutdown
  • Drilling Painting
  • Structural work I
  • Decay solenoid cryogenics
  • Shutdown
  • Beam line elements in synchrotron hall
  • Shielding I
  • Solenoid platform rails
  • Solenoid into place
  • Shielding II
  • Remaining beam line elements
  • Shielding III
  • Post shutdown
  • Commissioning
  • ToF
  • Tracker
  • Solenoid

Fire escape, trench Mezzanine Plinth Platform,
cellar
10
Time
Task-Milestones
11
Phase 1 Milestones
Weighted by e.g. cost, the gap may look different!
Aug03
Jul08
12
Design Reviews
  • Today in plenary
  • Yury
  • Friday pm Technical Board semi-open
  • Review the hall layout
  • Paper copies of layout for TB
  • Round table discussion
  • Task leaders nominees to be present
  • Questions raised to be documented

13
Design review road map
14
Schedule Phase 2
  • Depends on delivery of (to state the obvious)
  • solenoid II
  • AFC modules I
  • Cavity module I AFC module II
  • AFC module III Cavity module II
  • Schedule depends on Funding
  • MICE stage V by ?
  • MICE stage VI by ?

MICE note 137
15
Various things
  • Just starting to look at
  • Interlocks and access document
  • Control and monitoring infrastructure

16
Change control
Change Request raises an awareness X is not
adequate because This is what we have in
mind This is what we will do
Response from technical board The TB
agrees/disagrees The TB request that the
following is also done
Other views
Review
Finally, TB accepts the changes Change Request
? Change Note New baseline issued through TRD
17
Things to be aware of
  • Changes to the baseline
  • Cryo cooler choice (again!)
  • Design of the tracker solenoid
  • Tracker volume change
  • Diffuser mechanism
  • Hall Layout review Yury today, TB Friday
  • Shielding of scintillation detectors

18
Office space
  • Space is difficult to find at RAL
  • Senior management aware
  • Initial request
  • 4 offices
  • 12 persons 3 rooms
  • Meeting/secretarial/project office
  • Followup on experience of demand

19
Training
  • ISIS User Office
  • Procedures for training
  • General level aimed at short experiments
  • Services
  • Transport bookings
  • Finding hotels
  • Badges (radiation) Passports
  • Issue of MICE/RAL access badges
  • Specific MICE training
  • Magnetic fields
  • RF, HT, Hydrogen (what is safe, what is not)
  • Authorisation (who/what) rules
Write a Comment
User Comments (0)
About PowerShow.com