1
  • US 41 Corridor Project
  • Village of Howard-Board of Trustees Update
  • February 9, 2009

2
Presentation Outline
  • Project Overview
  • Project Goals
  • Project Highlights
  • Project Update
  • 2009 Construction Lettings

3
Project Overview
US 41 Project Overview
  • 17 miles in Winnebago County
  • 14 miles in Brown County
  • 13 interchanges reconstructed
  • 44 roundabouts
  • 8 lane Lake Butte des Morts Causeway
  • Largest road construction project in the history
    of Northeast Wisconsin
  • Construction start 2009

4
Project Cost Estimate
  • Brown County 545,000,000
  • Winnebago County 443,000,000
  • Total 988,000,000
  • Costs are SFY 2009 TPC estimates and include
    (Let, Non-Let and Delivery)

5
US 41 Project Schedule
Schedule subject to funding, NEPA and staging
reviews
6
US 41 Construction Schedule
  • Orange Lane to Glory Road
  • 2011-2015
  • Glory Road to Morris Street
  • 2011-2015
  • Morris Street to Memorial Drive
  • 2013-2015
  • STH 29 Interchange
  • 2011-2015
  • Memorial Drive to Lineville Road
  • 2013-2016

7
US 41 Project Goals
  • Deliver the US 41 Mega Project On-Time
  • Deliver the US 41 Mega Project On-Budget
  • Deliver a High Quality Project
  • Maintain Public Support, Trust Confidence
  • Create Opportunity
  • Achieve IH Design Standards
  • Deliver a Safe Project
  • Provide Aesthetics that Enhance the Character of
    the Project and Represent a Desired Community
    Image
  • Enhance Multi-Modal Opportunities
  • No Surprises

8
Project Highlights
  • Urban Service Interchange Reconstruction
  • System Interchange Upgrades
  • Mainline Capacity Improvements
  • Lake Butte des Morts Causeway Capacity
  • Safety Operational Improvement-Roundabouts
  • Safety Improvement-Lighting
  • Multi-Modal Improvements
  • Freeway Management Systems

9
US 41 Corridor Roundabout PlanA Safer Approach
  • ? Higher ? Lower

10
US 41 Corridor Roundabout PlanA Safer Approach
11
US 41 Corridor Roundabout PlanA Better Approach
  • ? Higher ? Lower

12
WIS 29 Interchange
  • US 41 WIS 29 interchange improvement
  • 3-leg system interchange
  • Imbedded service interchange(s)
  • Shawano Avenue (full)
  • Packerland Drive (half)
  • Addresses deficiencies
  • Meets Interstate Standards

13
STH 29 Fly Through
WIS 29 Interchange
14
IH 43 Interchange
  • US 41 IH 43 interchange improvement
  • Addresses deficiencies
  • Safety
  • Operations
  • Geometric
  • Meets Interstate Standards
  • 65 mph system ramps
  • Removes loop ramps

15
IH 43 Velp Avenue Access Change
  • US 41 IH 43 System Interchange Improvement
  • Removes access between IH 43 and Velp Avenue via
    US 41
  • Safety Operational Need
  • System ramps vs close interchange proximity
  • Eliminates deficient weaving segments
  • Access between IH 43 and Velp Avenue accomplished
    via
  • Velp Avenue and Atkinson Drive Interchange _at_ IH
    43
  • Lineville Road Interchange _at_ US 41
  • Shawano Avenue _at_ US 41

16
IH 43 Interchange
17
Collector Distributor Road System(Mason Street
to WIS 29)
  • A parallel roadway designed to remove weaving
    from the main line and to reduce the number of
    main line entrances and exits

18
Collector Distributor Road System(Mason Street
to WIS 29)
  • Significantly improved traffic operations at WIS
    29 and Mason Street interchanges
  • Eliminates freeway weaving
  • Improved long term service life of facility
  • Improves TMP constructability options (should
    WisDOT quantify savings due to easier
    construction staging)
  • C-D retrofit is not a possibility after
    construction

19
Collector Distributor Road System (Mason Street
to WIS 29)
20
Project Aesthetics-Winnebago County
  • Retaining Walls
  • Fencing/Railing
  • Columns
  • Roundabout Landscaping
  • Parapet Design
  • Decorative Lighting

Witzel Avenue Overpass Rendering
21
Project Update-Public Involvement
  • PI Goals
  • To meet with anyone, anyplace, anytime to create
    meaningful dialogue with the public
  • To establish trust and credibility within the
    community
  • To be the first and best source of information
    about the project
  • To seek public input at project milestones

22
Project Update-Community Outreach
  • Community Stakeholder Committee (CSC)
  • Semi-annual opportunity for communication between
    WisDOT, community officials and business leaders
  • February 16th initial meeting _at_ NE Region office
  • US 41 Neighborhood Liaisons
  • Provide connection to neighborhoods,
    communities
  • Provide opportunity for project input (access)
  • Provide timely project information
  • Community EventsLet Us Know


23
Project Update-Community Outreach-Public Meetings
  • Mid-April CTH F Interchange PIM
  • Mid-May WIS 29 PIM
  • May Initiate Morris to Memorial EIS
  • Mid-October WIS 29 EA Public Hearing
  • Various Community and Industry Events

24
Project Update-CSD
  • Community Sensitive Design (CSD)
  • Determine corridor aesthetics
  • Community coordination
  • CSD Committee/Workshops
  • Initial CSD Workshop is March 5th
  • 6 Workshops between March and September
  • Maintenance agreements will need to be developed
  • Village of Howard will be represented

25
Project Update-NEPA Process
  • South Segment (Orange Lane to 9th Street)
  • EA Re-evaluation (Summer 2009)
  • Middle Segment (9th Street to Memorial Drive and
    WIS 29)
  • EA FONSI (Spring 2010)
  • North Segment (Memorial Drive to Lineville Road
    and IH 43)
  • EIS ROD (2012)
  • Affects real estate acquisition, utility
    relocation and construction lettings

26
Project Update-Whats New
  • Traffic Management Plan
  • 2-lanes NB SB during construction
  • Interchange access restrictions-TBD
  • Staging workshops
  • Business community coordination
  • CTH M (Lineville Road) Interchange Reconstruction
  • 2013 construction
  • Done prior to Velp Avenue Interchange for TMP

27
Project Update-Whats New
  • GBMSD Utility Conflict
  • Mason Street to Velp Avenue
  • Potential for 16 million dollar utility
    relocation
  • Local Development Driven Improvements
  • WIS 29
  • Dousman extension
  • East-West connector
  • Velp Avenue
  • Development access, Wietor Wharf-Riverview Drive
    (CTH J)

28
US 41 Project Outreach Office
  • Project Outreach Office open in Green Bay at 100
    N. Packerland Drive
  • Opportunity for contractors to learn more about
    upcoming contracts
  • Opportunity for firms to learn about DBE
    certification, bidding requirements, etc.

29
2009 Construction Lettings
  • 2 Contracts
  • Lettings currently scheduled in March and June
  • Contract values ranging from 750,000 to
    3,000,000
  • Winnebago County
  • 12 Contracts
  • 40 million

30
DePere Stormwater Detention Pond
  • March 2009 Let
  • Series of new stormwater detention ponds adjacent
    to US 41 near Grant Street and Main Street (CTH
    G)
  • Contract value of 1,500,000 to 3,000,000

31
Brown County Building Razing Removal
  • June 2009 Let
  • Razing and removal of residential and commercial
    buildings along Shawano Avenue, Packerland Drive,
    Velp Avenue and Island Court
  • Contract value of 750,000 to 1,000,000

32
US 41 Project Quantities (Current Estimate)
33
US 41 Brown County
34
THE END
  • Questions?

Brett Wallace, PE USH 41 Corridor Program
Manager (920) 492-5693 Brett.wallace_at_dot.state.wi.
us
35
Brown County-Property Relocation Summary
  • 58 Total Parcels
  • Potential for 4-6 additional for GBMSD Conflict
  • 8 Commercial Parcels
  • 7 in Village of Howard
  • 1 in City of Green Bay
  • New WIS 29 (Shawano Avenue) Alignment
  • Shawano Avenue Taylor Street Intersection
  • Packerland Drive Interchange
  • Velp Avenue Interchange
  • Island Court

36
Winnebago County-Property Relocation Summary
  • 16 Total Parcels (14 Commercial)
  • 1 in City of Neenah
  • 2 in Town of Algoma
  • 4 in Town of Oshkosh
  • 9 in City of Oshkosh
  • US 45 Interchange
  • WIS 21 Interchange and Washburn Street
  • Breezewood Lane Interchange