Title: Environmental Groups
1San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
Contractors Outreach Program
November 10, 2000
2Civil/Environmental Steven Hulsebus, P.E.
3Project Limits
Project Limits
4Related Projects
- West Approach
- West Span
- West Viaduct
- Yerba Buena Island Tunnel
- East Span Interim Retrofit
- East Span Replacement
5Skyway Contract
6Civil / Environmental Concerns
- Contractor Access / Staging Areas
- Permitting
- Environmental Constraints
7Civil / Environmental Concerns
- Contractor Access / Staging Areas
- Permitting
- Environmental Constraints
- Caltrans will ensure access to the project site
- Contractors will need to identify and secure
other laydown and fabrication sites - Vehicle access to Yerba Buena Island will be
restricted - USCG will require 24 hour access through the work
zone
8Contractor Access on YBI
Vehicular Access
Potential Barge Mooring Areas
USCG Access
USCG Search and Rescue Base
9Yerba Buena Island
- Heavy topography -- 60 meter elevation
change - Steep slopes
- Narrow winding roads
- USCG base for 24 hour Search and Rescue unit
- Lots of underground utilities
10Contractor Access at Oakland Side
PGE Submarine Lines
Vehicular Access
Pacbell Submarine Line
EBMUD De-Chlor Plant
PGE Substation
EBMUD Outfall
11Oakland Touchdown
- Caltrans maintenance facilities
- Port of Oakland
- EBMUD De-chlorination facility and outfall
- PGE Substation
12Oakland Touchdown
13Civil / Environmental Concerns
- Contractor Access / Staging Areas
- Permitting
- Environmental Constraints
- Caltrans will secure permits
- for the project
- DMMO for disposal of dredged materials
- COE and BCDC for fill in the bay
- USFWS / NMFS for species of concern
- SWPPP
14Civil / Environmental Concerns
- Contractor Access / Staging Areas
- Permitting
- Environmental Constraints
- Historic Structures
- Environmentally Sensitive Areas
- Seasonal Restrictions for In-water Construction
- Noise
- Hazardous Materials
15Environmental Constraints on YBI
Historic Structures
USCG Facilities
16YBI Special Aquatic Sites
17Environmental Constraints at Oakland Side
18Oakland Touchdown Special Aquatic Sites
19Skyway Contract Dredge Access Area
20Typical Dredge Section
21Known Submarine Utilities
N
Unknown Utility Approximate Location
Navy Power Cable
PGE 10 Gas line
PGE Bay Cable 6 Abandoned in Place
ATT Fiber Optic
Existing SFOBB
Navy Cable
Phone Cables
EBMUD Outfall
PGE Bay Cable 3 Abandoned in Place
Known Submarine Utilities in the Project
Vicinity Not to Scale
2/22/99
22Submarine Utilities
1.2 m
To San Francisco
2.4 m
PGE 10 Gas Line
Navy Power Cable
To Oakland
23Utilities
Eastbound
Westbound
NOT TO SCALE
24Electrical Substation in Skyway
Access Stairways
Section
- Substation required for the bridges electrical
system - Access will be visible above the bridge barriers
25Conduits in Roadway Barriers
26Electrical Service Platform
27Roadway Light Standards
- Heights range from
- 7.5 m to 20 m
28Existing Seismic Sensor Location
29San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
30Geology Anthony R. Dover, P.E., G.E.
31Fugro-EM Reports
32Delineation of Areas Addressed
33Project Location Map
34Marine Exploration Location Map
35Structural ContoursBase of Young Bay Mud
36Isopach of Merritt-Posey-San Antonio Formations
37Structural ContoursTop of Lower Alameda Alluvial
Sand
38Top Franciscan and Onlap ofLower Alameda
Alluvial Sediment
39Structural Contours - Top of Franciscan Formation
Near Buena Island
40Phase 3 Bathymetry Contours
413-D View of Multi-Beam Bathymetry
42Phase 3 CPT Locations
43Boring and Cross SectionLocation Map - SFOBB
Main Span
44Boring and Cross Section Location Map - SFOBB
Skyway
45Key to Cross Sections
46Conceptual East-West Soil ProfileOutside (South)
of Recent Paleochannel
47Subsurface Cross Section A1-A1with Su and CPT
Tip Resistance
48Subsurface Cross Section A2-A2with Su and CPT
Tip Resistance
49Subsurface Cross Section A3-A3with Su and CPT
Tip Resistance
50Subsurface Cross Section A4-A4with Su and CPT
Tip Resistance
51Subsurface Cross Section A5-A5with Su and CPT
Tip Resistance
52Skyway Temporary Falsework Towers
- Required during construction to support portion
of superstructure - Two between piers E2-E3 connection to Main Span
- One between piers E16-E17 connection to Oakland
Shore Approach - Pile foundations will be required
- Contractor to select pile type, length, section
based on criteria provided - Maximum working axial load is limited to 1.8 MN
with - F.S. (side shear) 1.5
- Recommended piles and size range
- Steel pipe 0.41 to 0.61 m OD
- Square concrete 0.41 to 0.61 m on a side
- Steel H- pile 0.36 m width
- Soil profiles and example pile calculations to be
provided to contractor
53Subsurface Cross Section L-Lwith Su and CPT Tip
Resistance
54Expected Variation of Pile Tip Bearing Strata
55Axial Pile Design Parameters and ResultsSFOBB
Pier E7-Eastbound (Boring 98-49)
56Predicted Setup of Skin Frictionin Clay
57Soil Resistance to Driving andPredicted Blow
Counts
58Pile Installation Demonstration (PID) Project
59PID Project
- Document and evaluate hammer performance, pile
driveability, and driving behavior - Demonstrate marine construction techniques and
equipment - Develop welding procedures, specifications, and
document results - Measure noise (underwater, airborne) and ground
vibration from pile driving - Evaluate effectiveness of underwater noise
attenuation barriers - Observe marine mammal (seals) behavior
60PID Project
- 3 Steel pipe piles (1 vertical,
- 2 battered at 16)
- 2.438 m diameter, wall thickness
- 40 to 70 mm
- Each pile constructed in 4
- sections
- Specified pile tip elevation -102 m
- Pile length 107 m
- Hammers Menck MHU 500 and
- MHU 1700
61 PID Project
62PID Project - Status and Results to Date
(November 8, 2000)
- Pile Number 1 3 Sections Installed (Vertical)
- First section ran 6 m
- Pile tip currently at elev. - 78 m (end of
section 1C) - Menck MHU 500 Hammer used (full stroke at EOD)
- Blow count near EOD 20 to 30 bpqm
- Pile Number 2 1 Section Installed (Battered
16) - First section ran 6 m
- Welding
- Field pile splice welding is clearly a learning
curve - All field splice welds have required some repair
63PID Project - Status and Results to Date
(November 9, 2000)
- Pile Number 1 All 4 Sections Installed
(Vertical) - First section ran 6 m
- Pile tip currently at Elev. - 101 m (end of
section 1D) - Menck MHU 500 used on first 3 sections
- Menck MHU 1700 used on final section (At 100
stroke) - Blow count near EOD About 30 bpqm
- Pile Number 2 1 Section Installed (Battered
16) - First section ran 6 m
- Welding
- Field pile splice welding is clearly a Learning
Curve - Two field splice welds have required some repair
- Most recent splice - No repair
64San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
65Structures Overview Amer Bata, P.E.
66Project Limits
Project Limits
67SFOBB Contract Segments
Skyway
Oakland
Segment
YBI
SAS
Hinge A
Hinge E
Frame 1
Frame 2
Frame 3
Frame 4
68Cross Section
Shoulder
Shoulder
Five Traffic Lanes
Bike / Ped
69Segment 1-YBI Structures
- Viaduct Modification
- Temporary Detours
- Transition Structures
- EB On-Ramp
70YBI Viaduct Modification
- Structural Concrete 3500 M3
- Bar Reinforcing Steel 650,000 Kg
71Bent WB1
72Detour Structures
- Structural Concrete 6,700 M3
- Bar Reinforcing Steel 1,600,000 Kg
- Structural Steel 5,700,000 Kg
73West Bound Detour
74Eastbound Detour
75EB Detour Tie-In
76YBI Transition Structures
- Structural Concrete 54,000 M3
- Bar Reinforcing Steel 7,700,000 Kg
- Structural Steel 1,200,000 Kg
77YBI Transition Structures-Bent W4
78YBI Transition Structures-Bent W10
79YBI-EB On-Ramp
80 Segment 2 - SAS Bridge
- Structural Concrete 25,000 M3
- Bar Reinforcing Steel 5,200,000 Kg
- Structural Steel 52,000,000 Kg
81Dual Box Girder
82Bridge Elevation
657 m
385 m
80 m
180 m
12 m
Elev. 160m
Pier W2
Aprox. OG along PG Line
Pier 1 Tower
Pier E2
83Bridge Plan-Cable Layout
84Looping Cable Anchorage - Plan
- Cap beam
- Two deviation saddles, one jacking saddle
85Looping CableAnchorage - Elevation
- Roadway elevation differential
- Independent tie-down systems
86Looping Cable AnchorageSide Elevation
- West anchorage cap beam to bridge box girder
connection - Pier column to cap beam connection
- Gravity foundation system
87East Cable Anchorage Layout
- Main cable geometry at Pier E2
88Prefabricated Parallel Wire Strand Cable
89Cable Dehumidification
- Compressed dry air (40 humidity)
- Targeted air humidity inside the cable should be
less than 60
90Main Span-Tower Layout Details
91Main Span-Pier W2 Details
92East Pier
93Temporary Towers
94Segment 3 - Skyway
- Structural Concrete 220,000 M3
- Bar Reinforcing Steel 27,300,000 Kg
- Structural Steel 33,000,000 Kg
- Piling 15,000 M
95 Segment 4 - Oakland TD
- Structural Concrete
- 15,000 M3
- Bar Reinforcing Steel
- 5,400,000 Kg
- Piling 7,500 M
96Oakland TD Elevation
97Structure Plan - Oakland Approach
98Construction Staging WB Traffic Detour
- Skyway WB
- Main Span WB EB
- Construct Oakland Fill
- Construct Oakland EB Detour
- Traffic on Oakland EB Detour
- Construct WB Approach
- YBI Initial Viaduct Modification Portion of WB
Transition - WB Detour Structure
- Portion of EB Detour Structure
99Traffic On WB Detour
- Construct Oakland EB Landing
- Remove upper deck at YB4
- Complete EB YBI Detour Tie-In
- Switch traffic to YBI EB detour structure
100Traffic On Detour Structures
- Continue Oakland EB Landing
- Remove existing bridge from Bent 48 to YB4
- Continue EB Skyway
101Construction Staging
- Construct EB and remaining WB Transition
Structures - Switch EB traffic to new bridge
- Complete YBI Viaduct Modifications
- Switch WB traffic to new bridge
102Construction Staging
- Remove detour structures
- Construct EB on- ramp
- Complete bike path
103San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
104- Skyway Structures
- Sajid Abbas Ph.D., P.E.
- Rafael Manzanarez, P.E.
105Project Limits
106San Francisco Bay Area
107Existing Structure
108Existing SFOBB East Span
109Loma Prieta Earthquake
110New Bridge
111Design Philosophy
112Contract Limits
113Proposed SFOBB East Span
114Self-Anchored-Suspension Bridge
115Skyway Structures
116Skyway
117Site Geology
118Skyway Framing System
119Geology
120Conceptual Soil Profile Beneath Skyway
121Top of Franciscan Rock
122Pile Tip Bearing Strata
123Piles
124Foundation Types on Skyway
125Description of Pile Foundation
- 2.5 m constant outside diameter CISS piles.
- Driven shells with composite reinforced concrete
fill in upper section - Batter 18 and 112
- Shell (thickness 51-77 mm) fy345 MPa
- Concrete fc25 Mpa
- Reinforced Steel fy415 Mpa
- Lower core bond connection uses shear rings
- Upper core bond uses welded shear studs
126Target Tip Elevations
- Piles generally tipped 4 m into LAA sands (Elev.
- 95 m NGVD) - Bias pile tips into sand layers
- Driveability by 1,000 kJ (735 ft.kip) hammer
127Pile Details
128Hydraulic Pile Hammer
Jamuna River Bridge Mencke MHU 1700
129Pile Installation
- Pile shells to be driven 160
- Average pile length 94 m
- Total pile length 15,000 m
- Maximum pile weight 365 t
- Min. Hammer energy (_at_90) 1,000 kj
- Field splices not permitted in zones of high
bending
130Pile Caps
131Pile Cap
132Pile Cap
133San Francisco-Oakland Bay Bridge
134San Francisco-Oakland Bay Bridge
135San Francisco-Oakland Bay Bridge
136San Francisco-Oakland Bay Bridge
.
.
137San Francisco-Oakland Bay Bridge
138San Francisco-Oakland Bay Bridge
139San Francisco-Oakland Bay Bridge
140San Francisco-Oakland Bay Bridge
141San Francisco-Oakland Bay Bridge
142San Francisco-Oakland Bay Bridge
.
.
143San Francisco-Oakland Bay Bridge
144Piers
145Transverse Section
146Service Loads on End Piers
- Creep, Shrinkage, Elastic Shortening
- Imposed Displacement on Pier Tops
- Jacking in the middle of the frame
147Box Pier
148Superstructure
149Skyway Framing System
150Frame 1
151Box Girder
152Light Rail Configuration
.
153Bike/Pedestrian Path
154Bike/Pedestrian Path
155Typical Cantilever
156Typical Cantilever
157Prestressing Details
158Phase 1 Foundation
159Phase 2 Construction of Pier Table
160Phase 3 Cantilever Construction
161Phase 4 Closure of Exterior Spans
162Phase 5 Jacking and Closure of Interior Span
163Phase 6 Closure of Hinge Span
164Phase 7 Bridge Completion
165Expansion Joints
166Expansion Joints
167Hinge Beam Details
168Hinge Beam Details
169Hinge Bearing
170Hinge Beam Details
171Hinge Erection
172Construction Sequence 1
173Construction Sequence 2
174Construction Sequence 3
175Construction Sequence 4
176Construction Sequence 5
177Transition Span
178Skyway Cast-In-Place (1) Hinge A
179Skyway Cast-In-Place (2) Hinge A
180Skyway Cast-In-Place (3) Hinge A
181Skyway Cast-In-Place (4) Hinge A
182Construction Sequence for Hinge (Oakland 1)
183Construction Sequence for Hinge (Oakland 2)
184Construction Sequence for Hinge (Oakland 3)
185Construction Sequence for Hinge (Oakland 4)
186Skyway All The Way !
187(No Transcript)
188(No Transcript)
189 Go Build It !
190San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
191- Specifications
- Sharon Naramore, P.E.
192Specifications
- A B
- Working Days
- Metric Units
- Buy America
- Construction
- Surveying
- CRIP
- Marine Access
- Dredging
193Specifications
- Concrete
- Precast QC
- (all new)
- Welding QC
194Specifications
- Order of Work
- Existing Facilities
- Earthwork
- Piling
- Temporary Towers
-
195Specifications
- Furnish Precast Concrete
- Segments
- Erect Precast Concrete
- Segments
- Modular Joint Assemblies
- Segmental Circular Bearings
- Overlays
196Specifications
- Reinforcement
- Steel Structures
- Clean and Paint Structures
- Jack Superstructure
197Information Handout
- Design Criteria
- Foundation Recommendations
- Precast Concrete Plant Audit Form
- Steel Products Plant Audit Form
- Caltrans UT Certification Application
- Mass Concrete Report
- PIDP Results Including Welding Reports
198San Francisco 1906