having realised that the PPP development process will take longer than ... Commercial Space: refectory, bookstore. Housing: senior staff, junior staff, students ... – PowerPoint PPT presentation

Number of Views:150
Avg rating:3.0/5.0
Slides: 10
Provided by: emm73
Category:

less

Transcript and Presenter's Notes

Title: BOTSWANA INTERNATIONAL UNIVERSITY OF SCIENCE AND TECHNOLOGY BIUST


1
BOTSWANA INTERNATIONAL UNIVERSITY OF SCIENCE AND
TECHNOLOGY (BIUST)
  • FOUNDING DEVELOPMENT
  • Presented by
  • Eunice Naledi Mmono
  • To the Investors Conference
  • 4th November, 2008

2
The Founding Development (FD)
  • Background
  • What is the Founding Development and Why?
  • - this is a campus start up development that
    will form phase 1 of the BIUST.
  • - having realised that the PPP development
    process will take longer than anticipated,
    Government took a decision to start up the
    university in order to meet the expectations of
    Batswana at the soonest possible time.
  • - it was further decided that the development
    will be no where else but on site, where it will
    eventually form part of the overall BIUST
    development.

3
The Site- BIUST sits between the Martins Drift
fly over to the South, the Palapye built up
area to the North, the railway line westward and
the Tswapong hills to the East. - The NSWC
traverses the site, . A servitude will be
necessary.- The FD will be located at the heart
of the site.
4
Radial developmentThe university development
will occur in a radial fashion from the FD.
5
Elements of the Development
  • The development is to be Fast Tracked in order
    to open the university doors for student
    enrolment in March 2011.
  • The FD is to be financed by Government through a
    design and build contract.
  • A decision was made to have this as a closed
    tender where a total of six contractors were
    selected to tender.
  • Four of the six participated while the other two
    withdrew.
  • The tender closed on the 8th October 2008 and
    bids are awaiting evaluation which was pending
    the appointment of a project management team.

6
Elements cont
  • The project management firm for the FD will be
    announced during next week.
  • It is expected that the contract will be awarded
    by the end of the year.
  • Government will operate and maintain this FD
    until the phase 2 development of the campus is
    completed through a PPP.
  • Operation and maintenance of the physical
    facilities of the FD will be handed over to the
    PPP Operator.

7
Facilities for the Founding Development
  • Central Administration
  • Academics Sciences, Technology, Engineering,
    Management
  • General Teaching classrooms, small class
    breakout sessions
  • Library Learning Centre
  • Student Services Amenities student centre,
    health clinic, athletics
  • Commercial Space refectory, bookstore
  • Housing senior staff, junior staff, students

8
Founding Development size
  • The first cohort of an estimated 128 students
    will be admitted in March 2011.
  • In year two, the second cohort of 128 students
    will be admitted, for a total of 256 students.
  • Faculty and administration will also be in place
    from year one, growing in step with student
    cohort numbers.
  • Construction of the PPP will have to bear in mind
    the needs of students and faculty in year three
    and beyond.