Process Control in Huntsman Petrochemicals - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

Process Control in Huntsman Petrochemicals

Description:

Run column at maximum reflux subject to constraints. Constraints are ... Plant tested to measure responses of each constraint to reflux changes ... – PowerPoint PPT presentation

Number of Views:314
Avg rating:3.0/5.0
Slides: 23
Provided by: mikeog
Category:

less

Transcript and Presenter's Notes

Title: Process Control in Huntsman Petrochemicals


1
Process Control in Huntsman Petrochemicals
  • Mike Oglesby

2
Improving the Assets
  • The plants purchased from ICI had control systems
    nearing the end of their useful life
  • Spares becoming difficult to get
  • Increased failure rate of control room equipment
  • Control rooms dont meet current safety standards

3
Replacing the Control System
  • Existing heritage systems are control panel
    based pneumatic or electronic
  • New systems are computer based Distributed
    Control Systems (DCS)
  • Control Systems are very expensive
  • Their replacement has to be justified on
    financial grounds

4
Justifying the Replacement
  • Replacing a control system with one having the
    same functionality gives very little quantifiable
    benefit
  • Big benefits come from exploiting the improved
    functionality of the DCS system
  • For a viable project we need to combine the DCS
    with advanced process control (APC)
  • DCS costs 80 of total cost gives 20 of
    benefit

5
Identifying the Areas for Improved Control
  • Define plant objective
  • Maximum production rate of on-spec. material
  • Translate to local objectives for unit operations
  • Run column at maximum reflux subject to
    constraints
  • Constraints are
  • Flooding, Reboiler limits, condenser limits

6
Estimating the benefits
  • Use historic data
  • How well did the existing control system
    operator manage to achieve the objective on
    average?
  • What was the best ever achieved performance?
  • What benefits would result if the best ever was
    achieved all the time?

7
Achieving the Benefits
  • Approach followed depends on the plant and the
    Control opportunities identified
  • Approaches can be very different
  • Olefins plant has used on-line computer control
    for over 30 years plant very well understood
  • 30 year old Paraxylene plant uses same control
    philosophy as when built interactions between
    areas of plant not fully understood

8
Olefins Plant
  • Full plant on-line optimiser at the top level
  • Sends down control strategy objectives to next
    level
  • Runs every couple of hours
  • Model Based Predictive Controllers
  • Maintain control strategy on minute to minute
    basis between updates from optimiser
  • Send setpoints down to PID loops at bottom of
    chain
  • 23 Model Based Controllers co-ordinated
    operation
  • Very large schemes 41 by 72 multivariable
    controller

9
Data Flow Diagram
Set Points
Plant data
10
Paraxylene Plant
  • Benefits study here identified over 50 APC
    schemes
  • Many based on running plant up against
    constraints
  • Much simpler schemes than on Olefins plant
  • Largest is 8 by 24 with little dynamic
    interaction
  • Decision made to use PID based technology to
    achieve benefits

11
Implementing the APC schemes
  • Stage 1 is to cut over from existing Control
    System to the DCS
  • Operators have to get used to operating plant
    using new equipment
  • To ease this, the DCS uses exactly the same
    control system as the old system
  • Stage 2 is to install commission the new schemes

12
Project Plan
  • DCS installation complete
  • Early June
  • Plant Available for APC implementation
  • Early July
  • APC implementation to be completed Plant
    Maintenance Shutdown Starts
  • Mid September
  • Project has to be Fast Track

13
APC Scheme Implementation
  • Build scheme using standard DCS building blocks
  • Test Offline
  • Ensure there are no holes
  • Ensure correct response on signal failure, etc.
  • Operator Training Validation
  • There are 6 Shifts each with 5 people to train on
    about 50 different schemes
  • Scheme Tuning
  • Needs plant testing to define process gains
    dynamics

14
Speeding up the Project
  • Access to the plant is restricted due to fast
    track nature of whole project
  • Need to do as much as possible off-line
  • Interface Models to the APC schemes
  • Simple models based on 1st order lag Dead Time
  • Models based on dynamic chemical engineering
    models
  • Use these models to reduce time on site
  • Use plant tests to match models to plant
  • Then use the models to tune APC schemes

15
Distillation Column
  • Maximise reflux subject to
  • Column Flooding Column PD
  • Condenser Limit Pressure controller output
    lt100
  • Reboiler Limits
  • Fuel Gas Valve lt100
  • Furnace Tube Skin Temperature Limit
  • Low Stack Oxygen Limit

16
(No Transcript)
17
Commissioning
  • All non-APC controller tuning checked
  • Plant tested to measure responses of each
    constraint to reflux changes
  • PI settings for each constraint controller
    identified
  • Switch on with constraint setpoints closed in
  • Force each constraint in turn to become active
    and check response
  • As scheme proves its ability to control plant
    well move constraints out

18
Experience to Date
  • All schemes commissioned to plan
  • Delivering expected benefits
  • Spin-off benefits achieved
  • Distillation column with sharp temperature profile

19
Column with Sharp temperature Profile
  • Problem for 30 years
  • Process Gain at Setpoint VERY high but very low
    just a small distance away from the setpoint
  • Difficult / Impossible to Stabilise
  • Works well with Gain scheduled PID controller

Height
Control Tray
Setpoint
Temperature
20
(No Transcript)
21
Where Next?
  • Paraxylene
  • Now parts of the plant are tied down further
    opportunities can start to be seen
  • Starting to make use of data collected by DCS to
    understand the process
  • Olefins
  • Expert system to provide early warning of
    potential plant upset
  • Aromatics
  • Next plant to have a control system upgrade
  • Currently part DCS / part Pneumatic

22
The Future
  • Supply Chain Integration
  • Build on information platforms
  • Provide timely, accurate data to all key Business
    functions
  • Off plots Areas
  • Movements Automation Tracking
  • Benefits
  • Could be 10-12 of Turnover
Write a Comment
User Comments (0)
About PowerShow.com