TPC status and plans - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

TPC status and plans

Description:

Test of FEE & ROC (C-side) Test of FEE, Trigger, DAQ, DCS and services July ... Characterization of ROC FEE HV power supply. TPC: L. Musa, R. Campagnolo, C. ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 47
Provided by: NIC8169
Category:
Tags: tpc | plans | roc | status

less

Transcript and Presenter's Notes

Title: TPC status and plans


1
TPC status and plans LHCC CR7, CERN, 19th March
2007 L. Musa
  • Outline
  • Pre-commissioning above ground (2006) short
    summary
  • Preparing for the commissioning in the cavern
    (2007)

2
TPC pre-commissioning above ground (2006)
  • A first phase of TPC Commissioning was carried
    out above ground in the course of 2006
  • Jan-Mar installation of SSW and FEE
  • April start of gas system
  • May HV (100KV) applied to FC
  • JunDec test of all sectors (in pairs)
  • Each sector was operated continuously over a
    period of 40 hours and verified with
  • calibration pulser,
  • cosmic-muon trigger detector ACORDE
  • UV laser system for the generation of tracks in
    the detector

Many TPC and ALICE sub-systems (e.g. cooling,
gating grid pulser, temperature sensors, DCS,
Trigger, DAQ, HLT and Offline) have been part of
this commissioning programme
300 man shift, 3588 runs, 24 TB in CASTOR
3
TPC pre-commissioning above ground (2006)
ALICE COSMIC Trigger (ACORDE)
Laser tests
Cosmic tests
  • Only two sectors could be instrumented at a time
    with
  • Low Voltage Power Supplies
  • Cooling
  • Commissioning objectives
  • Test functionality of all components
  • gas stability, noise, signal tails, gain
    homogeneity, space resolution, etc.

Each pair of sectors continuously operated over
40 hours
4
TPC pre-commissioning (2006) some results Gas
system
Excellent stability ? excellent gas tightness
1-2 ppm oxygen _at_ 1/3 of nominal gas flow (TDR
requirement lt 5ppm O2)
5
TPC pre-commissioning (2006) some results
Noise measurements
after optimization of ground scheme and with VHV
off
? (PASAnoise2 ADCnoise2) 0.70 ADC counts
r.m.s. of the pedestals (sNOISE) is below 1 ADC
count as required in the Technical Design Report
6
First cosmic rays events
Outer ROC
Inner ROC
3-dimensional view of a cosmic muon track
traversing 2 sectors
7
First cosmic rays events
Outer ROC
Inner ROC
Front view
Side view
3-dimensional view of a shower induced by cosmic
rays
8
TPC pre-commissioning (2006) some results
Cosmic tracks
A
B
O2 extracted from fit to our data
space point resolution as function of z position
(cut on inclination angle tan(f) lt0.05)
A
TDR value 210mm / ?cm
  • Q total (total charge in the cluster) as
    function of z position
  • relative decrease over the full TPC length 10
  • decrease due to electron capture and tail losses
  • (diffusion)

B
1-2 ppm of O2 measured with oxygen analyser
9
TPC pre-commissioning (2006) some results
Laser tracks
Design
Measured
Drift velocity 2.73 cm/ms ? agreement with
drift monitor detector (Goofie)
10
Moving the TPC into the ALICE magnet
? Jan 07 TPC has been lowered in UX25
  • After the alignment with respect to the beam
    line, the TPC has
  • been put in parking position.
  • February, alignment of SSW with respect to
    endplate, and test of the
  • connection of FEE to the endplate
    (calibration pulser)

? All 4356 FECs and 216 RCUs are working ? All
26136 kapton cables are properly connected to the
pad plane
11
Alignment of SSW wrt endplate within mm
Displacements of SSW wrt endplate should not
exceed 3mm
7 mm
Readout Chamber
X
Front End Card
kapton cable
Y
Z
12
Preparing for Commissioning in UX25
  • In 2006 all efforts mostly devoted to
    pre-commissioning in SXL2
  • Few hardware components still to be finalized or
    constructed
  • Trigger Busy Box (being finalized and tested)
  • TriggerDCS Interface Unit for Laser, GG Pulser
    and Calibration Pulser
  • (starting design)
  • Many software components to be finalized and
    commissioned
  • Some examples
  • Software for the configuration and monitoring of
    the FEE
  • Interface to the FERO database
  • Interface to ECS
  • DCS for some of the sub-systems and TPC FSM
    (Supervisory Layer)
  • Data Quality Monitoring

13
Preparing for Commissioning in UX25
Connecting the TPC to the ALICE systems and
services
  • Cables, fibers and cooling pipes (all cables and
    cooling lines will be tested
  • before connecting them to the TPC )
  • Installation from crates to patch panels _at_
    backframe (C side)

completion end of April
  • test assembly of connectors _at_ patch panels on
    backframe (C side)

starting from May
  • TPC wil be moved to final position (interaction
    point) middle June
  • Connection of TPC C side second half of June
  • installation of miniframe (A side) middle of
    August
  • test assembly of connectors _at_ miniframe (A
    side)

second half of August
  • Connection of TPC A side 26 Aug 7 Sep

14
Preparing for Commissioning in UX25
Connecting the TPC to the ALICE systems and
services cont.
  • The TPC can be connected to the Gas system
  • only in final position

middle June
  • About 1 month to reach nominal gas composition

middle July
Note
  • The TPC can be connected to the Gas
  • System with final pipes (on A side)
  • only after installation of miniframe
  • (middle August) and closure of magnet
  • doors (middle October)
  • From middle June to middle October,
  • the TPC will be connected to the
  • Gas System via auxliary pipes

15
Preparing for Commissioning in UX25
Installation tasks for the TPC Collaboration
(starting from May)
  • cut, put connectors, mount cables going to TPC
  • (10 Redel, 5SHV, 38 LVsense, 19 ctrl, 19 mon,
  • 12 laser, 4 ELMB per side)
  • cut, put on lugs, LV cables
  • (72 per side)
  • mount stored cables coming from TPC
  • (44 per side)
  • proper bundling towards TPC and towards
  • backframe/miniframe
  • (252 cables, 112 fibers per side)
  • support structure between SSW and
  • backframe

HV, LV sense, temp ELMB, laser
LV
miniframe/ backframe
TPC
SSW
cooling
Gate, Calib, DCS DDL, TTC
16
TPC commissioning - Milestones
  • Test of FEE ROC (C-side)
  • Turn on FEE July
  • Test of FEE, Trigger, DAQ, DCS and services July
  • Test of ROCs July - Aug
  • Test of FEE ROC (A-side)
  • Turn on FEE Sep
  • Test of FEE, Trigger, DAQ, DCS and services Sep
  • TPC Commissioning with cosmic tracks, laser Sep
    - Oct
  • and Kr
  • ALICE Commissioning Oct -Nov

17
TPC work plan ( resources) in 2007
Cables, fibers, and pipes
TC ALICE Technical Coordination Team
18
TPC work plan resources
Cables, fibers, and pipes contd
TC Technical Coordination Team
19
TPC work plan resources
Power supplies and pulsers
TC Technical Coordination Team
20
TPC work plan resources
Electronics debugging spares new developments
TC Technical Coordination Team
21
TPC work plan resources
Electronics debugging spares new developments
contd
TC Technical Coordination Team
22
TPC work plan resources
Configuration, Control and Monitoring Software
TC Technical Coordination Team
23
TPC work plan resources
Configuration, Control and Monitoring Software
contd
TC Technical Coordination Team
24
TPC work plan resources
Other commissioning activities
TC Technical Coordination Team
25
TPC work plan resources
TPC Commissioning
TC Technical Coordination Team
26
Preparing the TPC Calibration
Calibration software for 2007)
  • Electronics (pedestals, noise, gain, time
    offset, peaking time)
  • pedestal runs, calibration pulser
  • R. Bramm, H. Helstrup, J. Thaeder
  • Gain (parametrization, pad-by-pad variations,
    dE-dx, attenuation loss)
  • Krypton, cosmics (parametrization), laser
    (central electrode signal)
  • J. Wiechula, P. Christiansen, P. Gros, H.
    Helstrup, J.Thaeder, D. Vranic, M. Kowalski,
  • S. Gaertner
  • drift velocity
  • laser tracks and central electrode signal
  • M. Ivanov, J. Wiechula, L. Bozyk, R. Bramm,
    J.Thaeder, R. Toft
  • Space point (resolution and cluster shaper
    parametrizations)
  • M. Ivanov (TDR values already achieved)
  • Space point corrections (E distorsions, E ? B,
    drift velocity)
  • laser tracks and central electrode signal
  • M. Ivanov, J. Wiechula, M. Mager, M. Kowalski

27
Preparing the TPC Calibration
Calibration software, contd
  • Alignment (central electrode, internal
    alignment, global alignment)
  • M. Kowalski, D. Vranic, M. Ivanov, J. Wiechula
  • Data quality monitoring based on calibration
    parameters
  • (noise, gain, time offset, space point
    resolution)
  • pulls for sectors, pad-rows, detection of
    outliers, alarms
  • TPC, HLT, DAQ, Offline (under discussion)

28
Conclusions
  • Exstensive commissioning of the TPC above ground
    (2006)
  • TPC in good shape
  • many parameters already verified and according
    to TDR specs
  • Successful transport to UX2, insertion and
    alignment into SF (Jan 07)
  • FEE re-tested after transport (Feb 07)
  • Still some hardware and software components to
    be finalized
  • TPC will be connected on the A side by June, and
    on the C side by August
  • Commissioning with calibration pulser, cosmics,
    UV laser tracks, and Krypton
  • Jul-Aug A-side only
  • Sep-Oct whole TPC
  • The TPC Collaboration is well organized to
    complete the installation and the
  • commissioning according to schedule and be
    ready for the LHC operation in Nov 07

29
Spare Slides
30
Commissioning of the Gas System
  • Features
  • ? 8 racks (CERN Gas working group)
  • ? PLC-controlled and PVSS-Unicos
  • user interface for control and
  • alarms (CERN IT-CO)
  • ? Precise detector pressure
  • regulation
  • ? Filling procedure for saving neon
  • (á la CERES)
  • Purge with CO2
  • Inject Ne while removing CO2
  • with molecular sieve Gas
  • Top-up with N2
  • ? Small fresh gas injection of
  • ternary mixture

Control Backup Mixer Purifier CO2 Distr
Analys Pump
TPC Gas System at SLXL2
31
Commissioning of the gas system
Control of Gas composition
Gas analysis with a Thermal conductivity device
Gas Chromatograph with a 'tandem' column
(premixed gas for reference)
32
Pedestal Measurments noise
before optimization of ground scheme
33
Pedestal Measurments noise
before optimization of ground scheme
34
Pedestal Measurments - baseline
busy FEC replaced on December 7th
35
Pedestal Measurments baseline
36
Pedestal Measurments baseline stability
37
Pedestal Measurments baseline stability (contd)
38
Gain Summary A side
?
?
?
39
Gain Summary C side
?
?
?
?
?
?
?
40
OROC exchange
  • Broken anode wire in OROC 00
  • Clearly caused by melting
  • It is still unclear, how this can happen
  • Studies with a test sector are ongoing
  • Mounting tool modified
  • longer lever due to presence of SSW
  • Complicated procedure, it required
  • Removing FEE and frames of full sector
  • Exchange of feet of FEE frames of neighboring
    sectors by smaller versions to allow removal of
    sealing bars
  • Remove pt1000 sensors on ROC body
  • Yellow platform in modified setup (cope with
    I-bars)
  • Exchange itself without any problems

41
ROC exchange
42
Trailer transport SXL2 to SX2
43
Trailer transport SXL2 to SX2
44
Descend to the cavern
2 hours for descent
45
TPC insertion into SF
40 cm to IP
  • Test-drive with TPC to IP
  • Align TPC, SF, ITS rail sys at IP
  • Back to parking position
  • Window of about 6 weeks
  • Check alignment SSW vs TPC
  • Re-test all FEE (all sectors)
  • Installation of beam line and ITS

at IP
46
Inside heat screen on ITS platform
Write a Comment
User Comments (0)
About PowerShow.com