Title: SSWP6 General Vision
1S_at_S-WP6- General Vision
- A.Fulfaro
- Paris Workshop 14\03\03
2-General objectives of the Presentation
- To give evidence of the FIN Safety methodological
approach - To correlate it with the aim of the project
- To underline the objectives of the applicative
tool developed in the project - To evaluate the input\output data expected in
terms of cost and alternative design solutions - using the tool (impact on breakdown structure)
3Safety FIN methodological approach
- To apply the As low as Reasonably practicable
Principle - To comply with national Health and safety
legislation - To make appropriate use of standards or when such
standards - do not exist then an acceptable cost effective
standards is to be - contrived reducing safety risk
- To apply a safety management system to ensure
that health - and safety hazards are identified, assessed and
controlled
4 Safety case
5Main relevant Hazards
- 1. Loss of the propulsion
- 2. Loss of electrical production
- 3. Loss of the HVAC system
- 4. Hardware/software
- 5. Explosion of a pressure capacity
- 6. Loss of integrity of under pressure pipes
and/or pipes carrying hazardous substances - 7. Fire/smoke
- 8. Risks associated with seamanship
activities - 9. Risks of crews intoxication
- 10. Risks concerning machines containing rolling
equipment - 11. Risks related to electrical or energy
discharges - 12. Risks related to materials
- 13. Collision
- 14. Flooding
- 15. Relevant environmental effects
- 16. Abandoning of ship.
6Safety Case Output Design measure proposition
7Safety Case Output 2 Mitigation measures\Impact
on design
Hazard
Top event
Most Likely causes
Potential Consequences
Risk Evaluation
Laws and Reg. applicable to mitigate risk
Risk control Measures
Residual risk
Mitigation measures Impact on Design
8Relevant Mitigation Measures
- When necessary, reduction measures were
identified during the PHA process. However, it
could be necessary to achieve a trade-off between
solutions to analyse the expected effectiveness
of each alternatives. Mishap risk mitigation is
an iterative process that culminates when a
residual risk has been reduced to a level
acceptable to the appropriate authority. -
- Two major reduction axes are available
-
- Reduction (elimination) of the hazardous
condition occurrence (i.e. improvement of the
failure tolerance whenever possible), - Implementation of protective devices to
reduce (eliminate) associated consequences. -
- Among the Safety solutions usually proposed as
mitigation measures one or more of the following
could be selected -
- design hazards out
- incorporate safety devices
- provide warning devices
- develop procedures and training
-
- In order to complete the process, in some cases a
verification of the mitigation measure through
appropriate analysis, testing or inspection may
be required to confirm the acceptability of the
residual risk.
9Impact on Cost
- One critical point in the previous process
- is to evaluate the real impact on Cost
- One Scope of S_at_S project
- Development and application of a formalised
safety methodology for design for safety of HSC
taking into account the impact on costs - seems to consider as relevant this aspect
10S_at_SIntegrated Tool
Tool relationship between risk and cost with a
well defined model For risk, functions and topics
adressed
WP1 Risk of Collision and grounding (risk)
To Navigate Safety of high speed (function)
Human factor\Level of automation\Manoeuvrability\E
nvironmental Condition (topics)
WP2Ship Motion risk Model for ship
motion (Function)
HF\Foundering\Structure ( Topics)
11S_at_SIntegrated Tool (2)
WP3 Foundering Structural Integrity of
the Hull girder Material properties\Structura
l strenght\building and repair cost
WP4 Containment of Damage and Fire
Safety and security of the ship
Structural insulation\Active\passive firefighting
system fire zone partition
WP5 Integration of the methodology and
validation with the current laws and
regulation
12S_at_SIntegrated Tool (3)
WP5
The system under study was a generic HSC
subdivited into 8 systems Crew General
arrengement Hull form Payload Safety
system Structure Operation Machinery
13Using the Tool
The Tool will be applied at different levels of
Design (see next Slide)in order to give the
right assessment of the critical risk parameters
evaluating their impact on the breakdown
structure at eight level as proposed in the WP5
(see for example Hull in the next slides) The
design will be modified in accordance with the
calculated level of risk and with the possible
alternative solution which could be applied on
board (the modification will involve the relavant
part of the breakdown structureHull or Machinery
for example ) A cost evaluation will guide the
final decision The goal is to optimize the Design
14Design Methodology Phases
- four phases summarised as follows
- 1.Preliminary Design
- 2.Basic Design
- 3.Functional design
- 4.Detailed Design
151.Preliminary Design
- Phase of Feasability in which the main ship
characteristics function of what is realizable
are defined taking into account also the Owners
request
161.Key Parameters (KP)
- Loading Capacity
- Velocity
- Autonomy
- Than If there is a specific request
- High Comfort ( which could influence for example
the level of Noise on board)
171. MOP (Management of Performances)
- Alternative Design solutions are evaluated in
order to define the optimal configuration
182.Basic Design
- General project is defined with is own
dimensional and functional characteristics
such - Dimensions of the Ship (KP.ship geometry)
- Preliminary General Displacement
(KP.autonomy/speed linked to fuel on board) - Oss Autonomy is connected with payload which is
generally fixed . - Preliminary General arrangment Plan (KP.
Displacement linked to the systems
architecture.The variables are ship dimension
and number of deck)
19Basic Design 2
- Preliminary Arrangement (for Engine room for
istance). (KP. speed (tempi di imbarco e sbarco)
and safety (escape routes, life savings..) - Preliminary layout drawings (for Propulsion
system for istance). (K.P. architecture of
systems (type of engine with its own technical
characteristics) - Midship section. (K.P. Cost, Type of material)
20Key factors
- Dimensions
- Velocity
- Power
- General Arrangement
213.Functional design
- A more complete level of detail in which for
example the general arrangment of Engine room
contains all the systems described in detail (if
we consider the cooling system the pumps with
their loading capacity or the piping with their
size are described for example) - Structural drawings are ready for Register
approval - (during Basic Design only Midship section is
ready for approval for istance) - There are no informations about the real location
of all the systems with their own components on
board
224.Detailed Design
- All the Drawings will be completed by evaluating
the sequence of cutting and welding or the right
piping design for example (Structural Drawings) - the so called Coordinate Plans (Detailed
Drawings of pipes,cables..) are completed in
order to define the exact position on board of
all the equipment and to evaluate (for istance)
if there are space interference among systems,
piping,equipment and so on
23MDV 1200 Table of Contents
- General
- Hull Structure
- Propulsion Plant
- Electric Plant
- Command and Surveillance
- Auxiliary Systems
- Outfit and Furnishing
24General
- Ships main characteristics are described like
dimensions, number of passengers\crew\cars,
deadweight (max), maximum continuous\service
speed,average fuel consumption, propulsion
description,environmental conditions - Project general concepts are described (see tech
specif.) - Deadweight capacity,tank capacity,weight
list,performances (speed, seakeeping) noise
levels, vibration and vibration
strengthenings,Stability and pre-selected Test
\Trials informations are given
25Hull
- Informations about
- Scantling,Materials,welding and structural
connections - Externall shell Plating
- Watertight bulkheads
- Decks\superstructures
- Foundations
- are given
26Propulsion Plant
- General informations
- Informations about Propulsion Units,Transmission
and Propulsion System, Propulsion Support
Systems, PMS, Sea Water system,Fuel oil system
and so on - are given
27Electrical Plant
- General
- Electric system configuration
- Protection and Distribution System
- Electric motors and Starters
- Electric Cables
- Generators
- Accumulator Battery
- Power Distribution System
- Lighting System
28Conclusion
- The Tool should be used first of all during
- the Basic Design phase
- and then
- in the other Design phases to
- evaluate the alternative design Solutions