Title: FINANCING ISSUES INVOLVED
1FINANCING ISSUES INVOLVED IN DEVELOPMENT OF
HYDRO POTENTIAL S.D.Dubey,
Director,CEA
P.K.Shukla,
Dy.Director,CEA
2HYDRO SCENARIO IN INDIA
3HYDRO POTENTIAL DEVELOPMENT AT A GLANCE
4(No Transcript)
5VISION FOR HYDRO POWER DEVELOPMENT
- Plan to develop the balance potential by the end
of 14th Plan i.e. by 2026-27 - For development of entire potential , over Rs.
5,00,000 crores would be required. - Survey Investigation activities of all
identified projects would need to be completed by
the end of 12th Plan i.e. by 2016-17. - Completion of Survey Investigation activities
would involve an expenditure of over Rs. 5000
Crs.
6VISION FOR HYDRO POWER DEVELOPMENT
7FUNDS REQUIRED FOR HYDRO CAPACITY ADDITION
8ADVANTAGES OF HYDRO POWER
- RENEWABLE, ECONOMIC AND NON POLLUTING SOURCE
OF ENERGY - PROMOTES CONSERVATION OF NON-RENEWABLE FOSSIL
FUEL - ENVIRONMENTAL FRIENDLY AND DOES NOT ADD TO GREEN
HOUSE EFFECT AND PROBLEMS OF SOLID WASTE DISPOSAL - ABILITY FOR INSTANTANEOUS STARTING, STOPPING AND
LOAD VARIATION THEREBY IDEALLY SUITED FOR
PEAKING OPERATION - LONGER USEFUL LIFE SPAN
- IMPROVES RELIABILITY OF POWER SYSTEM
9ADVANTAGES OF HYDRO POWER
- NO FUEL COST DURING THE LIFE OF THE STATION AND
THUS REMAINS ESCALATION FREE - EMERGES TO BE CHEAPEST SOURCE OF POWER IN LONG
RUN - ACCRUAL OF INCIDENTAL BENEFITS OF
DEVELOPMENT OF ROAD/ RAIL COMMUNICATION,
ELECTRIFICATION, INDUSTRIALIZATION IN THE
AREA OF HYDRO PROJECTS - IMPROVEMENT OF THE QUALITY OF LIFE OF THE
REMOTE HILLY AND BACKWARD AREA - STORAGE PROJECTS PROVIDE FLOOD CONTROL,
IRRIGATION, DRINKING WATER SUPPLY, RECREATION
FACILITIES ETC AND THUS HELP IN THE MAXIMUM
UTILIZATION OF OUR SCARCE WATER RESOURCES
10ISSUES INVOLVED IN HYDRO POWER DEVELOPMENT
- LAND ACQUISITION PROBLEMS
- RESETTLEMENT REHABILITATION PROBLEMS
- ENVIRONMENT AND FOREST ISSUES
- GEOLOGICAL SURPRISES
- INTER-STATE ASPECTS
- PAUCITY OF FUNDS AND LONGER GESTATION PERIOD
- LAW ORDER PROBLEMS
11ISSUES INVOLVED IN HYDRO POWER DEVELOPMENT
- APPORTIONMENT OF PROJECT COST AMONG VARIOUS
AGENCIES - EXORBITANT CALCULATIONS OF NET PRESENT VALUE
(NPV) - ENSURING OPTIMUM DEVELOPMENT AND SAFETY ASPECTS
- ALLOCATION OF PROJECTS FOR DEVELOPMENT
- STORAGE VS. R-O-R PROJECTS
12Land Acquisition Problems
- The problems arising in acquisition of land for
hydro- electric project construction are causing
suspension and delay in the construction
activities. - This problem may be minimized with the
co-operation of concerned state Govts.
13Resettlement And Rehabilitation Issues
- The progress of some of the projects has been
severely affected on account of opposition to the
construction by environmentalists and project
affected people. - -Sardar Sarover,
- - Indira Sagar,
- - Bansagar Tons
- - Tehri
- These are some of the hydro projects where the
progress has/ is being severely hampered from
sustained opposition to project construction. - R R is becoming a major issue in the
implementation of storage-based hydro
development. - Many times, it is one of the main reasons for the
delay in the execution resulting in Time Cost
Over-runs
14 Issues Related to Environment And Forest
- The progress of some of the projects has
been affected on account of delay/non-clearance
from Environment and Forest aspects. - Hydro electric projects involve submergence
causing displacement of project area people and
often require forest land for their
implementation. - The impact on ecology, monuments, seismicity,
resettlement and rehabilitation, catchment
area treatment, flora and fauna are assessed in
the environment appraisal of the project.
Forest clearance requires compensatory
afforestation on the non forest lands. - These aspects need to be looked into carefully to
avoid undue problems during execution of the
projects.
15Geological Surprises
- The features of the hydro electric projects,
being site specific, depend on the geology,
topography and hydrology at the site. The
construction time of a hydro project is greatly
influenced by the geology of the area and its
accessibility. - It is, therefore, essential that state-of-the-art
investigation and construction techniques are
adopted to minimise geological risks as well as
the overall gestation period of hydel projects. - Even if, extensive investigation using new
techniques of investigations, are undertaken
an element of uncertainty remains in the
sub-surface geology and the geological surprises
during actual construction can not be ruled out.
16Inter State Issues
- A substantial hydel power potential has remained
locked up and many mega hydel projects could not
be taken up , even though these projects are well
recognized as attractive and viable, because of
unresolved Inter-State issues. - At present 34 hydro electric projects (6810 MW)
are held up because of various interstate
disputes. - Govt. of India recognizes the need for evolving
an approach to ensure that the available
hydro-electric potential is fully utilized
without prejudice to the rights of the riparian
States as determined by the Awards of the
Tribunals/ Agreements arrived at among the party
States for a given river basin with regard to
water sharing. - A consensus would need to be evolved amongst
the basin states regarding the location of such
project, basic parameters involved and mechanism
through which each project would be constructed
and operated.
17Paucity of Funds and Longer Gestation Period
- Paucity of funds in the past has been the major
cause of slow hydro development. - There has been the reluctance of FIs to fund
these projects given the risks of geological and
hydrological uncertainties, delays in land
acquisitions, rehabilitation and resettlement
problems, law and order problems and poor
communications in addition to the general
problems of IPPs like payment security etc. - The thermal projects used to get priority in fund
allotments with a view to get early benefits, as
the gestation period of thermal plants is
comparatively short.
18Law and Order Problems
- Disturbed condition in some part of the country
is one of the factors causing delay in project
execution and even suspension of work. Some of
the hydro-electric projects suffering due to
these problems are - Dulhasti
- Upper Sindh
- Dhansiri
- Tuirial
- Gundia,Agnashini,Gangavali and Kalinadi stage-III
etc.
19Apportionment of Project Cost Among Various
Agencies/States
- Efforts need to be made to evolve consensus for
apportioning the costs , among various Agencies
on account of extra security charges, additional
cost on flood moderation, irrigation, drinking
water, infrastructure (access roads) development
etc. - Approx. 37 of hydro potential is concentrated in
North Eastern region of the country, where demand
of power is quite low as compared to the
available potential. The major chunk of power
would be required to be transmitted to other
states.This would necessitate cost sharing among
various beneficiaries. - Large Storage Projects developed in the higher
reaches of river give benefits to the projects
downstream and there should be apportionment of
project cost among all the beneficiaries.
20Exorbitant Net Present Value (NPV)
- Excessive burden of NPV - Based on the Supreme
Courts orders, MoEF vide letter dated 18.9.03
has issued guidelines for collection of NPV
(_at_Rs.5.80 lacs to Rs.9.20 lacs per ha. depending
upon the quantity and density of forest land
involved). - This even covers land with no vegetation at all
like river bed etc. Moreover, this is in addition
to, payment of compensatory Afforestation for
double the area of forest land diverted for the
project, catchment area treatment, the value of
the timber standing on the land to be inundated
by the reservoir which is credited to the State
Forest Department etc. - Loading of NPV on the project would result in
increase in tariff of hydro-electricity. e.g. in
the Tipaimukh Project the NPV has resulted in an
increase in the cost of the project by over
Rs.1000 crores i.e. over 20 increase in the
project cost.
21Ensuring Optimum Development And Safety Aspects
- As per Section 8 (1) of Electricity Act, 2003 the
generating company intending to setup a hydro
generating station shall prepare and submit to
Authority for its concurrence, a scheme estimated
to involve a capital expenditure exceeding such
sum, as may be fixed by the Govt. from time to
time by notification. - During concurrence by CEA, the following concerns
get addressed. - Optimal development of the projects in the river
- Optimum design of project to get maximum power
- Civil designs incorporating safety aspects
- Adherence to inter-State water regulation
/allocation - Tying up of all inputs for development of the
schemes including transmission aspects,
MOEF clearance etc. - Determining of capital cost which becomes the
basis for tariff fixation by Regulators etc. - The above requirements would need to be ensured
whether concurrence of CEA is required or not.
22Allocation of Projects
- Allocation of hydro projects are within the
domain of respective States - Their concern lies with maximisation of their
return by way of free power/equity return in the
project. - Presently, free power is fixed at a maximum of
12 and return of equity fixed at 14 for
projects that come under the regulatory regime.
23Allocation of Projects
- States are following different models for
allocation of hydro projects to Private
developers. - While some states are allocating projects on the
basis of per MW upfront payment to the state and
additional free power over and above 12 . - Others are making allocation on the basis of
equity participation to the state at the cost of
the developer and additional free power over
and above 12 . - Many States are allocating projects to developers
with conditions that the project should revert
back to the State after periods varying from 15
to 45 years.
24Storage Vs. R-O-R Projects
- There is a lot of controversy in the
development of Hydro Projects as Storage or
R-O-R . - The development of a Storage scheme involve huge
complexities in issus like land acquisition,
rehabilitation, environment concerns , water
management etc, and most of the available sites
for storage schemes are located in the Hill
states, whereas the downstream benefits of flood
control, drinking water, irrigation etc. become
available to the states in the plains.
25Storage Vs. R-O-R Projects
- Thus, most of the distress caused by storage
schemes occur in the Hill states whereas the
benefits are largely in the states in the plains
which are perceived to be more prosperous. - Therefore , Hill states prefer R-O-R schemes and
there is a move by states like Arunachal Pradesh
to convert identified storage schemes to R-O-R,
which is not desirable keeping the larger
interest of the country in view. - The type (Storage/ROR) of a hydro project depends
upon the topography, geology and hydrology of the
area and is site specific. The storage sites in
the country are limited and hence their optimum
development would need to be ensured .
26FINANCING ISSUES INVOLVED IN DEVELOPMENT OF
HYDRO POTENTIAL
- Developing Appropriate Funding Strategies
- Providing Longer Tenure Loans
- Rationalisation of Hydro Tariff
- Promoting Small and Mini Hydel Projects
- Mega Power Projects Policy
27Developing Appropriate Funding Strategies
- Power being most crucial infrastructure, public
sector investments, both at the Central
Government and State Governments, will have to
be stepped up. Considering the magnitude of the
expansion of the sector required, a sizeable part
of the investments will also need to be brought
in from the private sector . - The Electricity Act, 2003 creates a conductive
environment for investments in all segments of
the industry, both for public sector and private
sector by removing barrier to entry in different
segments. Section 63 of the Act provides for
participation of suppliers on competitive basis
in different segments, which will further
encourage private sector investment.
28Providing Longer Tenure Loans
- A special requirement of hydel projects is the
availability of long term funding at reasonable
interest rates for back ending of tariffs so that
the cost of power during the initial years is
reasonable. - The FIs perceive a lower payment security risk if
the first year tariff is reasonable and are
reluctant to fund project with high first year
tariff even if it is demonstrated that the tariff
would be reasonable in the later years . - The minimum tenure of PPAs should be atleast 25
years. Institutions like the Power Finance
Corporation have developed special schemes for
funding hydro projects with tenures of upto 25
years to address this concern.This would ensure
equitable benefits to flow to the lenders,
consumers at large and reasonable returns to the
developers.
29Rationalisation of Hydro Tariff
- The hydro projects involve longer gestation
period, difficult approach and construction of
large infrastructure development etc. There is a
need to reformulate the principles on the basis
of which tariff is determined for hydel
generation . - Recognising the difficulties in execution of
hydro projects, the Government has decided to
rationalize the existing hydro tariff norms,
improve the incentives for better operation and
evolve a solution to the contentious issue of
computing the completing cost in the face of
geological uncertainties and surprises and
natural incidents of rock slide etc. - Recognising the problems in operation of hydro
power stations in the initial years especially in
project with silt laden water, the normative
availability factor has been reduced from 90 to
85. Further the rate for secondary energy has
been made equal to rate for Primary energy. - Review of Design Energy by CEA every five years.
30Providing Longer Tenure Loans
- Encouraged by the provisions of the Electricity
Act, 2003, the financial institutions are no
longer looking for Government guarantees and
have reiterated that there would be no dearth of
fund for projects with viable tariffs promoted by
credible developers. - An inter-institutional group (IIG) with the MD,
SBI as its convener and representatives from
other financial institutions and the Ministry of
Power has been constituted to facilitate
financial closure of private sector power
projects. - .
31Promoting Small and Mini Hydel Projects
- Ministry of Non-Conventional Energy Sources
(MNES) has been vested with all matters related
to Small Hydel Projects (up to 25 MW capacity).
These projects are being provided with the
following incentives . - Incentives for detailed survey investigation
and preparation of DPR. - Incentives during the execution of the project in
the form of capital/interest subsidy. - Special incentives for execution of small hydro
projects in the North Eastern Region by the
Government departments/SEB/State agencies. - Financial support for renovation and
modernization and uprating of old small hydro
power stations . - .
32Mega Power Projects Policy
- Revised in May2006.
- Keeping in view the requirements of power
projects located in certain special category
States of JK, Sikkim and the seven states of
North East, the minimum qualifying capacity of
hydro power plants for availing mega benefits has
been reduced from 500 MW to 350 MW..
33Mega Power Projects Policy
- The following are the Fiscal concessions/benefits
available to Mega Power Projects - Import of capital equipment free of customs duty.
- Deemed export benefits as per the Foreign Trade
Policy to domestic bidders. - Income Tax holiday regime as per section 80-IA of
the Income Tax Act,1961. - Price Preference of 15 to domestic PSUs bidders.
34CONCLUSION
- The changes now brought about in Mega Power
Policy will facilitate setting up of Mega Power
Plants in the country and the special category
states of North-East including Sikkim and Jammu
Kashmir. - Inter-Institutional Group (IIG) with the MD, SBI
as its convener and representatives from other
financial institutions and the Ministry of Power
is likely to facilitate financial closure of
private sector power projects .
35CONCLUSION
- In view of the huge complexities involved in
storage schemes ,the involvement of public sector
in hydel projects particularly in storage
projects would have to be enlarged. - The IPPs may be allotted simpler/R-O-R schemes.
- The hydro projects should be allocated by the
States on tariff based competitive bidding based
on the quality DPRs to ensure that the inherent
low tariff benefit of hydro resource is captured
and passed on to the consumers.
36CONCLUSION
- There is an urgent need to formulate long term
strategy for harnessing the balance 75 untapped
potential of the country. - In order to develop the balance potential by the
end of 14th Plan ( 2026-27) , Survey
Investigation activities would need to be
completed by the end of 12th Plan i.e. by 2016-17
- Storage reservoir schemes with flood control and
other benefits must be taken up for development
keeping in view the overall requirement of the
country.
37Thank you!