FINANCING ISSUES INVOLVED - PowerPoint PPT Presentation

1 / 37
About This Presentation
Title:

FINANCING ISSUES INVOLVED

Description:

Plan to develop the balance potential by the end of 14th Plan i.e. by 2026-27 ... on ecology, monuments, seismicity, resettlement and rehabilitation, catchment ... – PowerPoint PPT presentation

Number of Views:94
Avg rating:3.0/5.0
Slides: 38
Provided by: mem8
Category:

less

Transcript and Presenter's Notes

Title: FINANCING ISSUES INVOLVED


1
FINANCING ISSUES INVOLVED IN DEVELOPMENT OF
HYDRO POTENTIAL S.D.Dubey,
Director,CEA
P.K.Shukla,

Dy.Director,CEA
2
HYDRO SCENARIO IN INDIA
3
HYDRO POTENTIAL DEVELOPMENT AT A GLANCE
4
(No Transcript)
5
VISION FOR HYDRO POWER DEVELOPMENT
  • Plan to develop the balance potential by the end
    of 14th Plan i.e. by 2026-27
  • For development of entire potential , over Rs.
    5,00,000 crores would be required.
  • Survey Investigation activities of all
    identified projects would need to be completed by
    the end of 12th Plan i.e. by 2016-17.
  • Completion of Survey Investigation activities
    would involve an expenditure of over Rs. 5000
    Crs.

6
VISION FOR HYDRO POWER DEVELOPMENT
7
FUNDS REQUIRED FOR HYDRO CAPACITY ADDITION
8
ADVANTAGES OF HYDRO POWER
  • RENEWABLE, ECONOMIC AND NON POLLUTING SOURCE
    OF ENERGY
  • PROMOTES CONSERVATION OF NON-RENEWABLE FOSSIL
    FUEL
  • ENVIRONMENTAL FRIENDLY AND DOES NOT ADD TO GREEN
    HOUSE EFFECT AND PROBLEMS OF SOLID WASTE DISPOSAL
  • ABILITY FOR INSTANTANEOUS STARTING, STOPPING AND
    LOAD VARIATION THEREBY IDEALLY SUITED FOR
    PEAKING OPERATION
  • LONGER USEFUL LIFE SPAN
  • IMPROVES RELIABILITY OF POWER SYSTEM

9
ADVANTAGES OF HYDRO POWER
  • NO FUEL COST DURING THE LIFE OF THE STATION AND
    THUS REMAINS ESCALATION FREE
  • EMERGES TO BE CHEAPEST SOURCE OF POWER IN LONG
    RUN
  • ACCRUAL OF INCIDENTAL BENEFITS OF
    DEVELOPMENT OF ROAD/ RAIL COMMUNICATION,
    ELECTRIFICATION, INDUSTRIALIZATION IN THE
    AREA OF HYDRO PROJECTS
  • IMPROVEMENT OF THE QUALITY OF LIFE OF THE
    REMOTE HILLY AND BACKWARD AREA
  • STORAGE PROJECTS PROVIDE FLOOD CONTROL,
    IRRIGATION, DRINKING WATER SUPPLY, RECREATION
    FACILITIES ETC AND THUS HELP IN THE MAXIMUM
    UTILIZATION OF OUR SCARCE WATER RESOURCES

10
ISSUES INVOLVED IN HYDRO POWER DEVELOPMENT
  • LAND ACQUISITION PROBLEMS
  • RESETTLEMENT REHABILITATION PROBLEMS
  • ENVIRONMENT AND FOREST ISSUES
  • GEOLOGICAL SURPRISES
  • INTER-STATE ASPECTS
  • PAUCITY OF FUNDS AND LONGER GESTATION PERIOD
  • LAW ORDER PROBLEMS

11
ISSUES INVOLVED IN HYDRO POWER DEVELOPMENT
  • APPORTIONMENT OF PROJECT COST AMONG VARIOUS
    AGENCIES
  • EXORBITANT CALCULATIONS OF NET PRESENT VALUE
    (NPV)
  • ENSURING OPTIMUM DEVELOPMENT AND SAFETY ASPECTS
  • ALLOCATION OF PROJECTS FOR DEVELOPMENT
  • STORAGE VS. R-O-R PROJECTS

12
Land Acquisition Problems
  • The problems arising in acquisition of land for
    hydro- electric project construction are causing
    suspension and delay in the construction
    activities.
  • This problem may be minimized with the
    co-operation of concerned state Govts.

13
Resettlement And Rehabilitation Issues
  • The progress of some of the projects has been
    severely affected on account of opposition to the
    construction by environmentalists and project
    affected people.
  • -Sardar Sarover,
  • - Indira Sagar,
  • - Bansagar Tons
  • - Tehri
  • These are some of the hydro projects where the
    progress has/ is being severely hampered from
    sustained opposition to project construction.
  • R R is becoming a major issue in the
    implementation of storage-based hydro
    development.
  • Many times, it is one of the main reasons for the
    delay in the execution resulting in Time Cost
    Over-runs

14
Issues Related to Environment And Forest
  • The progress of some of the projects has
    been affected on account of delay/non-clearance
    from Environment and Forest aspects.
  • Hydro electric projects involve submergence
    causing displacement of project area people and
    often require forest land for their
    implementation.
  • The impact on ecology, monuments, seismicity,
    resettlement and rehabilitation, catchment
    area treatment, flora and fauna are assessed in
    the environment appraisal of the project.
    Forest clearance requires compensatory
    afforestation on the non forest lands.
  • These aspects need to be looked into carefully to
    avoid undue problems during execution of the
    projects.

15
Geological Surprises
  • The features of the hydro electric projects,
    being site specific, depend on the geology,
    topography and hydrology at the site. The
    construction time of a hydro project is greatly
    influenced by the geology of the area and its
    accessibility.
  • It is, therefore, essential that state-of-the-art
    investigation and construction techniques are
    adopted to minimise geological risks as well as
    the overall gestation period of hydel projects.
  • Even if, extensive investigation using new
    techniques of investigations, are undertaken
    an element of uncertainty remains in the
    sub-surface geology and the geological surprises
    during actual construction can not be ruled out.

16
Inter State Issues
  • A substantial hydel power potential has remained
    locked up and many mega hydel projects could not
    be taken up , even though these projects are well
    recognized as attractive and viable, because of
    unresolved Inter-State issues.
  • At present 34 hydro electric projects (6810 MW)
    are held up because of various interstate
    disputes.
  • Govt. of India recognizes the need for evolving
    an approach to ensure that the available
    hydro-electric potential is fully utilized
    without prejudice to the rights of the riparian
    States as determined by the Awards of the
    Tribunals/ Agreements arrived at among the party
    States for a given river basin with regard to
    water sharing.
  • A consensus would need to be evolved amongst
    the basin states regarding the location of such
    project, basic parameters involved and mechanism
    through which each project would be constructed
    and operated.

17
Paucity of Funds and Longer Gestation Period
  • Paucity of funds in the past has been the major
    cause of slow hydro development.
  • There has been the reluctance of FIs to fund
    these projects given the risks of geological and
    hydrological uncertainties, delays in land
    acquisitions, rehabilitation and resettlement
    problems, law and order problems and poor
    communications in addition to the general
    problems of IPPs like payment security etc.
  • The thermal projects used to get priority in fund
    allotments with a view to get early benefits, as
    the gestation period of thermal plants is
    comparatively short.

18
Law and Order Problems
  • Disturbed condition in some part of the country
    is one of the factors causing delay in project
    execution and even suspension of work. Some of
    the hydro-electric projects suffering due to
    these problems are
  • Dulhasti
  • Upper Sindh
  • Dhansiri
  • Tuirial
  • Gundia,Agnashini,Gangavali and Kalinadi stage-III
    etc.

19
Apportionment of Project Cost Among Various
Agencies/States
  • Efforts need to be made to evolve consensus for
    apportioning the costs , among various Agencies
    on account of extra security charges, additional
    cost on flood moderation, irrigation, drinking
    water, infrastructure (access roads) development
    etc.
  • Approx. 37 of hydro potential is concentrated in
    North Eastern region of the country, where demand
    of power is quite low as compared to the
    available potential. The major chunk of power
    would be required to be transmitted to other
    states.This would necessitate cost sharing among
    various beneficiaries.
  • Large Storage Projects developed in the higher
    reaches of river give benefits to the projects
    downstream and there should be apportionment of
    project cost among all the beneficiaries.

20
Exorbitant Net Present Value (NPV)
  • Excessive burden of NPV - Based on the Supreme
    Courts orders, MoEF vide letter dated 18.9.03
    has issued guidelines for collection of NPV
    (_at_Rs.5.80 lacs to Rs.9.20 lacs per ha. depending
    upon the quantity and density of forest land
    involved).
  • This even covers land with no vegetation at all
    like river bed etc. Moreover, this is in addition
    to, payment of compensatory Afforestation for
    double the area of forest land diverted for the
    project, catchment area treatment, the value of
    the timber standing on the land to be inundated
    by the reservoir which is credited to the State
    Forest Department etc.
  • Loading of NPV on the project would result in
    increase in tariff of hydro-electricity. e.g. in
    the Tipaimukh Project the NPV has resulted in an
    increase in the cost of the project by over
    Rs.1000 crores i.e. over 20 increase in the
    project cost.

21
Ensuring Optimum Development And Safety Aspects
  • As per Section 8 (1) of Electricity Act, 2003 the
    generating company intending to setup a hydro
    generating station shall prepare and submit to
    Authority for its concurrence, a scheme estimated
    to involve a capital expenditure exceeding such
    sum, as may be fixed by the Govt. from time to
    time by notification.
  • During concurrence by CEA, the following concerns
    get addressed.
  • Optimal development of the projects in the river
  • Optimum design of project to get maximum power
  • Civil designs incorporating safety aspects
  • Adherence to inter-State water regulation
    /allocation
  • Tying up of all inputs for development of the
    schemes including transmission aspects,
    MOEF clearance etc.
  • Determining of capital cost which becomes the
    basis for tariff fixation by Regulators etc.
  • The above requirements would need to be ensured
    whether concurrence of CEA is required or not.

22
Allocation of Projects
  • Allocation of hydro projects are within the
    domain of respective States
  • Their concern lies with maximisation of their
    return by way of free power/equity return in the
    project.
  • Presently, free power is fixed at a maximum of
    12 and return of equity fixed at 14 for
    projects that come under the regulatory regime.

23
Allocation of Projects
  • States are following different models for
    allocation of hydro projects to Private
    developers.
  • While some states are allocating projects on the
    basis of per MW upfront payment to the state and
    additional free power over and above 12 .
  • Others are making allocation on the basis of
    equity participation to the state at the cost of
    the developer and additional free power over
    and above 12 .
  • Many States are allocating projects to developers
    with conditions that the project should revert
    back to the State after periods varying from 15
    to 45 years.

24
Storage Vs. R-O-R Projects
  • There is a lot of controversy in the
    development of Hydro Projects as Storage or
    R-O-R .
  • The development of a Storage scheme involve huge
    complexities in issus like land acquisition,
    rehabilitation, environment concerns , water
    management etc, and most of the available sites
    for storage schemes are located in the Hill
    states, whereas the downstream benefits of flood
    control, drinking water, irrigation etc. become
    available to the states in the plains.

25
Storage Vs. R-O-R Projects
  • Thus, most of the distress caused by storage
    schemes occur in the Hill states whereas the
    benefits are largely in the states in the plains
    which are perceived to be more prosperous.
  • Therefore , Hill states prefer R-O-R schemes and
    there is a move by states like Arunachal Pradesh
    to convert identified storage schemes to R-O-R,
    which is not desirable keeping the larger
    interest of the country in view.
  • The type (Storage/ROR) of a hydro project depends
    upon the topography, geology and hydrology of the
    area and is site specific. The storage sites in
    the country are limited and hence their optimum
    development would need to be ensured .

26
FINANCING ISSUES INVOLVED IN DEVELOPMENT OF
HYDRO POTENTIAL
  • Developing Appropriate Funding Strategies
  • Providing Longer Tenure Loans
  • Rationalisation of Hydro Tariff
  • Promoting Small and Mini Hydel Projects
  • Mega Power Projects Policy

27
Developing Appropriate Funding Strategies
  • Power being most crucial infrastructure, public
    sector investments, both at the Central
    Government and State Governments, will have to
    be stepped up. Considering the magnitude of the
    expansion of the sector required, a sizeable part
    of the investments will also need to be brought
    in from the private sector .
  • The Electricity Act, 2003 creates a conductive
    environment for investments in all segments of
    the industry, both for public sector and private
    sector by removing barrier to entry in different
    segments. Section 63 of the Act provides for
    participation of suppliers on competitive basis
    in different segments, which will further
    encourage private sector investment.

28
Providing Longer Tenure Loans
  • A special requirement of hydel projects is the
    availability of long term funding at reasonable
    interest rates for back ending of tariffs so that
    the cost of power during the initial years is
    reasonable.
  • The FIs perceive a lower payment security risk if
    the first year tariff is reasonable and are
    reluctant to fund project with high first year
    tariff even if it is demonstrated that the tariff
    would be reasonable in the later years .
  • The minimum tenure of PPAs should be atleast 25
    years. Institutions like the Power Finance
    Corporation have developed special schemes for
    funding hydro projects with tenures of upto 25
    years to address this concern.This would ensure
    equitable benefits to flow to the lenders,
    consumers at large and reasonable returns to the
    developers.

29
Rationalisation of Hydro Tariff
  • The hydro projects involve longer gestation
    period, difficult approach and construction of
    large infrastructure development etc. There is a
    need to reformulate the principles on the basis
    of which tariff is determined for hydel
    generation .
  • Recognising the difficulties in execution of
    hydro projects, the Government has decided to
    rationalize the existing hydro tariff norms,
    improve the incentives for better operation and
    evolve a solution to the contentious issue of
    computing the completing cost in the face of
    geological uncertainties and surprises and
    natural incidents of rock slide etc.
  • Recognising the problems in operation of hydro
    power stations in the initial years especially in
    project with silt laden water, the normative
    availability factor has been reduced from 90 to
    85. Further the rate for secondary energy has
    been made equal to rate for Primary energy.
  • Review of Design Energy by CEA every five years.

30
Providing Longer Tenure Loans
  • Encouraged by the provisions of the Electricity
    Act, 2003, the financial institutions are no
    longer looking for Government guarantees and
    have reiterated that there would be no dearth of
    fund for projects with viable tariffs promoted by
    credible developers.
  • An inter-institutional group (IIG) with the MD,
    SBI as its convener and representatives from
    other financial institutions and the Ministry of
    Power has been constituted to facilitate
    financial closure of private sector power
    projects.
  • .

31
Promoting Small and Mini Hydel Projects
  • Ministry of Non-Conventional Energy Sources
    (MNES) has been vested with all matters related
    to Small Hydel Projects (up to 25 MW capacity).
    These projects are being provided with the
    following incentives .
  • Incentives for detailed survey investigation
    and preparation of DPR.
  • Incentives during the execution of the project in
    the form of capital/interest subsidy.
  • Special incentives for execution of small hydro
    projects in the North Eastern Region by the
    Government departments/SEB/State agencies.
  • Financial support for renovation and
    modernization and uprating of old small hydro
    power stations .
  • .

32
Mega Power Projects Policy
  • Revised in May2006.
  • Keeping in view the requirements of power
    projects located in certain special category
    States of JK, Sikkim and the seven states of
    North East, the minimum qualifying capacity of
    hydro power plants for availing mega benefits has
    been reduced from 500 MW to 350 MW..

33
Mega Power Projects Policy
  • The following are the Fiscal concessions/benefits
    available to Mega Power Projects
  • Import of capital equipment free of customs duty.
  • Deemed export benefits as per the Foreign Trade
    Policy to domestic bidders.
  • Income Tax holiday regime as per section 80-IA of
    the Income Tax Act,1961.
  • Price Preference of 15 to domestic PSUs bidders.

34
CONCLUSION
  • The changes now brought about in Mega Power
    Policy will facilitate setting up of Mega Power
    Plants in the country and the special category
    states of North-East including Sikkim and Jammu
    Kashmir.
  • Inter-Institutional Group (IIG) with the MD, SBI
    as its convener and representatives from other
    financial institutions and the Ministry of Power
    is likely to facilitate financial closure of
    private sector power projects .

35
CONCLUSION
  • In view of the huge complexities involved in
    storage schemes ,the involvement of public sector
    in hydel projects particularly in storage
    projects would have to be enlarged.
  • The IPPs may be allotted simpler/R-O-R schemes.
  • The hydro projects should be allocated by the
    States on tariff based competitive bidding based
    on the quality DPRs to ensure that the inherent
    low tariff benefit of hydro resource is captured
    and passed on to the consumers.

36
CONCLUSION
  • There is an urgent need to formulate long term
    strategy for harnessing the balance 75 untapped
    potential of the country.
  • In order to develop the balance potential by the
    end of 14th Plan ( 2026-27) , Survey
    Investigation activities would need to be
    completed by the end of 12th Plan i.e. by 2016-17
  • Storage reservoir schemes with flood control and
    other benefits must be taken up for development
    keeping in view the overall requirement of the
    country.

37
Thank you!
Write a Comment
User Comments (0)
About PowerShow.com