Beam Delivery Cost Estimate - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Beam Delivery Cost Estimate

Description:

NLC - The Next Linear Collider Project ** Site layout options due to new Energy ... to contiguous BLOCKS of BENDS separated from other blocks by a quad or sext ... – PowerPoint PPT presentation

Number of Views:90
Avg rating:3.0/5.0
Slides: 13
Provided by: ThomasWMa9
Category:
Tags: beam | cost | delivery | estimate | sext

less

Transcript and Presenter's Notes

Title: Beam Delivery Cost Estimate


1
Beam DeliveryCost Estimate
  • T. Markiewicz
  • 1 June 2000

2
Site layout options due to new Energy
Collimation under discussion
3
Caveats
  • Costs are the hardware to deliver beam to one IP
  • Conventional facilities provide tunnels for two
    IPs
  • Costs estimated in 1999 were never scrutinized
  • No tops-down reality checks have been applied
  • 2000 acquisition costs are taken from 1999
    numbers scaled by current part counts or lengths
  • 2000 EDI model is best estimate of area
    engineer
  • Leif Eriksson
  • Lattices are new
  • low energy operational limit (magnet bore) not
    yet specified
  • only one iteration on diagnostic and tuning
    elements
  • system not yet mature enough for a value
    engineering optimization

4
Technical Changes Relative to 1999
  • NOT included in cost estimate
  • Magnet Stringing
  • All magnets in same geographic area that are of
    the same type and have the same pole-tip field
    are strung
  • ADDITIONAL (BEND) stringing possible once
    engineering model allows for different coil
    windings in the same magnet core.
  • Trim Supplies Added
  • to individual QUADS in a stringI
  • to contiguous BLOCKS of BENDS separated from
    other blocks by a quad or sext
  • Tunnel Electronic Enclosures
  • when permissible need radiation estimates
  • Included in current cost estimate
  • Stainless Steel Vacuum System
  • BUT placement rules have not changed to reflect
    new apertures

5
Lattice Length Changes (m)
6
Parts Counts by Family (One IR Only)
7
EDI Methodology
  • Either
  • Estimate Standing Army needed for given task for
    period given by straw-man schedule. Examples
  • Systems Engineering 7 people, 9
    years
  • Conceptual Design 41 people, 2 years
  • Vacuum Sustaining Engineering 1 person, 6
    years
  • Make grounds up estimate for a hardware system
    and slice it into WBS buckets using a formula.
    Ex Magnet EDI 18.5M
  • RD 10
  • Design 50
  • Sustaining Engineering 15
  • Assess MS for computers, travel,
    5k/person/year

8
Acquisition Methodology
  • Magnets Systems Magnets, PS, Cables, BPMs,
    Supports, Movers
  • Grounds up estimates of hours/materials _at_ SLAC
    shops
  • Inflate by 40 for vendor profit
  • Vacuum
  • Catalog prices
  • No volume discount
  • Collimators, Dumps, Instrumentation
  • Assume build at a DOE lab
  • Grounds up estimates of hours/materials _at_ SLAC
    shops

9
Beam Delivery 5/18/00 Estimate179.6M
10
Comparison to 1999 Estimate
11
Engineering Savings 66
12
Summary
  • Conceptual Design and RD are paramount at this
    point
  • design impact on physics should be stressed
  • Engineering model
  • should be flexible and parametric to respond to
    design changes
  • Beam Delivery costs estimates are
  • relatively small
  • half due to an engineering model and half due to
    a business model
  • We should
  • develop a parametric cost model good for
    trade-off studies
  • allow MBA group to apply a a scheduled
    acquisition strategy uniformly across the project
  • assign more effort into parsing data from LHC,
    SLC, PeP-II,.. into buckets and flavors useful
    for a NLC cost comparison
Write a Comment
User Comments (0)
About PowerShow.com