Sustainable Design in Engineering - PowerPoint PPT Presentation

1 / 49
About This Presentation
Title:

Sustainable Design in Engineering

Description:

Lab 1: Sustainable Design Challenge. LCAs of TV and an Electro-hydraulic Valve ... Printed circuit boards at Skive, DK plant. Highly uniform production, assembly ... – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 50
Provided by: mrsdian
Category:

less

Transcript and Presenter's Notes

Title: Sustainable Design in Engineering


1
Sustainable Design in Engineering
  • ECE 0909.403 / 0909.504.02 - Lecture 13
  • Why the lights went out? 14 August 2003
  • Lab 1 Sustainable Design Challenge
  • LCAs of TV and an Electro-hydraulic Valve
  • 19 November 2003
  • Dr. Peter Mark Jansson PP PE

2
Aims
  • 14 August 2003 Elaboration
  • Lab 1 Sustainable Design Challenge
  • LCA of the Bang Olufsen LX5500 Television
  • Scope definition of product system
  • Environmental exchanges / Impact assessment
  • Environmental diagnosis for the LX5500 TV
  • LCA of an EHC Valve
  • Scope definition of product system
  • Environmental exchanges / Impact assessment

3
14 August 2003
  • https//reports.energy.gov/
  • U.S. Canada Power Systems Outage Task Force
    Causes of the August 14th Blackout

4
Reliable transmission
  • 7 principles
  • 1. Continuously balance generation / demand
  • 2. Balance reactive power to maintain voltage
  • 3. Monitor flows to not exceed thermal limits
  • 4. Keep system in stable condition
  • 5. Keep system in reliable condition (n-1)
  • 6. Plan, design and maintain to operate reliably
  • 7. Prepare for emergencies

5
Sequence unchanged
  • Assessment
  • Inadequate System Observation Loss of System
    Control and Data Acquisition
  • Outages due to inadequate tree trimming
  • Harding Chamberlain 345 kV 43.5 loaded
  • Hanna-Juniper 345kv 87.5 loaded
  • Star South 345kV 93.2 of emergency rating
  • Once this situation occurred FE needed to
    voluntarily reduce load so as not to impact
    remaining system, due to their unawareness of the
    n-1 contingency breach they did not take this
    critical action

6
Lab 1 Sustainable Design Challenge
  • Rowan University Plans to spend 27.3 Million on
    townhouses in Rowan Woods to create 464
    additional beds on campus for housing residential
    students.
  • You have 1 hour in your lab to determine the key
    2-5 Sustainable Design project investments you
    propose to President Farish and the Board of
    Trustees costing less than 30 million that would
    make Rowan a premier sustainable university
    campus.
  • Maximize the environmental savings to the
    university (CO2 reduction, BTUs, etc.) while
    attempting to create the strongest business case
    for your proposals (I.e., shortest paybacks, rate
    of returns, etc,)
  • Use sustainable technologies you have learned
    about

7
Sustainable Technologies to Consider
  • Energy Efficiency investments
  • HVAC technologies (geothermal, etc.)
  • Lighting retrofits, controls, etc.
  • Increased efficiency in building envelopes
  • Renewable Energy Investments
  • Wind, Solar (PV, thermal, etc.), Biomass,
  • Cogeneration Systems
  • Gas turbines
  • Fuel Cells,

8
Background Campus Data
  • Annual Energy Usage
  • Electric 24,011,814 kWh 2,173,028
  • Cogeneration Plant 8,137,700 kWh 737,920
  • Gas - 2,116,799
  • Campus Size 1,904,337 sq.ft
  • gt 40 buildings, gt 5 large parking lots
  • Average Use for Comparable Universities 18.9 kWh
  • Rowan Usage per sq.ft 16.9 kWh (electricity
    only)

9
(No Transcript)
10
Constraints
  • Identify and list all key assumptions
  • Use web or me for assistance for any renewable
    energy resource estimates
  • All capital investments must be made within a 50
    miles radius of campus
  • Present each project in detail
  • Estimated cost, units, energy impact, env.
    benefits, payback estimate
  • You will have 4-5 minutes to sell your overall
    plan and discuss its benefits

11
Projects will be peer graded
  • You will each assign a priority to one anothers
    conceptual designs
  • Our 30 million will be spent on the top 3-5
    project proposal elements

12
The LCA Process
Impact Assessment
Goal
Scope
Inventory
Environmental. Assessment (E.A.) of
References Environmental Diagnosis E.A. of
Concepts E.A. of Details
The Product System Materials Manufacture Use
Disposal
Environmental Exchanges Inputs (Energy
Materials) Outputs (Air, Water Waste) Work
Environment
Impact Potentials Resource Consumption (Energy
Materials) Environmental Impacts (Global
Warming, Acidification, Ozone, etc.) Impact on
Work Environment
13
LX5500
  • Chosen as Reference Product
  • TV believed to have greatest impact
  • Greatest environmental FOCUS in BO
  • Representative model (flagship)
  • High degree of complexity

14
Functional Unit
  • Reception of TV programs for 6 hours per day with
    18 hours standby for 10 years for a 28 color
    television
  • Secondary qualities
  • BASIC FEATURES Picture quality (colors and
    sharpness), sound quality, number of channels,
    etc.
  • OPTIONS remote control, teletext, decoders,
    connecting with external speaker system.

15
MECO Scope def.
  • Extent of product system included based upon the
    MECO analysis
  • Materials with few exceptions all components are
    included in the LCA (mfg proc. for gt 90)
  • 24.5 kg picture tube (21.8 glass, 1.5 Fe, .5 Cu)
  • 11.0 kg plastic (casing, rear cover, speakers)
  • 2.9 kg contrast screen (2.75 glass, .15 Fe)
  • 0.96 kg speakers (.43 Fe, .53 magnets)

16
MECO Materials (cont.)
  • 3.15 kg electronics of which
  • 2.0 kg plastic
  • 0.5 kg Fe (iron)
  • 0.42 kg Cu
  • 0.10 kg Al
  • 0.12 kg Pb (lead)
  • 0.23 kg Aluminum for edging
  • Remaining 10 of weight, estimate of scarce
    resource consumption was undertaken

17
MECO (continued)
  • Chemicals ancillary substances for the
    manufacturing process at Bang Olufsen (i.e.,
    lubricants and cleaning chemicals) were included
    and emissions (incomplete in the tracking of
    chemical production all the way back to nature)
  • Others working environment impacts were omitted
    from the LCA since many large components were
    manufactured by subcontractors, service and
    repairs not included

18
Material Production (Gram)
  • Crude Oil ME, Africa, North Sea, EE, US
  • Natural Gas North Sea
  • Coal Europe, US
  • Plastic Italy (ABS), Germany (PE, PVC)
  • Chemicals Netherlands, France, Germany
  • Metals ores from all over the world (ship and
    rail) and processed in Europe

19
Manufacturing Process
  • Mostly from subcontractors
  • Germany and France
  • Few components in-house
  • Printed circuit boards at Skive, DK plant
  • Highly uniform production, assembly
  • Total consumption of materials
  • Emissions and total waste of factory
  • Transport included for 90 of TV (weight)

20
Other
  • Wastewater treatment plant output tested 9 times
    per year
  • Rejection rate faulty components discarded at
    each step in manufacturing process, raw materials
    consumed gt raw materials in final TVs shipped
  • Overhead Allocation of HVAC, lighting, canteen
    costs from factory and administrative facilities
    distributed to each television produced on weight
    basis of years sales

21
Use Process
  • Used mostly in European Union (Germany, France,
    Denmark, Sweden, Finland, rest of EU) with 10
    sent to rest of world
  • Country of use is important for 4 reasons
  • Transport (by trucks to central and dealers)
  • Use patterns vary between nations
  • Electricity impacts vary
  • Disposal varies environmental impact

22
Use (continued)
  • In winter months, unit contributes to heating of
    homes, so energy consumption in the homes is
    reduced. (i.e., quantity of energy replaced was
    subtracted from televisions consumption)
  • Impact on cooling was not considered
  • Electricity for use was for country of use

23
Disposal Process
  • Assumed
  • no recycling of TVs today
  • 70 of TVs are dumped (15 km transport)
  • 30 are assumed incinerated (30 km)

24
Resource Consumption
  • Television 42.7 kg
  • Resources to produce materials 80 kg
  • Manufacturing 23 kg
  • Use 480 kg
  • Transport 3.5 kg
  • TOTAL 630 kg

25
Emissions to Air
  • CO2 (1.3 tonnes)
  • Primarily from energy systems (81 in use)
  • Use 75-80 of NOx, 92 SO2
  • Transport 44 of CO and 54 of Pb
  • Disposal most of Dioxins emitted

26
Emissions to Water
  • Some heavy metal emissions in production and
    extraction of raw materials

27
Waste
  • Largest in use phase (coal residue)
  • Television itself in dump, or quartz slag during
    incineration

28
Energy Profiles
  • Energy accounts for a large proportion of
    resource consumption and emissions
  • 78 of energy consumption in Use Phase 90 while
    TV is on and 10 while TV is in Standby mode
  • 22 of total energy consumption is raw material
    extraction, and material production.
  • Designer has most impact on materials selected
    (i.e., energy needed to extract, manufacture
    materials, etc.)
  • Calorific value only 11 (recycle vs. incinerate)

29
Impact Assessment
  • Most significant resources copper and natural
    gas
  • Most significant environmental impact global
    warming, acidification, radioactive waste, slag
    and ashes and bulk waste
  • Most significant working environment impacts not
    estimated based upon scope

30
Sources of Impact
  • The picture tube 20 of oil and 50 of natural
    gas resources are used in its production
  • Electricity 82 of slag and ashes, 68 of bulk
    waste and 83 of global warming

31
Environmental Diagnosis
  • To identify the potentials for improvement in the
    product so that, together with the environmental
    assessment of the reference product, a basis can
    be formed for points of focus

32
How?
  • Simulate various theoretical changes in the
    product or product system
  • Or
  • Generate information on known technologies that
    are potentials for improvement

33
Simulation
  • Following the MECO principle
  • Materials disposal
  • 100 recycle of metals
  • Wood case instead of plastic
  • Energy use
  • Standby energy is halved

34
Simulation
  • Chemicals consumption
  • Casing not painted
  • Others
  • Change lifetime increase

35
Findings from Simulation
  • Consumption of Cu reduced 90 and Al 75 by
    recycling scenario
  • Wood casing reduces oil and gas use by 5, global
    warming by 2 (Casing only product system impacts
    are gtgt)
  • Not painting reduces ozone impact by 72

36
Efficiency
  • 5, 10 and 30 increases in efficiency were
    simulated
  • Overall 10 reductions in electricity yield 8
    reduction in global warming impact potential
  • 7 reductions achieved in Avant model
  • 30 unlikely without technology change

37
Sources of Improvement
  • Picture tube (Large contributor to use,
    materials production and waste phases) LCD
    alternative 50 less energy, laser scanning or
    plasma displays
  • Electricity Use part is forgetting to turn off
    or as background entertainment
  • Install sensor (motion or presence) control
  • Remote control notification (TV off in 100 min.)
  • Separate Tube from sound and control tube only

38
Potentials Identified
  • PC boards in Electronics Package thick film
    technology from Danfoss
  • Increases electronics lifespan
  • Reduces scarce metal use (70 Sn, 65 Pb, 25
    Cu)
  • Standby energy 10 of use stage energy
  • Construct TV and VCR in single unit and combine
    standby energy requirement

39
Potentials (continued)
  • Number of materials reduce total
  • recovery is difficult due to two types of
    plastic (PS and ABS), trim metals, internal
    metals
  • use one type of plastic, omit items (trim)
  • Casing, rear cover and front panel painting
    reduces recyclability
  • avoid painting or use different paints
  • change materials (wood, etc.)

40
Material Points of Focus
  • copper in deflection coils, replaced with other
    material or make it easier to separate from tube
  • zinc in picture tube spacers can be made of
    steel, cast iron or recycled aluminum
  • primary aluminum profiles replaced with
    recycled Al, make case not needing profiles in
    design, make Al more easily removed

41
Env. Specification for TV
  • Materials choose materials that enable
    recycling, construct for ease of dismantling,
    substitute primary aluminum
  • Energy reduce power use during operation and
    standby
  • Chemicals avoid toxic substances, dont paint
    with substances that reduce recyclability

42
LCA of Danfoss PVEH
  • Proportional Valve Electric High Performance
    the electro-hydraulic activation unit for
    hydraulic valves, cranes, excavators, trucks and
    many other hydraulic applications

43
PVEH
  • Chosen as Reference Product
  • Danfoss developing a new generation of EHV units
  • Complex product
  • Mechanical, electronic, hydraulic parts

44
Functional Unit
  • Regulation of one hydraulic proportional valve in
    a hydraulic system for 5 years
  • Secondary qualities
  • Inbuilt error monitoring, fast reaction time with
    an inductive feedback transducer monitoring the
    main sliding valves position in the hydraulic
    valve, little hysteresis (i.e., very high
    precision)

45
Resource Consumption
  • PVEH 1 kg
  • Resources to produce materials 3 kg
  • Manufacturing 4 kg
  • Use 12 kg
  • Transport 0.14 kg
  • TOTAL 20 kg

46
Energy Profiles
  • Energy accounts for a large proportion of
    resource consumption and emissions
  • Energy in use stage is highest
  • Energy in manufacture is second highest (86 of
    this is from overheads for manufacturing)

47
Environmental Diagnosis
  • To identify the potentials for improvement in the
    product so that, together with the environmental
    assessment of the reference product, a basis can
    be formed for points of focus

48
Summary of Simulations
  • Thick film technology increases life span of PVEH
    (fewer soldered joints)
  • Use of materials is decreased by increased life
    span
  • TF technology also decreases consumption rate for
    scarce metals
  • Removal of PC boards prior to shredding enhances
    material separation

49
New Product Design
  • Thick film instead of conventional fiber glass
    reinforced epoxy laminate technology increases
    life from 5 to 8 years reducing all metal use
  • Thick film technology requires less energy in
    manufacturing
  • Tantalum capacitors are replaced by ceramic caps
  • Change in yoke design reduces Fe by 30
Write a Comment
User Comments (0)
About PowerShow.com