RSVP Review Closeout Comments November 5, 2004 - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

RSVP Review Closeout Comments November 5, 2004

Description:

RSVP Review. Closeout Comments ... essential aspects of the plan, including the proposed scope that has been ... MECO production solenoid, target etc. ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 21
Provided by: ray87
Category:

less

Transcript and Presenter's Notes

Title: RSVP Review Closeout Comments November 5, 2004


1
RSVP ReviewCloseout CommentsNovember 5, 2004
  • RSVP Review Committee
  • R. Larsen, S. Ecklund, J. Seeman,
  • A. Marchionni, E. Metral, G. McMichael, R.
    Pasquinelli

2
  •   CHARGE TO
    THE COMMITTEE
  •  
  • 1 Review all elements of the proposed AGS
    Upgrade Construction Program for RSVP through
    presentations by the design team. Team should
    present
  •  
  •         essential aspects of the plan, including
    the proposed scope that has been verified with
    RSVP experimental teams
  •         upgrade implementation plan, including
    resource loaded schedule
  •         as clearly identified and separately
    costed, any non-RSVP elements of the proposed
    plan
  •         technical, schedule and cost risks to
    the plan.
  •  
  • 2 Review the proposed Operations Plan for RSVP,
    including plan and resource-loaded schedule
    potential conflict with non-RSVP operations and
    vice-versa.
  •  
  • 3 Examine the management structure of the AGS
    Upgrade Program for RSVP, including line
    authorities in the Brookhaven Laboratory and RSVP
    management. Is there sufficient integration,
    interaction, communication, etc.? Are
    responsibilities clear?
  •  
  • 4 Explore with the design team possible
    reductions in scope, deferment, or future staging
    of elements of the proposed upgrade. Identify
    and characterize attendant risks and trade-offs
    associated with each of these changes. Explore
    all issues of joint concern to AGS, RSVP teams.
  •  
  • 5 Summarize findings and recommendations in
    final closeout report.

3
Presentations
  • Team presentations
  • Booster
  • AGS
  • Electrical
  • Mechanical
  • Switchyard
  • KOPIO, MECO infrastructure
  • Beam development
  • Schedule Personnel
  • Operations cost schedule
  • Management Issues
  • The Committee was pleased to see the level of
    work represented by the presentations, which were
    clear and well integrated.
  • Most detailed planning cost work accomplished
    since July 2004.
  • Some aspects of content need further development.

4

  • CHARGE TO THE COMMITTEE
  •  
  • 1 Review all elements of the proposed AGS
    Upgrade Construction Program for RSVP through
    presentations by the design team. Team should
    present
  •  
  •         essential aspects of the plan, including
    the proposed scope that has been verified with
    RSVP experimental teams
  •         upgrade implementation plan, including
    resource loaded schedule
  •         as clearly identified and separately
    costed, any non-RSVP elements of the proposed
    plan
  •         technical, schedule and cost risks to
    the plan.
  •  
  • 2 Review the proposed Operations Plan for RSVP,
    including plan and resource-loaded schedule
    potential conflict with non-RSVP operations and
    vice-versa.
  •  
  • 3 Examine the management structure of the AGS
    Upgrade Program for RSVP, including line
    authorities in the Brookhaven Laboratory and RSVP
    management. Is there sufficient integration,
    interaction, communication, etc.? Are
    responsibilities clear?
  •  
  • 4 Explore with the design team possible
    reductions in scope, deferment, or future staging
    of elements of the proposed upgrade. Identify
    and characterize attendant risks and trade-offs
    associated with each of these changes. Explore
    all issues of joint concern to AGS, RSVP teams.
  •  
  • 5 Summarize findings and recommendations in
    final closeout report.

5
Implementation Plan Resource Loaded Schedules
  • The implementation plan for Booster, AGS and
    Switchyard was well detailed.
  • The plans for experimental beams and Beam
    Development have questions concerning the
    experimental interfaces and schedule.
  • Some resource analysis was shown, but resource
    loaded schedules are not yet developed.

6
  • CHARGE TO THE COMMITTEE
  •  
  • 1 Review all elements of the proposed AGS
    Upgrade Construction Program for RSVP through
    presentations by the design team. Team should
    present
  •  
  •         essential aspects of the plan, including
    the proposed scope that has been verified with
    RSVP experimental teams
  •         upgrade implementation plan, including
    resource loaded schedule
  •         as clearly identified and separately
    costed, any non-RSVP elements of the proposed
    plan
  •         technical, schedule and cost risks to
    the plan.
  •  
  • 2 Review the proposed Operations Plan for RSVP,
    including plan and resource-loaded schedule
    potential conflict with non-RSVP operations and
    vice-versa.
  •  
  • 3 Examine the management structure of the AGS
    Upgrade Program for RSVP, including line
    authorities in the Brookhaven Laboratory and RSVP
    management. Is there sufficient integration,
    interaction, communication, etc.? Are
    responsibilities clear?
  •  
  • 4 Explore with the design team possible
    reductions in scope, deferment, or future staging
    of elements of the proposed upgrade. Identify
    and characterize attendant risks and trade-offs
    associated with each of these changes. Explore
    all issues of joint concern to AGS, RSVP teams.
  •  
  • 5 Summarize findings and recommendations in
    final closeout report.

7
Non-RSVP Elements
  • These elements appear to have been identified and
    excluded appropriately.
  • Manpower support for operations requires
    integration with the existing RHIC matrix, which
    will be augmented with levels of manpower
    appropriate to the incremental RSVP levels.

8
  • CHARGE
    TO THE COMMITTEE
  •  
  • 1 Review all elements of the proposed AGS
    Upgrade Construction Program for RSVP through
    presentations by the design team. Team should
    present
  •  
  •         essential aspects of the plan, including
    the proposed scope that has been verified with
    RSVP experimental teams
  •         upgrade implementation plan, including
    resource loaded schedule
  •         as clearly identified and separately
    costed, any non-RSVP elements of the proposed
    plan
  •         technical, schedule and cost risks to
    the plan.
  •  
  • 2 Review the proposed Operations Plan for RSVP,
    including plan and resource-loaded schedule
    potential conflict with non-RSVP operations and
    vice-versa.
  •  
  • 3 Examine the management structure of the AGS
    Upgrade Program for RSVP, including line
    authorities in the Brookhaven Laboratory and RSVP
    management. Is there sufficient integration,
    interaction, communication, etc.? Are
    responsibilities clear?
  •  
  • 4 Explore with the design team possible
    reductions in scope, deferment, or future staging
    of elements of the proposed upgrade. Identify
    and characterize attendant risks and trade-offs
    associated with each of these changes. Explore
    all issues of joint concern to AGS, RSVP teams.
  •  
  • 5 Summarize findings and recommendations in
    final closeout report.

9
Technical, Schedule Cost Risks
  • The bulk of the Booster, AGS and Switchyard
    upgrades are low technical risk.
  • Achieving higher levels of intensity and cleaner
    extinction between pulses through additional RF
    magnets are critical to the experiments these
    have been modeled but not been demonstrated and
    are higher technical risk.
  • Changes in the experiments may pose additional
    technical risks beyond the control of the AGS
    team.

10
Schedule Risk
  • The risks were discussed during various
    presentations.
  • The schedule risks for the bulk of AGS upgrades
    appears to be mostly in ramping up to needed
    manpower levels and finding appropriate people
    for temporary work, esp. engineers.
  • The start date of 2006 appears aggressive
    considering the unknowns of total project cost
    and funding.
  • The Beam Development schedule is a draft and will
    be reexamined to attempt to reduce duration from
    five to three years.
  • The overall schedule integrated with the
    experiments needs to be developed.
  • The delivery of critical experimental components
    poses risks beyond the control of the AGS Upgrade
    team.

11
Cost Risk
  • Cost risks were not presented as a separate
    analysis by the team, but in subsequent
    presentations.
  • The contingency levels of most estimates averaged
    less than 25 which indicates high confidence
    factor.
  • This is appropriate for most parts of the AGS
    complex since the upgrade includes few technical
    uncertainties.
  • Uncertainties of experiments can pose serious
    risk
  • KOPIO production angle, pit size
  • MECO production solenoid, target etc.
  • Overall cost growth in estimates is causing
    serious concern within the funding agency.

12
Cost Growth
  • The cost estimate has grown since January 2004 by
    30M to a final total of 84M of which 32M is
    attributed to Beam Development.
  • The latter is in reality Pre-Ops as opposed to
    construction and did not change since January.
  • Therefore the construction segment appears to
    have more than doubled.
  • Reasons
  • Magnet/PS/controls upgrades to reduce risk to
    RHIC
  • ESH requirements for caps over high-activation
    areas
  • Growth in experimental beams costs
  • Addition of Project Office

13
  • CHARGE TO THE COMMITTEE
  •  
  • 1 Review all elements of the proposed AGS
    Upgrade Construction Program for RSVP through
    presentations by the design team. Team should
    present
  •  
  •         essential aspects of the plan, including
    the proposed scope that has been verified with
    RSVP experimental teams
  •         upgrade implementation plan, including
    resource loaded schedule
  •         as clearly identified and separately
    costed, any non-RSVP elements of the proposed
    plan
  •         technical, schedule and cost risks to
    the plan.
  •  
  • 2 Review the proposed Operations Plan for RSVP,
    including plan and resource-loaded schedule
    potential conflict with non-RSVP operations and
    vice-versa.
  •  
  • 3 Examine the management structure of the AGS
    Upgrade Program for RSVP, including line
    authorities in the Brookhaven Laboratory and RSVP
    management. Is there sufficient integration,
    interaction, communication, etc.? Are
    responsibilities clear?
  •  
  • 4 Explore with the design team possible
    reductions in scope, deferment, or future staging
    of elements of the proposed upgrade. Identify
    and characterize attendant risks and trade-offs
    associated with each of these changes. Explore
    all issues of joint concern to AGS, RSVP teams.
  •  
  • 5 Summarize findings and recommendations in
    final closeout report.

14
Operations Plan, Resource-Loaded Schedule,
Conflicts
  • The plan was presented along with an incremental
    total manpower analysis.
  • The resources were averaged and not leveled in
    detail.
  • Conflicts with RHIC requirements have to be
    worked out in detail.
  • Concerns about difficulties of finding skilled
    people matrix management.
  • Potential impacts on costs and schedules.

15
  • CHARGE TO THE COMMITTEE
  •  
  • 1 Review all elements of the proposed AGS
    Upgrade Construction Program for RSVP through
    presentations by the design team. Team should
    present
  •  
  •         essential aspects of the plan, including
    the proposed scope that has been verified with
    RSVP experimental teams
  •         upgrade implementation plan, including
    resource loaded schedule
  •         as clearly identified and separately
    costed, any non-RSVP elements of the proposed
    plan
  •         technical, schedule and cost risks to
    the plan.
  •  
  • 2 Review the proposed Operations Plan for RSVP,
    including plan and resource-loaded schedule
    potential conflict with non-RSVP operations and
    vice-versa.
  •  
  • 3 Examine the management structure of the AGS
    Upgrade Program for RSVP, including line
    authorities in the Brookhaven Laboratory and RSVP
    management. Is there sufficient integration,
    interaction, communication, etc.? Are
    responsibilities clear?
  •  
  • 4 Explore with the design team possible
    reductions in scope, deferment, or future staging
    of elements of the proposed upgrade. Identify
    and characterize attendant risks and trade-offs
    associated with each of these changes. Explore
    all issues of joint concern to AGS, RSVP teams.
  •  
  • 5 Summarize findings and recommendations in
    final closeout report.

16
Management Plans
  • Integration, Communication major factors
  • There is recent precedent at BNL for similar
    management issues, e.g. SNS and ATLAS.
  • Lines of authority appear well understood though
    inherently complicated by dual lines of authority
    up the chain.
  • Standing management meetings either exist already
    or will be set up alongside the current RHIC
    management structure.
  • Operations will be well integrated with RHIC
    through liaisons, daily weekly meetings.

17
  • CHARGE TO THE COMMITTEE
  •  
  • 1 Review all elements of the proposed AGS
    Upgrade Construction Program for RSVP through
    presentations by the design team. Team should
    present
  •  
  •         essential aspects of the plan, including
    the proposed scope that has been verified with
    RSVP experimental teams
  •         upgrade implementation plan, including
    resource loaded schedule
  •         as clearly identified and separately
    costed, any non-RSVP elements of the proposed
    plan
  •         technical, schedule and cost risks to
    the plan.
  •  
  • 2 Review the proposed Operations Plan for RSVP,
    including plan and resource-loaded schedule
    potential conflict with non-RSVP operations and
    vice-versa.
  •  
  • 3 Examine the management structure of the AGS
    Upgrade Program for RSVP, including line
    authorities in the Brookhaven Laboratory and RSVP
    management. Is there sufficient integration,
    interaction, communication, etc.? Are
    responsibilities clear?
  •  
  • 4 Explore with the design team possible
    reductions in scope, deferment, or future staging
    of elements of the proposed upgrade. Identify
    and characterize attendant risks and trade-offs
    associated with each of these changes. Explore
    all issues of joint concern to AGS, RSVP teams.
  •  
  • 5 Summarize findings and recommendations in
    final closeout report.

18
Explore Reductions in Scope, etc.
  • This was attempted throughout the meeting
  • Delete one of the experiments Unacceptable.
    Experiments have been sold as a package.
  • Defer AGS upgrades Bad strategy poses high risk
    to RHIC and would miss existing low activation
    window of opportunity in AGS.
  • Reduce or eliminate Beam Development program
    Possible cost reduction of 14M without much
    compromise to program, if any, appears feasible.
    Team will investigate.
  • Additional cost reductions should be sought
    through scrubbing technical component design
    and costs, labor costs, system design
    improvements in both AGS and experiments.

19
Recommendations
  • Continue refining estimates with Lehman-like
    documentation (resource loaded leveled
    schedules, cost books etc.) for future review.
  • Schedule future cost scrubbing reviews of both
    AGS and experimental programs.
  • Continue aggressive cost-reduction plan, such as
    design improvements to replacement components,
    reducing/eliminating Beam Development program,
    beam operations manpower levels etc
  • Continue identifying, mitigating technical,
    schedule and cost risks.

20
Conclusion
  • The Committee is very pleased that a large effort
    over the past four months has shown impressive
    progress and dividends in the planning process.
  • We look forward to seeing continued progress in
    planning and development, and ultimate success in
    securing full funding and staffing.
  • Thanks to all the presenters for their diligent
    efforts in helping meet our Charge.
  • Keep up the good work!
Write a Comment
User Comments (0)
About PowerShow.com