Title: optics measurements needed at top energy
1optics measurements needed at top energy
thanks to Ralph Assmann, Rama Calaga, Stephane
Fartoukh, Massimo Giovannozzi, Per Hagen, Rhodri
Jones, John Jowett, Verena Kain, Jean-Pierre
Koutchouk, Stefano Redaelli, Stephane
Sanfilippo, Frank Schmidt, Ralph Steinhagen
2basic considerations
- nominal optics similar to 450 GeV optics
- IR2 optics magnet errors different
- BPM offsets expected to change by less than 50 mm
- apertures already checked at 450 GeV/c
normalized aperture 4x larger at 7 TeV - damage and quench levels reduced
- it takes much longer (1 h) to return after beam
loss
3critical beam intensities
4two extreme cases
- no need for detailed studies if optics hardly
changes compared with injection - but if optics strongly varies between 450 GeV/c
and 7 TeV we may need to measure and correct
optics already on the ramp
5orbit change
- 50 units change in transfer function of arc
dipoles - about 700 units change for D1, D2, D3 and D4!
- - warm magnets saturation
- - cold magnets very low excitation at
injection - assume 1 transfer function accuracy
- ? 7x10-4 error in D1 to D4 ? 50 mm change each
- exact local correction not foreseen for LSS
- ? orbit different if Q4 correctors not touched
- 2 beams 2.5 mm separation bump reduced gt5 TeV
- change in rf frequency circumference
- orbit feedback will correct most of the changes
6Animesh Jain, December 4, 2002 Stephane Fartoukh
7
7rf frequency swing
Dfrf1 kHz ? Dx10 mm
dominant error may come from BPMs/pick-ups
p
208Pb82
radial loop gets input from orbit feedback
John Jowett
may expect 20-100 mm error for pilot
8energy reconstruction error as function of BPM
noise for d10-5
Ralph Steinhagen
9optics change
- tune change DQ0.1 (F.Z., Chamonix 2006)
- chromaticity change DQ320 units
- peak beta beat change up to 40 peak?
- - Db2 /-2.5 units (apertures 1 and 2), 7-8
peak - - Db3 7 units (spool-piece excitation 0.6 mm
rms spool misalignment), 6 peak - - WISE model 13-18 w/o geometric effects
- IP1-5 phase advance change Df0.14 x 2p
- coupling change Dk0.05 (Chamonix 2006)
- IR2 optics change (injection ? pre-squeeze)
- tune and coupling feedback likely to be active
- chromaticity feedback less probable
10illustration b2 evolution with MB current for
the two apertures
Courtesy of N. Sammut
S. Fartoukh and M. Giovannozzi, FQWG 08/03/2005
11illustration b3 evolution with MB current
- change of sign!
- 4 units (inj.)
- ? 3 units (7 TeV)
L. Bottura, 13.01.2004
12expected b beating (av. 2s)
preliminary WISE results from Per Hagen
rough guesses
larger error at 7 TeV than at injection due to
uncertainty
13IR2 injection and pre-collision optics
- Injection optics has to have phase advance of 90
degrees between MKI and TDI, and a vertical phase
advance of 360-20 degrees and 36020 degrees
between the TDI and the two auxilliary
collimators - Not possible at 7 TeV without exceeding
quadrupole strength limits - Pre-collision optics has same b10 m but
different phase advances and does not respect
injection condition - Need to change optics in the ramp, called
pre-squeeze here for want of a better word - At which energy ?
- Following examples for V6.5
- Need to be updated, indicative only for now
John Jowett
14Horizontal optics in pre-squeeze
Beam 1/2 thick/thin, Injection/Pre-collisionRed
/Blue
John Jowett
15Vertical optics in pre-squeeze
Beam 1/2 thick/thin, Injection/Pre-collisionRed
/Blue
John Jowett
16Horizontal phase in pre-squeeze
Beam 1/2 thick/thin, Injection/Pre-collisionRed
/Blue
John Jowett
17Vertical phase in pre-squeeze
Beam 1/2 thick/thin, Injection/Pre-collisionRed
/Blue
John Jowett
187 TeV measurements corrections
- tunes (excite beam) do we go to collision
tunes? - or tunecoupling feedback
- chromaticity (tune radial steering, or
head-tail monitor, or rf phase modulation) - orbit (stabilized with feedback?)
- coupling (minimize CTA or coupling line in tune
spectrum) using orthogonal knobs or
tunecoupling feedback - beta function dispersion
- IP1-5 phase advance
- ORM measurements not needed for feedback
- b3 correction check? (likely not needed at 7
TeV beam smaller already done at injection)
19dispersion
- aperture permits up to Dd /- 3.5x10-3
- tighten momentum collimators to be safe
- against optics errors, e.g. to 1.0 or 1.7x10-3?
- 20 mm BPM resolution
- for pilot in orbit mode
Stephane Fartoukh
20beta function / linear optics
- phase beating from turn-by-turn data
- how to excite the beam at 7 TeV
- - aperture kicker 1.6s max. (LTC 15 June
2005) - - tune kicker 0.7s maximum
- - ac dipole available at this stage?
- machine protection issues?
- repeated kicks of same bunch problematic,
- - several pilots kicking single bunches?
- collimator scans
- and/or K modulation in collimator straights?
21resolution of turn-by-turn data
- rms BPM resolution for pilot 200 mm 1s
- phase error (Rogelio Rama)
- correction works for Dfpeak3Dfrmslt1o (Rama)
- example 400 turns with 1.6s kick Dfpeak7.6o
limited kicker strength BPM noise ? 7-TeV
optics measurements with pilot bunch extremely
difficult
22Rama Calaga
20 s kick, 200 mm (1s) BPM noise, 400 turns, no
decoherence
20s kick and 400 turns or 6.3s kick and 4000
turns give 0.5o peak phase error
23Rogelio Tomas Rama Calaga
0.5 degree peak phase error
with 0.5o peak phase error, peak b beat can be
corrected for all seeds
24Rogelio Tomas Rama Calaga
1 degree peak phase error
with 1o peak phase error, peak b beat cannot be
corrected for many seeds
25proposed procedure
- priority machine protection
- close collimators by factor 2 (during ramp)
- measure local beam sizes at all collimators with
collimator scans to roughly check optics
re-adjust, so that secondaries indeed are
secondaries - if inferred beating is in safe range (lt100)
raise bunch intensity to gt 3x1010 for b
measurements with aperture kicker or ac dipole ?
50 mm BPM noise ? Dfpeak1.9o - or (if resolution insufficient) use ac dipole!?
26SR monitors undulator light ? dipole
light Main change light intensity. No change
in measured beam size expected. Current
plan Fine tune telescopes at 450 GeV 7
TeV. Use 450-GeV settings up the ramp. Requires
time with "stable" circulating beam. Most can be
done parasitically if emittance blow-up limited.
Cross calibration with wire scanners required at
both energies.
Rhodri Jones
27D1/D2 transfer function
- recall
- D1-D2 transfer function errors can have a
significant effect on closed orbit during squeeze
(10 units ? 3s orbit change at triplet) - local correction requires careful analysis and
distinction between - D1/D2 transfer function errors
- Triplet alignment errors
- Triplet gradient errors with crossing-angle bump
offsets
O. Bruning, Chamonix XII F. Zimmermann,
LHCCWG10
28IR1 layout
D2
D2
D1
D1
common BPMs
separate BPM
separate BPM
BPM distances to IP 21.35, 31.53, 58.32, 151.14 m
29D1/D2 suggestion
- assume alignment was done at injection (i.e. BPM
readings for straight reference line identified
quad offsets determined) - main error after ramp is due to D1 D2 TF
uncertainty (perform Q1/Q2/Q3 K modulation to
verify quad misalignments?!) - suggested approach correct incoming beams for 0
orbit and slope upstream of D2, then use D1 and
D2 strengths to bring both beams onto the same
orbit at 7 TeV
O. Bruning, Chamonix XII F. Zimmermann,
LHCCWG10
30D1/D2 problems (LHCCWG10)
- low-b quads misalignment of mechanical
magnetic axes 0.1-0.2 mm in x, 0.5 mm in y beam
needs to be steered through the mechanical
center! - BPM offsets may cause error of up to 5 mrad (?),
compared with total deflection angle of 1.5 mrad
this is larger than desired precision of 3x10-4 - BPMs might have different offsets for beam1 and
beam2 (?)
S. Fartoukh, M. Giovannozzi, F.Z.
31longitudinal blow up?
- longitudinal emittance at injection to the LHC
will be 0.6 eVs for nominal intensity - design emittance at 7 TeV 2.5 eVs
- emittance blow up at the middle of the ramp (or
at 7 TeV?) to combat IBS rates and to stabilize
the beam longitudinally - if instability occurs, may need to implement the
blow up in the commissioning
32draft 7 TeV procedure
close b collimators by factor 2 on ramp
measure b phase Df IP1-5 aperture kicker and
higher intensity bunch or ac dipole
orbit, tune coupling (pre-)corrected by
feedback manual adjustment if needed
correct optics? (and iterate if correction is
needed)
(pre-)correct chromaticity (decoherence, radial
steering)
ORM for feedback calibration?
collimator beam-size scans, and adjustments
settle D1/D2 (D3/D4) transfer function, prior to
squeeze
measure dispersion Q with radial steering
e blow up?
33summary
- optics errors at 7 TeV can be significant and are
different from 450 GeV/c orbit optics also
differ - we should close collimators on ramp and perform
collimator scans - feedback may take care of (most of ) orbit, tune
and coupling correction - limited aperture kicker 200-mm BPM noise do not
allow for clean optics measurements with pilot
bunch need higher intensity and/or ac dipole - dispersion Q can be measured by radial
steering - other issues D1/D2 (D3/D4) transfer function,
feedback calibration, beam parameters