MINE ECONOMICS - PowerPoint PPT Presentation

1 / 42
About This Presentation
Title:

MINE ECONOMICS

Description:

THE INTERACTION BETWEEN THE RESOURCE AND THE TECHNICAL OPTIONS ... Open pit and stope designs. Operating costs/tonne. Fixed costs/tonne. UNSW Mining Engineering ... – PowerPoint PPT presentation

Number of Views:987
Avg rating:3.0/5.0
Slides: 43
Provided by: edmundj5
Category:
Tags: economics | mine | stope

less

Transcript and Presenter's Notes

Title: MINE ECONOMICS


1
MINE ECONOMICS

Resource estimates and other technical
inputs. JORC Code Ed Malone
2
THE RESOURCE IS PARAMOUNT
  • NO RESOURCE, NO PROJECT
  • THE INTERACTION BETWEEN THE RESOURCE AND THE
    TECHNICAL OPTIONS DEFINES THE NATURE OF THE
    DEVELOPMENT

3
EFFECTS OF RESOURCE TYPE
  • grade estimation versus homogeneity
  • the nature of gold resources
  • comparison with other resource types
  • nature of resource affects resource estimation

4
THE MINERAL RESOURCE
  • Knowledge of the resource is essential for
    successful development
  • Inaccurate resource estimates are the most common
    causes of project failure
  • Tomic paper illustrates this for gold projects
    Paper by Bruce Tomic, RI Bank of W A
  • To SMEDG Resource Estimation Symposium, Sydney,
    16/10/92

5
300 project proposals submitted to RI Bank
during 80s mining boom
  • 82 Feasibility studies reviewed in detail
  • (Rest of submissions were totally inadequate)
  • 63 of the 82 proposals were developed generally
    with a mix of debt and equity
  • 31 of the 63 developments had failed or were in
    trouble within 18 months of commissioning

6
Review of 82 F. studies
  • Cap. Ex. Range A1M to A100M (All very small to
    small-medium)
  • Project types
  • 57 new projects
  • 34 upgrades of operating projects
  • 9 reopening old projects
  • Mining method 70 open pit and 30 underground

7
Postmortem review of 63 projects
  • Significant concerns in F. studies
  • 82 Insufficient mineable reserve tail
  • 76 Resource uncertainty
  • 43 Mining method uncertainty
  • 29 Metallurgical performance uncertainty
  • 9 Environmental performance uncertainty
  • Project performance does not correlate well with
    feasibility study review

8
Echo Bays Cove Gold Project, Nevada, USA
  • Reserves estimate, 23/12/88 9.6M oz contd. AuEq
    in proved probable inferred reserves
  • Revised estimate, 16/02/90 5.5M oz contd AuEq,
    still proved, probable inferred
  • Of 560 RCP holes originally, 137 holes, mostly
    deeper than 300m, eliminated because of
    contamination of samples

9
Exxons Harbourlights, W. A.
  • March, 84 Reserves estimate 5.5Mt_at_4g/tAu _at_
    1.5g/tAu cutoff
  • 0.7M oz contd. Au
  • July, 85 Mine opened
  • June, 87 revision
  • Mined to date, 1Mt_at_3.5g/tAu
  • Reserves, 2.5Mt_at_3g/tAu _at_ 1.25g/tAu cutoff
  • L G reserves, 1Mt_at_1.8g/tAu
  • 0.42M oz contd Au
  • Downhole smearing of grade in RCP holes

10
Agricola Mine, Qld. Nov. 1987
  • Lode 1 Reserves, 82,000t_at_4.5g/tAu mined
    65,200t_at_3.8g/tAu
  • Lode 2 Reserves, 174,000t_at_5.5g/tAu mined
    52,300t_at_4.8g/tAu
  • Total 60 contd Au shortfall
  • Geological misinterpretations
  • Au sale price, A630/oz production cost A683/oz
  • Debt, A4.5M gold loan, repayable by 7419oz Au
    produced 13,520oz Au

11
Shamrock mine, Qld.
  • Reserves, 344,000t_at_3.2g/tAu
  • Nov, 90, reconciliation after initial 5 months
    mining
  • Predicted, 75,000t_at_4.5g/tAu
  • Mined, 49,000t_at_2.8g/tAu
  • 45 gold shortfall A1.4M cashflow shortfall
    bankrupt.
  • Geological error, mining method error, management
    failings
  • Postmortem re-estimation 308,000t_at_3.2g/tAu, 21
    gold shortfall.

12
Henty Mine, Tasmania
  • Premining reserves, 506kt_at_27g/tAu
  • Mining commenced April, 1996
  • Reserves, 30/6/96 526kt_at_26.2g/tAu
  • Reserves, 30/7/96 381kt_at_28.4g/tau
  • Depletion in year 73kt_at_21.1g/tAu
  • Reduction of reserves 72kt_at_19.7g/tAu
  • Loss of reserves 10 of contained Au, near
    limit of accuracy of proved reserves.

13
Underestimates common
  • Paddington, W A
  • Original resource, 8.4Mt_at_3.2g/tAu
  • Production, 19.2Mt_at_2.3g/tAu
  • Mt Muro, Indonesia
  • Original reserves, 8.5mt_at_3.9g/tAu,86g/tAg
  • Production, 11.2Mt_at_3.8g/tAu,99g/tAg
  • Ernest Henry, Qld., Peak Mine, Cobar, NSW, and
    others

14
NATURE OF THE RESOURCE
  • CONTROLS THE DEVELOPMENT
  • DIFFERENT ARRAYS OF TECHNICAL INPUTS REQUIRED FOR
    DIFFERENT COMMODITIES
  • GOLD PROJECTS ARE DISTINCTIVE

15
OPTIMUM DEVELOPMENT
  • REQUIRES THE CORRECT BLEND OF MAJOR TECHNICAL
    OPTIONS
  • RESOURCE DEFINITION, MINING METHOD, TREATMENT,
    SALABLE PRODUCT SELECTION, MARKETING
  • BEST POSSIBLE MINOR TECHNICAL OPTIONS

16
TECHNICAL STAFF ROLE
  • DEFINE RESOURCE
  • IDENTIFY AND REVIEW POSSIBLE OPTIONS IN
    CONJUNCTION WITH MARKETING AND MANAGEMENT
  • DEFINE RESERVES, MINING METHOD, MILLING AND
    SALABLE PRODUCT/S FOR VIABLE OPTIONS
  • CONTRIBUTE TO FINANCIAL MODELLING

17
FINANCIAL EVALUATION
  • RANKS THE DEVELOPMENT OPTIONS
  • BUT
  • CANNOT JUDGE THE TECHNICAL INPUTS
  • NOR
  • RECOGNISE IF THE OPTIMUM DEVELOPMENT WAS
    CONSIDERED

18
MANAGEMENT INPUT
  • MAKE NECESSARY STRATEGIC DECISIONS EARLY
  • AVOID ARBITRARY REQUIREMENTS
  • ASK THE RIGHT QUESTIONS TO IDENTIFY THE OPTIMUM
    DEVELOPMENT

19
NATURE OF RESOURCE ESTIMATES
  • Resource estimates are never accurate
  • What is the order of accuracy of the resource
    estimate?
  • Is the project economic at the lower limit of the
    resource estimate?
  • increase the size of the resource or improve the
    accuracy of estimation
  • There is no substitute for a big margin for error

20
RESOURCE DEVELOPMENT
  • resource --gt minable reserves --gt mill feed
  • The mining department mission
  • to mine the ore body, the whole ore body and
    nothing but the ore body - at the lowest possible
    cost
  • the sting is in the tail

21
RECONCILIATION
  • The economic resource is not a fixed quantity
  • variances between predicted resource and minable
    reserves
  • variances between minable reserves and mill feed
  • a reserve tail may be no protection against a
    resource shortfall

22
MINOR PROBLEMS
  • The early mined ore
  • Metallurgical performance
  • All project components must fit together
  • Every project is unique

23
RESOURCES AND RESERVES
  • Australasian reporting code
  • History and future
  • Broad definitions only - mainly guiding
    principles
  • Importance of competent person
  • ?peer review in future

24
DECEMBER, 2004 EDITION
  • Expands on 1999 edition to cover diamonds and
    industrial minerals in more detail but few
    changes in principles
  • Maintains the large checklist of assessment
    criteria
  • But Code still implies an unachievable level of
    accuracy
  • Still working on Coal draft code

25
INTERNATIONAL COMPATIBILITY
  • Definitions in 2004 JORC code identical to or not
    materially different from international
    definitions
  • Code meets most of main requirements
  • Non-technical people can understand
  • definitions comprehensive but user friendly
  • definitions acceptable to all major players
  • capable of amendment over time
  • regarded as minimum levels

26
INTERNATIONAL INITIATIVE
  • 1997 CMMI adopted
  • standard international definitions for resources
    and reserves
  • at least for Aa, S A, U K, C, USA (major members
    CMMI)
  • 1998, UN-ECE International Framework
    Classification for Reserves and Resources
    adopted similar definitions
  • Spin off from Busang

27
(No Transcript)
28
(No Transcript)
29
(No Transcript)
30
(No Transcript)
31
(No Transcript)
32
MINERAL RESOURCE CATEGORIES
  • Inferred resource
  • Indicated resource
  • Measured resource
  • in order of increasing confidence downwards
  • Criteria needing qualification
  • Cut-off grade
  • Must be potentially economic

33
ORE RESERVES
  • Probable reserves
  • Proved reserves
  • Reserve category based on resource category with
    option to convert measured resources to probable
    reserves
  • after application of economic, mining,
    metallurgical, marketing, legal, environmental,
    social and governmental factors

34
(No Transcript)
35
(No Transcript)
36
(No Transcript)
37
(No Transcript)
38
Example of Rounding, Clause 24
  • Calculated resource estimate
  • 10,863,000 tonnes _at_ 8.23
  • Code suggests tonnes should be rounded to
  • 11Mt (11Mt /- 500kt, /- 4.5 error)
  • Code suggests grade should be rounded to
  • 8.2 (8.2 /- 0.05, /- 0.6 error)
  • Metal content error, /- 5.1
  • Very hard to achieve that accuracy in resource or
    reserve estimates, particularly at the
    Feasibility Study stage.

39
ESTIMATION UNCERTAINTY
  • measured resource --gt proved reserves
  • /- 10 to 15
  • indicated resource --gt probable reserves
  • /- 15 to 25
  • inferred resource /-50
  • This inherent uncertainty is not made obvious
    when reported under the JORC code

40
CUT-OFF GRADE, NATURAL OR ECONOMIC
  • Factors affecting cut-off grade
  • Revenue/tonne at average grade and at cut-off
    grade
  • Mining dilution and ore continuity
  • Metallurgical performance
  • Fixed, variable and marginal costs
  • Ease of application
  • Lead time to production
  • Changes in external variables

41
CUT-OFF GRADE CHANGES
  • may affect the following parameters
  • Ore continuity
  • Minable reserves
  • Open pit and stope designs
  • Operating costs/tonne
  • Fixed costs/tonne

42
OTHER RESOURCE AND RESERVES MATTERS
  • Top cuts
  • Samples above the top cut are not as
    representative as samples below the top cut
  • correction factors
  • empirical factors based on mining performance
Write a Comment
User Comments (0)
About PowerShow.com