Title: MINE ECONOMICS
1MINE ECONOMICS
Resource estimates and other technical
inputs. JORC Code Ed Malone
2THE RESOURCE IS PARAMOUNT
- NO RESOURCE, NO PROJECT
- THE INTERACTION BETWEEN THE RESOURCE AND THE
TECHNICAL OPTIONS DEFINES THE NATURE OF THE
DEVELOPMENT
3 EFFECTS OF RESOURCE TYPE
- grade estimation versus homogeneity
- the nature of gold resources
- comparison with other resource types
- nature of resource affects resource estimation
4THE MINERAL RESOURCE
- Knowledge of the resource is essential for
successful development - Inaccurate resource estimates are the most common
causes of project failure - Tomic paper illustrates this for gold projects
Paper by Bruce Tomic, RI Bank of W A - To SMEDG Resource Estimation Symposium, Sydney,
16/10/92
5300 project proposals submitted to RI Bank
during 80s mining boom
- 82 Feasibility studies reviewed in detail
- (Rest of submissions were totally inadequate)
- 63 of the 82 proposals were developed generally
with a mix of debt and equity - 31 of the 63 developments had failed or were in
trouble within 18 months of commissioning
6Review of 82 F. studies
- Cap. Ex. Range A1M to A100M (All very small to
small-medium) - Project types
- 57 new projects
- 34 upgrades of operating projects
- 9 reopening old projects
- Mining method 70 open pit and 30 underground
7Postmortem review of 63 projects
- Significant concerns in F. studies
- 82 Insufficient mineable reserve tail
- 76 Resource uncertainty
- 43 Mining method uncertainty
- 29 Metallurgical performance uncertainty
- 9 Environmental performance uncertainty
- Project performance does not correlate well with
feasibility study review
8Echo Bays Cove Gold Project, Nevada, USA
- Reserves estimate, 23/12/88 9.6M oz contd. AuEq
in proved probable inferred reserves - Revised estimate, 16/02/90 5.5M oz contd AuEq,
still proved, probable inferred - Of 560 RCP holes originally, 137 holes, mostly
deeper than 300m, eliminated because of
contamination of samples
9Exxons Harbourlights, W. A.
- March, 84 Reserves estimate 5.5Mt_at_4g/tAu _at_
1.5g/tAu cutoff - 0.7M oz contd. Au
- July, 85 Mine opened
- June, 87 revision
- Mined to date, 1Mt_at_3.5g/tAu
- Reserves, 2.5Mt_at_3g/tAu _at_ 1.25g/tAu cutoff
- L G reserves, 1Mt_at_1.8g/tAu
- 0.42M oz contd Au
- Downhole smearing of grade in RCP holes
10Agricola Mine, Qld. Nov. 1987
- Lode 1 Reserves, 82,000t_at_4.5g/tAu mined
65,200t_at_3.8g/tAu - Lode 2 Reserves, 174,000t_at_5.5g/tAu mined
52,300t_at_4.8g/tAu - Total 60 contd Au shortfall
- Geological misinterpretations
- Au sale price, A630/oz production cost A683/oz
- Debt, A4.5M gold loan, repayable by 7419oz Au
produced 13,520oz Au
11Shamrock mine, Qld.
- Reserves, 344,000t_at_3.2g/tAu
- Nov, 90, reconciliation after initial 5 months
mining - Predicted, 75,000t_at_4.5g/tAu
- Mined, 49,000t_at_2.8g/tAu
- 45 gold shortfall A1.4M cashflow shortfall
bankrupt. - Geological error, mining method error, management
failings - Postmortem re-estimation 308,000t_at_3.2g/tAu, 21
gold shortfall.
12Henty Mine, Tasmania
- Premining reserves, 506kt_at_27g/tAu
- Mining commenced April, 1996
- Reserves, 30/6/96 526kt_at_26.2g/tAu
- Reserves, 30/7/96 381kt_at_28.4g/tau
- Depletion in year 73kt_at_21.1g/tAu
- Reduction of reserves 72kt_at_19.7g/tAu
- Loss of reserves 10 of contained Au, near
limit of accuracy of proved reserves.
13Underestimates common
- Paddington, W A
- Original resource, 8.4Mt_at_3.2g/tAu
- Production, 19.2Mt_at_2.3g/tAu
- Mt Muro, Indonesia
- Original reserves, 8.5mt_at_3.9g/tAu,86g/tAg
- Production, 11.2Mt_at_3.8g/tAu,99g/tAg
- Ernest Henry, Qld., Peak Mine, Cobar, NSW, and
others
14NATURE OF THE RESOURCE
- CONTROLS THE DEVELOPMENT
- DIFFERENT ARRAYS OF TECHNICAL INPUTS REQUIRED FOR
DIFFERENT COMMODITIES - GOLD PROJECTS ARE DISTINCTIVE
15OPTIMUM DEVELOPMENT
- REQUIRES THE CORRECT BLEND OF MAJOR TECHNICAL
OPTIONS - RESOURCE DEFINITION, MINING METHOD, TREATMENT,
SALABLE PRODUCT SELECTION, MARKETING - BEST POSSIBLE MINOR TECHNICAL OPTIONS
16TECHNICAL STAFF ROLE
- DEFINE RESOURCE
- IDENTIFY AND REVIEW POSSIBLE OPTIONS IN
CONJUNCTION WITH MARKETING AND MANAGEMENT - DEFINE RESERVES, MINING METHOD, MILLING AND
SALABLE PRODUCT/S FOR VIABLE OPTIONS - CONTRIBUTE TO FINANCIAL MODELLING
17FINANCIAL EVALUATION
- RANKS THE DEVELOPMENT OPTIONS
- BUT
- CANNOT JUDGE THE TECHNICAL INPUTS
- NOR
- RECOGNISE IF THE OPTIMUM DEVELOPMENT WAS
CONSIDERED
18MANAGEMENT INPUT
- MAKE NECESSARY STRATEGIC DECISIONS EARLY
- AVOID ARBITRARY REQUIREMENTS
- ASK THE RIGHT QUESTIONS TO IDENTIFY THE OPTIMUM
DEVELOPMENT
19NATURE OF RESOURCE ESTIMATES
- Resource estimates are never accurate
- What is the order of accuracy of the resource
estimate? - Is the project economic at the lower limit of the
resource estimate? - increase the size of the resource or improve the
accuracy of estimation - There is no substitute for a big margin for error
20RESOURCE DEVELOPMENT
- resource --gt minable reserves --gt mill feed
- The mining department mission
- to mine the ore body, the whole ore body and
nothing but the ore body - at the lowest possible
cost - the sting is in the tail
21RECONCILIATION
- The economic resource is not a fixed quantity
- variances between predicted resource and minable
reserves - variances between minable reserves and mill feed
- a reserve tail may be no protection against a
resource shortfall
22MINOR PROBLEMS
- The early mined ore
- Metallurgical performance
- All project components must fit together
- Every project is unique
23RESOURCES AND RESERVES
- Australasian reporting code
- History and future
- Broad definitions only - mainly guiding
principles - Importance of competent person
- ?peer review in future
24DECEMBER, 2004 EDITION
- Expands on 1999 edition to cover diamonds and
industrial minerals in more detail but few
changes in principles - Maintains the large checklist of assessment
criteria - But Code still implies an unachievable level of
accuracy - Still working on Coal draft code
25INTERNATIONAL COMPATIBILITY
- Definitions in 2004 JORC code identical to or not
materially different from international
definitions - Code meets most of main requirements
- Non-technical people can understand
- definitions comprehensive but user friendly
- definitions acceptable to all major players
- capable of amendment over time
- regarded as minimum levels
26INTERNATIONAL INITIATIVE
- 1997 CMMI adopted
- standard international definitions for resources
and reserves - at least for Aa, S A, U K, C, USA (major members
CMMI) - 1998, UN-ECE International Framework
Classification for Reserves and Resources
adopted similar definitions - Spin off from Busang
27(No Transcript)
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32MINERAL RESOURCE CATEGORIES
- Inferred resource
- Indicated resource
- Measured resource
- in order of increasing confidence downwards
- Criteria needing qualification
- Cut-off grade
- Must be potentially economic
33ORE RESERVES
- Probable reserves
- Proved reserves
- Reserve category based on resource category with
option to convert measured resources to probable
reserves - after application of economic, mining,
metallurgical, marketing, legal, environmental,
social and governmental factors
34(No Transcript)
35(No Transcript)
36(No Transcript)
37(No Transcript)
38Example of Rounding, Clause 24
- Calculated resource estimate
- 10,863,000 tonnes _at_ 8.23
- Code suggests tonnes should be rounded to
- 11Mt (11Mt /- 500kt, /- 4.5 error)
- Code suggests grade should be rounded to
- 8.2 (8.2 /- 0.05, /- 0.6 error)
- Metal content error, /- 5.1
- Very hard to achieve that accuracy in resource or
reserve estimates, particularly at the
Feasibility Study stage.
39ESTIMATION UNCERTAINTY
- measured resource --gt proved reserves
- /- 10 to 15
- indicated resource --gt probable reserves
- /- 15 to 25
- inferred resource /-50
- This inherent uncertainty is not made obvious
when reported under the JORC code
40CUT-OFF GRADE, NATURAL OR ECONOMIC
- Factors affecting cut-off grade
- Revenue/tonne at average grade and at cut-off
grade - Mining dilution and ore continuity
- Metallurgical performance
- Fixed, variable and marginal costs
- Ease of application
- Lead time to production
- Changes in external variables
41CUT-OFF GRADE CHANGES
- may affect the following parameters
- Ore continuity
- Minable reserves
- Open pit and stope designs
- Operating costs/tonne
- Fixed costs/tonne
42OTHER RESOURCE AND RESERVES MATTERS
- Top cuts
- Samples above the top cut are not as
representative as samples below the top cut - correction factors
- empirical factors based on mining performance