IPPC implementation in Hungary Points of special interest - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

IPPC implementation in Hungary Points of special interest

Description:

Simplifying the administrative procedure ('one window' system) ... Methods were already in place, taking into account the principle of subsidiarity ... – PowerPoint PPT presentation

Number of Views:101
Avg rating:3.0/5.0
Slides: 22
Provided by: pack57
Category:

less

Transcript and Presenter's Notes

Title: IPPC implementation in Hungary Points of special interest


1
IPPC implementation in HungaryPoints of special
interest
  • Ildikó Babcsány
  • Head of Department
  • National Directorate for Environment, Nature and
    Water
  • Directorate for Environment
  • 26 April, 2004

2
Main objectives of the harmonisation of the IPPC
Directive
  • Meeting EU requirements
  • High level protection of the environment as a
    whole
  • Further implementing integrated approach
  • Simplifying the administrative procedure (one
    window system)
  • Transparency of the permitting procedure (public
    involvement)

3
Legislative background for the integrated
permitting
  • Act LV of 2001 on the modification of certain
    acts with environment protection purpose
    (modification of Act LIII of 1995 on the general
    regulations of the environment protection)
  • Introduces the new definitions
  • Sets the place of the new permit
  • Gov.Decree 193/2001 (X.19.) on the detailed
    regulations of the integrated permitting
    procedure
  • Determines the detailed procedures
  • Framework regulation, the details are in the
    media-specific legislation
  • (Amended by the 47/2004 (III. 18.) Gov.Decree)

4
Scope of the new legislation
  • Annex I as defined in the IPPC Directive
  • Additional activity Mining
  • 13.1. Coal mining from 100 000 t/year, also in
    case of open-cast mining where the surface of the
    site is at least 25 ha
  • 13.2. Extraction of petroleum and natural gas
    where the amount extracted is at least 500 t/day
    in the case of petroleum and 500 000 m3/day in
    the case of gas
  • 13.3. Uranium ore mining where the amount
    extracted is at least 100 000 t/year
  • 13.4. Metal ore mining in case of iron ore from
    1 million t/year, in case of non-ferrous metals
    100 000 t/year extracted, also in case of
    open-cast mining where the surface of the site is
    at least 25 ha

5
Fitting the new permitting into the existing
permit system
  • Installations that are obliged to EIA ?
    environmental permit
  • Installations that are obliged to IPPC integrated
    permit ? integrated permit for the use of the
    environment
  • Installations that are obliged to EIA and
    integrated permit ? integrated permit for the use
    of the environment
  • Environmental audit ? environmental operation
    permit or integrated permit
  • REIs other decisions, expert authority
    statements are integrated into the permits of
    other authorities

6
Main requirements of the legislation
  • Permitting authority is the regionally competent
    environmental authority
  • Construction of the installation can only be
    started after receiving such permit
  • In case of IPPC permit, all permits to be issued
    by the environmental authority shall be
    considered as issued
  • In case the target state of the environment
    requires, requirements stricter than BAT can be
    specified
  • The statements of EIA and Safety Report and
    Analysis has to be considered during permitting
  • Procedure takes 90 days, can be extended by 30
    days
  • 6 months test operation period

7
Integrated permitting procedure
New installations
  • (in case of EIA, decision on the entitlement to
    environmental permit )
  • ?
  • Application for permit (ex officio)
  • ?
  • Involving competent authorities
  • ?
  • Involvement of the public
  • ?
  • Permit

Existing installations
authority obligation for comprehensive
environmental audit
8
Scope of the new integrated permit
  • EIA permitting unit - site
  • IPPC permitting unit - activity
  • boundaries geographic, economic and technical
  • list of IPPC installations in Hungary (January
    2004)
  • less than 10 where installation ? site
  • decision on the boundaries on case by case basis
  • 74 permits so far
  • approximately 1100 installations

9
(No Transcript)
10
(No Transcript)
11
Authorities in IPPC enforcement
  • REIs - at present 12, areas by water catchment
    areas, issuing all environmental permits (and the
    IPPC permit)
  • Water Directorates - at present 12, areas more or
    less the same, issuing water permits
  • under reorganisation, after the merge of the two
    tasks in one ministry
  • IPPC permit covers all environmental media
    aspects, energy efficiency, EMS, decommissioning
  • IPPC permits dont contain water permits, all
    safety issues and building permits

12
Experiences from issued IPPC permits and the list
of installations
  • Most usual cases
  • IPPC activity large combustion plant
  • IPPC activity WWTP or landfill technically
    connected
  • cement kiln nearby limestone quarry (not the
    operation, but noise, dust and the remediation
    activities)

13
Complex chemical site
ethylene
ethylene
LDPE-1 55 kt/y
LDPE
LDPE-2 65 kt/y
ethylene
naphta
Cracker 370 kt/y Ethylene 185 kt/y Propylene
HDPE 200 kt/y
HDPE
ethylene
PP-2 50 kt/y
gas oil
polypropylene
PP-3 105 kt/y
propylene
PP-4 140 kt/y
propylene
C4 C6 C7 fractions, conversion oil, hydrogene
propylene
14
Pharmaceutical factory
basic pharmaceutical products
research and development
formulating
RD
15
Factory for producing electrical equipment
2.6
WWTP
?
hazardous waste storage
production of electrical equipment
painting with pulverised paint and heat hardening
air polluting point source
16
Disintegration of large industrial sites
  • mainly chemical and iron and steel production
    installations
  • usually different owners (economical boundary)
  • if one owner and more installations,
    consultations are needed (technical boundary)
  • Other sensitive issue
  • one owner, more installations (but for the same
    activity) geographically on the areas of
    different REIs

17
Involvement of the public in the permitting
  • Methods were already in place, taking into
    account the principle of subsidiarity
  • Permitting procedure
  • The application for the permit and the
    permitting documentation is open for the public,
    the received comments are evaluated by the REI
    -together with the other competent authorities-,
    and included in the justification part of the
    decision
  • Permit
  • The REI and the municipality notary publishes
    the decision for 15 days for the public
  • Green NGOs rights are set in law, they can act
    as client in environmental procedures

18
Actual needs and developments
  • Authority side
  • Institutional background (ministry, technical
    background institute, permitting authorities) was
    already in place, but it needed enlargement in
    staff
  • Still need of development in staff (importance of
    technological knowledge)
  • Multicountry PHARE project, industrial site
    visits organised by NDENW
  • Information on new aspects diffuse emission
    sources, energy efficiency, cost-effectiveness,
    cross-media effects

19
Actual needs and developments
  • Software development - preparation for data
    supply (EPER, ART 16), register of IPPC
    installations and permits
  • Publishing technological national BAT guidances
  • Finalisation of the application form for the
    integrated permit applications
  • Industry side
  • Costs of complying with BAT requirements is a
    primary aspect for new member states
  • They have to invest in order to being able to be
    competitive on the international market

20
Decision on BAT is supported by
  • The requirements of the Gov.Decree Annex 2
  • The requirements of the media specific
    legislation
  • The NDENW IPPEA Department
  • The development of national guidances based on
    the BREFs and the national characteristics
  • Consultation between authorities and applicants

21
Thank you for your attention!
Write a Comment
User Comments (0)
About PowerShow.com