Title: IPPC implementation in Hungary Points of special interest
1IPPC implementation in HungaryPoints of special
interest
- Ildikó Babcsány
- Head of Department
- National Directorate for Environment, Nature and
Water - Directorate for Environment
- 26 April, 2004
2Main objectives of the harmonisation of the IPPC
Directive
- Meeting EU requirements
- High level protection of the environment as a
whole - Further implementing integrated approach
- Simplifying the administrative procedure (one
window system) - Transparency of the permitting procedure (public
involvement)
3Legislative background for the integrated
permitting
- Act LV of 2001 on the modification of certain
acts with environment protection purpose
(modification of Act LIII of 1995 on the general
regulations of the environment protection) - Introduces the new definitions
- Sets the place of the new permit
- Gov.Decree 193/2001 (X.19.) on the detailed
regulations of the integrated permitting
procedure - Determines the detailed procedures
- Framework regulation, the details are in the
media-specific legislation - (Amended by the 47/2004 (III. 18.) Gov.Decree)
4Scope of the new legislation
- Annex I as defined in the IPPC Directive
- Additional activity Mining
- 13.1. Coal mining from 100 000 t/year, also in
case of open-cast mining where the surface of the
site is at least 25 ha - 13.2. Extraction of petroleum and natural gas
where the amount extracted is at least 500 t/day
in the case of petroleum and 500 000 m3/day in
the case of gas - 13.3. Uranium ore mining where the amount
extracted is at least 100 000 t/year - 13.4. Metal ore mining in case of iron ore from
1 million t/year, in case of non-ferrous metals
100 000 t/year extracted, also in case of
open-cast mining where the surface of the site is
at least 25 ha
5Fitting the new permitting into the existing
permit system
- Installations that are obliged to EIA ?
environmental permit - Installations that are obliged to IPPC integrated
permit ? integrated permit for the use of the
environment - Installations that are obliged to EIA and
integrated permit ? integrated permit for the use
of the environment - Environmental audit ? environmental operation
permit or integrated permit - REIs other decisions, expert authority
statements are integrated into the permits of
other authorities
6Main requirements of the legislation
- Permitting authority is the regionally competent
environmental authority - Construction of the installation can only be
started after receiving such permit - In case of IPPC permit, all permits to be issued
by the environmental authority shall be
considered as issued - In case the target state of the environment
requires, requirements stricter than BAT can be
specified - The statements of EIA and Safety Report and
Analysis has to be considered during permitting - Procedure takes 90 days, can be extended by 30
days - 6 months test operation period
7Integrated permitting procedure
New installations
- (in case of EIA, decision on the entitlement to
environmental permit ) - ?
- Application for permit (ex officio)
- ?
- Involving competent authorities
- ?
- Involvement of the public
- ?
- Permit
Existing installations
authority obligation for comprehensive
environmental audit
8Scope of the new integrated permit
- EIA permitting unit - site
- IPPC permitting unit - activity
- boundaries geographic, economic and technical
- list of IPPC installations in Hungary (January
2004) - less than 10 where installation ? site
- decision on the boundaries on case by case basis
- 74 permits so far
- approximately 1100 installations
9(No Transcript)
10(No Transcript)
11Authorities in IPPC enforcement
- REIs - at present 12, areas by water catchment
areas, issuing all environmental permits (and the
IPPC permit) - Water Directorates - at present 12, areas more or
less the same, issuing water permits - under reorganisation, after the merge of the two
tasks in one ministry - IPPC permit covers all environmental media
aspects, energy efficiency, EMS, decommissioning - IPPC permits dont contain water permits, all
safety issues and building permits
12Experiences from issued IPPC permits and the list
of installations
- Most usual cases
- IPPC activity large combustion plant
- IPPC activity WWTP or landfill technically
connected - cement kiln nearby limestone quarry (not the
operation, but noise, dust and the remediation
activities)
13Complex chemical site
ethylene
ethylene
LDPE-1 55 kt/y
LDPE
LDPE-2 65 kt/y
ethylene
naphta
Cracker 370 kt/y Ethylene 185 kt/y Propylene
HDPE 200 kt/y
HDPE
ethylene
PP-2 50 kt/y
gas oil
polypropylene
PP-3 105 kt/y
propylene
PP-4 140 kt/y
propylene
C4 C6 C7 fractions, conversion oil, hydrogene
propylene
14Pharmaceutical factory
basic pharmaceutical products
research and development
formulating
RD
15Factory for producing electrical equipment
2.6
WWTP
?
hazardous waste storage
production of electrical equipment
painting with pulverised paint and heat hardening
air polluting point source
16Disintegration of large industrial sites
- mainly chemical and iron and steel production
installations - usually different owners (economical boundary)
- if one owner and more installations,
consultations are needed (technical boundary) - Other sensitive issue
- one owner, more installations (but for the same
activity) geographically on the areas of
different REIs
17Involvement of the public in the permitting
- Methods were already in place, taking into
account the principle of subsidiarity - Permitting procedure
- The application for the permit and the
permitting documentation is open for the public,
the received comments are evaluated by the REI
-together with the other competent authorities-,
and included in the justification part of the
decision - Permit
- The REI and the municipality notary publishes
the decision for 15 days for the public - Green NGOs rights are set in law, they can act
as client in environmental procedures
18Actual needs and developments
- Authority side
- Institutional background (ministry, technical
background institute, permitting authorities) was
already in place, but it needed enlargement in
staff - Still need of development in staff (importance of
technological knowledge) - Multicountry PHARE project, industrial site
visits organised by NDENW - Information on new aspects diffuse emission
sources, energy efficiency, cost-effectiveness,
cross-media effects
19Actual needs and developments
- Software development - preparation for data
supply (EPER, ART 16), register of IPPC
installations and permits - Publishing technological national BAT guidances
- Finalisation of the application form for the
integrated permit applications - Industry side
- Costs of complying with BAT requirements is a
primary aspect for new member states - They have to invest in order to being able to be
competitive on the international market
20Decision on BAT is supported by
- The requirements of the Gov.Decree Annex 2
- The requirements of the media specific
legislation - The NDENW IPPEA Department
- The development of national guidances based on
the BREFs and the national characteristics - Consultation between authorities and applicants
21Thank you for your attention!