Title: FEDERALAID LOCAL PROJECTS
1FEDERAL-AID LOCAL PROJECTS
General Requirements and Procedures
District 10 Local Assistance Jesus Serrano, TE
(Civil) Nestor Gavino, TE (Civil)
2INTRODUCTION
- This is an informal training.
- Goal to provide a general understanding of
Fed-Aid project procedures. - Objective to emphasize on submittal
requirements, completeness of Request For
Authorization (RFA) packages, and accuracy of
project data. - Local Assistance Webpage
- http//www.dot.ca.gov/hq/LocalPrograms/
3FINANCIAL MANAGEMENT PROCEDURESPROJECT
AUTHORIZATION/OBLIGATION
NO
YES
4BASIC PROCEDURES
- Federal Aid projects must follow Federal Rules.
- Local Assistance Procedures Manual
- Local Assistance Program Guidelines
- FTIP identifies projects (scope, cost and
schedule) - Must have authorization (E-76) PRIOR to starting
any reimbursable work. - Must have NEPA clearance PRIOR to authorization
of Right-of-Way and Construction funds. - Federal funds get reimbursed after completion of
the reimbursable work.
5CAPITAL OVERSIGHT PROJECTS(on State Hwy. system)
- Project Manager (PM) is Single Focal Point of
contact - All RFA packages go to PM from the Agency.
- PM verifies completeness and accuracy of RFA
package and forwards to Local Assistance (LA) to
process Request for Authorization (E-76) only. - PM needs to sign Finance Letter.
- Capital Subvention Reimbursement (LAPM Exhibit
3-H) request to be submitted by PM. - If required - Cooperative Agreement must be
executed prior to authorization for any phase.
- Project Manager (PM) is Single Focal Point of
contact - Agency can submit RFA package directly to Local
Assistance (LA). - LA Engineer can verify completeness and accuracy
of RFA package. - Capital Subvention Reimbursement (LAPM Exhibit
3-H) request to be submitted by LA (DLAE). - If required - Cooperative Agreement must be
executed prior to authorization for any phase.
6FEDERAL AID PROCESS CHART
PLANNING
DESIGN
ROW
CONST.
FINANCE
At lease once every 6 months for every phase
otherwise the project will be on inactive list
7REVIEW PROCESS
- Request for Authorization (RFA) Packages
- Preliminary Engineering (PE)
- Right Of Way (R/W)
- Construction (CON)
- Award Package
- Federal Report of Expenditures (Final Invoice
Package) - Additional Federal Funds Request (Post
Programming) - Transfer of Federal Funds to FTA
8PE RFA PACKAGES
- LAPM Exhibit 3-A RFA to proceed with PE
- LAPM Exhibit 3-E RFA to proceed Data Sheets
- LAPM Exhibit 3-L Project Prefix Checklist
- LAPM Exhibit 3-O Finance Letter
- LAPM Exhibit 4-A Local Agency Agreement
Checklist - LAPM Exhibit 7-B Field Review Form (required for
HBRR and Seismic Safety Retrofit programs) Needs
to be submitted within 4 months of PE
authorization if not submitted initially - FTIP/FSTIP Page showing programmed funds
- For specific type of projects
- CMAQ Projects -- copy of Emissions Benefit
Calculation (Emission Reduction) - ITS Projects LAPM Exhibit 7-I Systems
Engineering Review Form (SERF) - BRIDGE Projects LAPM Exhibit 7-C Roadway Data
- (Additional documents may be needed depending
upon the project type, see LAPM Chapter 3)
9ENVIRONMENTAL REVIEW
- Local Agency submits Preliminary Environmental
Studies (PES, LAPM Exhibit 6-A) form which
identifies - Scope of Project
- Existing Condition of the Project Area
- Potential existence of sensitive environmental
resources - Required technical studies
- NEPA document classification
10ENVIRONMENTAL REVIEW (cont.)
- Required items for completion of PES form
- Current version of the PES form (May 30, 2008)
- Detailed Project Description on the first page
(use additional page if needed) - Answer all questions on the PES form and document
answers on the comment section - Original signature and date
- FTIP information
- Include required attachments listed at the bottom
of the first page of PES form
11ENVIRONMENTAL REVIEW (cont.)
- Caltrans determines required technical studies
and process NEPA clearance. - NEPA document is valid for 3 years and must be
revalidated if it expires prior to R/W or CON
authorization
12R/W RFA PACKAGES
- LAPM Exhibit 3-B RFA to proceed with R/W
- LAPM Exhibit 3-E RFA to proceed Data Sheets
- LAPM Exhibit 3-O Finance Letter
- LAPM Exhibit 7-B Field Review Form (if not
submitted previously) - LAPM Exhibit 4-A Local Agency Agreement
Checklist - Copy of NEPA document
- Copy of FTIP showing programmed funds
- (Additional documents may be needed depending
upon the project type)
13CONSTRUCTION RFA PACKAGES
- LAPM Exhibit 3-D RFA to proceed with
Construction - LAPM Exhibit 3-E RFA to proceed Data Sheets
- LAPM Exhibit 3-O Finance Letter
- LAPM Exhibit 7-B Field Review Form (if not
submitted previously) - LAPM Exhibit 13-A (No R/W Certification) OR 13-B
(R/W Certification) - LAPM Exhibit 12-C PSE Certification
- LAPM Exhibit 12-D PSE Checklist
- Copy of PSE package
- LAPM Exhibit 15-A Local Agency Construction
Contract Administration Checklist - LAPM Exhibit 4-A Local Agency Agreement
Checklist - Copy of NEPA document
- Copy of FTIP sheet, (Lump Sum Project include
backup list) - (Additional documents may be needed depending
upon the project type)
14CONSTRUCTION RFA (cont.)
Exceptions to RFA for Construction
- For specific type of projects
- (non-construction) rideshare or vehicle purchase
project a work-plan is needed in lieu of PSE
package - (CMAQ Projects) Provide a copy of Emissions
Reduction Calculation Sheet - (Projects on SHS) Provide a copy of Executed
Cooperative Agreement or Encroachment Permits (if
required)
15BRIDGE PROJECTS
- Application for Bridge Projects
- LAPG Exhibit 6-A HBP Application/Scope
definition form - LAPG Exhibit 6-B Special cost approval checklist
- District reviews and forwards the application
to HQ for approval. Local Agency gets
notification when application is approved. After
approval, the agency can program funds through
RTPA/ MPO. Typically, new bridge projects are
programmed into FTIP/FSTIP in September of each
year.
16BRIDGE PROJECTS
- Change of Scope, Cost or Schedule
- LAPG Exhibit 6-D Change of Scope/Cost/Schedule
Request - LAPG Exhibit 6-B Special cost approval checklist
- If there is a scope, cost or schedule change for
the bridge projects, the agency submits LAPG
Exhibit 6-D with justification along with 6-B (if
cost change) to the District. After completion
of review, the District forwards them to HQ for
approval. Local Agency gets notification of
final approval, and then the agency can program
funds through RTPA/ MPO. If additional funds
are needed for the current phase of work, the
agency may not need to wait for FTIP/FSTIP
approval. Contact DLAE for details.
17AWARD PACKAGES
- LAPM Exhibit 15-L Local Agency Contract
Administration Checklist - LAPM Exhibit 15-M Final Detail Estimate
- LAPM Exhibit 15-O Finance Letter
- LAPM Exhibit 15-B Residents Engineers
Construction Administration Checklist - LAPM Exhibit 15-G Local Agency Bidder-DBE
Information - List of Bidder
-
- Note The agency must award the project within
180 days of the authorization date for
construction - (Additional documents may be needed depending
upon the project type, see LAPM Chapter 15)
18FEDERAL REPORT OF EXPENDITURE PACKAGES
- LAPM Exhibit 17-A Federal Report of Expenditures
Cover Letter and Checklist - LAPM Exhibit 17-C Local Agency Final Inspection
Form - LAPM Exhibit 17-D Final Invoice
- LAPM Exhibit 15-M Final Detail Estimate
- LAPM Exhibit 17-E Change Order Summary
- Include Statement of the liquidated damages
and/or contractor claims, if there is any. - LAPM Exhibit 17-F Final Report Utilization of
Disadvantaged Business Enterprises (DBE). - LAPM Exhibit 17-G Materials Certification
- LAPM Exhibit 17-O DBE Certification of Status
Change - (Additional documents may be needed depending
upon the project type, see LAPM Chapter 17)
19INACTIVE PROJECTS
- 6 months rule
- Agency must invoice every 6 months
- Justification letter
- Detail and specific reasons, including backup
documentation - Exception
- Advertisement cost can be charged under PE phase
to make project active, required special
coordination with HQ
20REQUEST FOR ADDITIONAL FEDERAL FUNDS
- Justification Letter with a detailed explanation
why additional funding is being requested - LAPM Exhibit 15-O Revised Finance Letter
- LAPM Exhibit 15-M Revised Detail Estimate
- LAPM Exhibit 17-E Change Order Summary
- LAPM Exhibit 7-B Updated Field Review Form
- Concurrence Letter from MPO/RTPA stating the
changes will not affect their MPO/RTPAs
financial constraint - Note Post Programming should be requested before
completion of the project - Up to 20 of obligated amount
21Transfer of Federal Funds to FTA Package
Transfer of Federal Funds to FTA
- LAPM Exhibit 3-J Request for transfer of Federal
Funds to FTA - LAPM Exhibit 3-O Finance Letter
- Grant Application with pending Grant Number
- Caltrans Notification Letter (Sections 5311
5310 only) - FTIP/FSTIP page showing programmed funds
22FORMAT REQUIREMENTS
- Use the most current version of the Exhibits
- Do not modify the Exhibits
- Do not remove headers and footers (Always show
Exhibit number) - Use online forms (you may use prior project forms
for reference only) - If the Exhibits are not applicable for specific
project, print N/A on the checklist and include
the Exhibit in the package (for final invoice
package)
23COMMON DISCREPANCIES
- Incomplete Packages
- Delays depend on level of incompleteness
- Will be returned for completion if Exhibits are
missing, incomplete or inaccurate. - May be rejected due to lack of justification.
- Inconsistency of cost estimate in field review
form and finance letter - Inconsistency in Funding info FTIP, Finance
letter, detail estimate for all, Field Review - Inconsistency in Data sheets
- The often used of old/previous project
information - Missing signature
- Lack of Justification.