Title: Roads Sector Policy Support Programme Review
1Roads Sector Policy Support Programme Review
- FINDINGS OF PHASE 1 REVIEW AND MID-TERM
EVALUATION OF ONGOING SPSP - DAG Transport TWG, 26 February 2008
2Objectives of Study
- To analyse the achievements and possible
shortcomings of the ongoing SPSP with a view to
formulate a proposal for continuation, taking
account of the lessons learnt - The analysis should be based on seven key areas
of assessment - Determine whether the May 2005 report is still
valid or needs to be adapted
3Objectives of Phase 1
- To assess the relevance, effectiveness,
efficiency, impact and sustainability of the
ongoing SPSP - Re-assess the seven key areas
- Describe lessons learnt so far
- Draw conclusions
- If necessary, propose adaptations for a future
continuation of the SPSP
4Objectives of Phase 2
- Based on the outcome of Phase 1, formulate a
second SPSP for financing under EDF 10
5Objectives of Phase 3
- Based on the outcome of Phase 2, prepare a draft
financing proposal
6The Study Timetable
7Objective of Presentation
- To present the findings of Phase 1, especially
- Lessons learnt so far
- Conclusions
- Proposed adaptations
8The Seven Key Areas
- Sector policy and strategy
- Sector budgeting and its medium-term perspective
- Sector and donor coordination
- Institutional setting and capacity issues
- Performance monitoring systems
- Macroeconomic framework
- Public financial management
9The Seven Key Areas
- Sector Policy and Strategy
101. Sector Policy and Strategy
- Is Ethiopias sector policy and strategy coherent
with the national poverty reduction strategy as
enshrined in PASDEP? - Only partially
- Inadequate provision of sustainable road
infrastructure to the rural population - Development of strong management and technical
capacity to manage the network is lacking at
regional and woreda level - The capacity of the domestic road construction
industry is still too low and development efforts
weak
111. Sector Policy and Strategy
- Does the policy need to be reviewed and adapted
in the light of the National Transport Master
Plan? - Yes
- If plan adopted, will recommend a significant
shift of resources towards woreda and community
roads, with long-term goal of all kebeles being
connected to the network - Plan also includes a 20-year programme to develop
a cadre of rural labour-based contractors
nationwide - Plan includes strengthening MWUD and allocating
clear responsibility for this 20-year programme
121. Sector Policy and Strategy
- Is the policy and strategy widely agreed by the
sector stakeholders? - No
- RSDP achievements welcomed, but Ministries of
Health, Education and Agriculture all requesting
roads to kebele centres as part of national
development strategy - TA also thinks balance is wrong
- TA thinks there is not enough transport-related
education in the sector. Contractors say the
same from their perspective - Coordination and consultation on safety and plans
is not effective enough - Widespread ignorance of RSDP which is presented
without sufficient prior dialogue in any
formalised way. RSDP is not the only element of
roads sector policy though it is often seen as
such
13The Policy Instruments
141. Sector Policy and Strategy
- Lessons learnt
- There needs to be a much stronger policy dialogue
leading to a comprehensive roads sector policy
document
15The Seven Key Areas
- Sector Budgeting and its Medium-Term Perspective
162. Sector Budgeting
- Is the 3 years expenditure forecast of RSDP-III
realistic and affordable? - No
-
172. Sector Budgeting
- Is GOE budgeting for roads sector conducive to
bring about improvement at regional, district and
sub-district level regarding access to transport?
- No
- No mechanism to ensure that block grants are
sufficient for the purpose and are being
allocated sufficiently for roads at regional,
district or sub-district level
182. Sector Budgeting
- Are collected road user charges sufficient to
maintain Ethiopia's expanding road network and to
sustain the considerable investments in the
sector infrastructure? - Seemingly not
- For 2007/08 total requests of 1.5 billion birr
exceed available resources of 1.2 billion birr - The real need is said to be greater than the
requests - Projections need to be made for subsequent years
192. Sector Budgeting
- Lessons learnt
- Initial political commitment to RSDP-III is not
proving to be financially sustainable - Mechanisms need to be developed for effective
and sufficient federal support to regional and
local levels
20The Seven Key Areas
- Sector and Donor Coordination
213. Sector and Donor Coordination
- Is ERA effectively leading the coordination of
the sector development partners? - Yes, but
- Does ERA represent the roads sector as a whole
and all aspects of the policy?
223. Sector and Donor Coordination
- Is the coordination process formalised and
accepted by the sector stakeholders? - No
- No evidence found of a formalised and accepted
coordination process that includes other
Ministries, the TA, Road Fund or other
stakeholders.
233. Sector and Donor Coordination
- Are the sector donors subscribing to the concept
of a sector-wide approach with sector budget
support as the preferred financing modality? - Only partially
- European Commission yes
- DFID partly
- Others no.
243. Sector and Donor Coordination
- Lessons learnt
- A more holistic leadership with a formalised and
agreed coordination process could encourage more
sector budget support
25The Seven Key Areas
- Institutional Setting and Capacity Issues
264. Institutional Setting and Capacity Issues
- How do ERA and other key agencies assess their
institutional performance from year to year? - ERA amount disbursed (fivefold increase in 10
years.). (The workload has increased, and
physical and financial targets are being met.)
Indicators produced by consultants appear to be
secondary. BPR is assessing performance but this
is not an annual exercise. - For both construction and maintenance, monthly
reports of progress against plan are evaluated
internally but assessment of the quality of the
works is at local level. - RF biannual meeting with road agencies to
compare performance against plan, identify
bottlenecks and prepare next annual plan.
Internal assessment as to whether on track
against plan. - Others MWUD has delegated most responsibilities
to ERA oversight is by Board, not by Ministry.
But ERAs performance has improved they are
spending all the money.
274. Institutional Setting and Capacity Issues
- Are staff development programmes of sector
agencies effective and efficient and how is this
measured? - Efforts being made throughout public sector, but
staff turnover is high - There is inadequate training for contractors,
traffic police and others
284. Institutional Setting and Capacity Issues
- Are staff and resources used in an optimal way?
- No
- Resource planning practices by most of the
agencies need substantial and urgent
improvement the resource planning and
management practices of the DMOs are the worst - Increased workload and staff shortages mean that
staff are being more intensively utilised than
before. BPR may increase efficiency and
effectiveness - Question has been raised as to whether the Road
Fund needs to spend so much time double-checking
performance on maintenance contracts, when ERA
has already conducted its own checks - Compared with RRAs and MRAs. Consultancy
Contract for Financial and Technical Audit
Services, Louis Berger with Afro-Consult, August
2005
294. Institutional Setting and Capacity Issues
- What are the key issues regarding the development
of the domestic consulting and contracting
industry and how can development partners assist? - Contractors are new since last 12 years and have
short track records, low experience and not
enough training - Equipment tends to be poor and the pay for scarce
equipment operators is very high only Alemgena
can train for whole country. Chinese now
bringing own operators - Lack of finance and lack of financial and project
management skills - Payment delays, design changes, contract
documents not clear, etc. leads to claims.
Lack of materials testing facilities - Lack of joint ventures which could help skills
transfer - Lack of arbitration means that the only recourse
to solve disputes is to courts - Most useful assistance would be to help MWUD
prepare and implement a holistic programme for
contractor development, including for RADA and
equipment rental, training of skilled people
304. Institutional Setting and Capacity Issues
- Lessons learnt
- There is no overall institution responsible for
the roads sector - There is a need for an anchoring ministry
- Sector budget support must include strengthening
MWUD.
31The Seven Key Areas
- Performance Monitoring Systems
325. Performance Monitoring Systems
- Are the mechanisms of monitoring and performance
assessment adequate and do they render reliable
results? - Monitoring RSDP 16 indicators
- Density. OK.
- Traffic flow OK when number of counting stations
consistent - Roughness/road condition/VOC road condition
assessment only and apparently based on different
3000 km each year - Freight and passenger tariffs OK at federal
level - Fatalities/accidents per vehicle should be
vehicle-km? - Maintenance budget, expenditure and km
maintained unclear - Maintenance costs unclear
- Time for contract administration difficult to
understand no data for latest year - Private/total construction ratio some weird
fluctuations, includes international - Labour-based/total construction ratio sharp
fall, recording method questioned - Actual axle load/legal limit ratio OK, but
overloading is not just axle load issue - Construction, rehabilitation and maintenance
costs figures incomplete - Journey time unclear how assessed buses and
trucks lumped together - Employment opportunity for local labour figures
unclear and strange fluctuations - Income generation source not stated
- Improvement in skill levels (road works) falling
but figures not presented - Conclusion clear report summary, but data
sources and figures unclear
335. Performance Monitoring Systems
- Are the mechanisms of monitoring and performance
assessment adequate and do they render reliable
results? - Determining variable tranche disbursement 10
indicators - Density. Based on all standards roads, but
figures seem to be based on the classified
network - Accessibility based on land area, not
populations or kebele centres - Maintenance asphalt roads in good condition
OK, but what per cent of roads are asphalt? - Maintenance gravel roads in good condition OK
- Maintenance expenditure of Road Fund OK
- Axle load control average overload of trucks
OK for protection of network, not enough for
safety - Private sector development figures include
international contractors (75) - Capturing Road Fund in the budget OK
- Institutional capacity-building based on
schedule, not on programme - Road safety OK
- Conclusion need to develop clearer policy
objectives with related performance indicators
and targeted data collection
345. Performance Monitoring Systems
- Are the indicators well chosen and consistent to
assess the sector achievements from year to year? - Four areas in particular need attention
- Accessibility need to identify at woreda and
kebele level - Condition needs more formal assessment and needs
to include per cent of network that is paved - Procurement and contract administration, and time
for payments - Private sector development should identify
domestic contractors by size of contractor
355. Performance Monitoring Systems
- Is the process of stakeholder consultation and
the flow of information widely accepted as being
sufficient and adequate for decision-making? - No
- Annual reports not available in English
- Big data gap regarding woredas and kebeles
- Lack of overall responsibility for the
implementation of the road sector policy - Consultation on policy, RSDP-III and ERA
restructuring needs greater focus
365. Performance Monitoring Systems
- Lessons learnt
- A Roads Department is needed in the Ministry of
Works
37The Seven Key Areas
386. Macro-Economic Framework
- Is the present process of assessing the
macro-economic context adequate and providing
reliable information for decision making? - Yes, but
- Although the overall macro-economic assessment
taking into account total estimated revenues,
loans, assistance and debt service and
expenditure at federal and regional level appears
to be sound, - the current budget process is inappropriate in
terms of priority setting and achieving policy
objectives. The budget is based on a line-item
classification looking at inputs rather than at
prioritising expenditure with the aim of
achieving policy goals
396. Macro-Economic Framework (continued)
- Programme budgeting is being introduced (pilot
implementation is ongoing with IMF support) to
integrate strategic planning with financial
planning and management. A programme means a
group of activities and projects under a single
manager which uses resources to contribute to a
single policy objective
406. Macro-Economic Framework
- Lessons learnt
- Programme budgeting would really be meaningful
once we have a comprehensive programme to
support, linked to policy and with an anchoring
institution for implementation
41The Seven Key Areas
- Public Financial Management
427. Public Financial Management
- Are the present methods of assessing budget
credibility, comprehensiveness and unification
adequate for decision making? - Not yet
- Large variations between original budget and
expenditure outturns for ERA in particular in
2005/06 (20 underspending) and also 2006/07 (6
underspending) - Budget does not include Road Fund
- Medium-term budget does not yet fully unify
recurrent and capital expenditures (although this
will be rectified under programme budgeting)
437. Public Financial Management
- Are procurement procedures used by ERA and other
sector agencies transparent and according to best
international practices? Do they provide value
for money? - Yes and no
- So long as planning, control and design
procedures are inadequate, procurement procedures
cannot provide value for money
44 7. Public Financial Management
- Do sector agencies provide timely audited
accounts and reports that confirm good financial
management? - MOFED audit report 2005/06 (only in Amharic)
reveals problems, audit not finalised - ERA 2005/06 audit report reveals problems,
especially at District level - RF 2005/06 audit report is unqualified (i.e.
satisfactory)
45 7. Public Financial Management
- Lessons learnt
- Budget reform is in its initial stages and needs
to be continued - Better planning control and project preparation
needed - Financial management needs to be strengthened
especially at the level of MOFED, which is the
receiver and disburser of sector budget support
46Conclusions and Suggested Adaptations of SPSP
- Conclusion 1
- The sector policy needs to be modified to include
the development of a comprehensive sector policy
that includes local roads and contractor issues,
with clear overall responsibility anchored in
MWUD, and a realistic match between plans and
resources - Suggested adaptation to SPSP
- A target date should be set for agreement on
such a holistic policy, with anchorage in MWUD
implemented by the end of SPSP 2
47Conclusions and Suggested Adaptations of SPSP
- Conclusion 2
- It is essential to strengthen MWUD with a Roads
Department to take this responsibility (including
ERA, Road Fund) and establish linkages with RRAs,
CRs (RADA?), Transport Authority, Traffic Police
and domestic construction industry. - Suggested adaptation to SPSP
- Such a strengthened MWUD should be included in
the supported policy
48Conclusions and Suggested Adaptations of SPSP
- Conclusion 3
- Budget reforms should continue and credible,
unified and comprehensive linkages with policy
and plans should be developed - Suggested adaptation to SPSP
- There should be progress towards a holistic and
realistic programme budget for the roads sector,
anchored in MWUD and in the agreed policy
49Conclusions and Suggested Adaptations of SPSP
- Conclusion 4
- MWUD must ensure formalised consultation with
sector stakeholders - Suggested adaptation to SPSP
- Consultation processes and events can be
included in the performance indicators for
variable tranche disbursement
50Conclusions and Suggested Adaptations of SPSP
- Conclusion 5
- For ERA reorganisation, consultation with donors
is essential. There is also a need to review
designs and specifications for road works - Suggested adaptation to SPSP
- None as such, but should ERA reorganisation be
delayed until the holistic policy is in place and
the future MWUD/RD role defined?