Title: RemoteHandled Transuranic Waste Disposition Discussion
1Remote-Handled Transuranic Waste Disposition
Discussion
- Meeting of the National Governors Association
- April 12, 2001
2Topics To Be Discussed
- Definition of RH TRU Waste
- Volume of RH TRU at DOE sites
- Regulatory strategy for disposal of RH TRU at the
Waste Isolation Pilot Plant (WIPP) - Requirements and considerations for approval
- RH shipping casks
- Small Quantity Sites (SQS) strategy
- Current schedule
3Definition of RH TRU Waste
- TRU waste is waste containing more than 100
nanocuries of alpha-emitting transuranic isotopes
per gram with half-lives greater than 20 years - RH TRU waste has an outer surface dose rate of
greater than 200 millirem per hour - Homogeneous solids, debris, soil, and gravel
4Volume of RH TRU at DOE Sites(Stored and
Projected)
Hanford 900 m3
KAPL
INEEL 85 m3
10.5 m3
WV (2)
479 m3
ANL-W 54.5 m3
BAPL
3 m3
20.8 m3
BCL
ANL-E 77 m3
GE Vallecitos (1)
11.8 m3
LANL
ORNL
ETEC 8.7 m3
123.5 m3
2253.5 m3
SNL 25.5 m3
Source The National TRU Waste Management Plan,
Revision 2 (December 2000) (1) Waste may not be
of defense origin compliance with LWA
requirement will need to be demonstrated prior to
disposal at WIPP.(2) Waste is commercial and
does not meet the LWA requirement for disposal at
WIPP.
5Regulatory Strategy for Disposalof RH TRU at WIPP
- Characterization program to be proposed to the
Environmental Protection Agency (EPA) and New
Mexico Environment Department (NMED) is
performance-based, responsive to - ALARA requirements
- Joint EPA/NRC guidance
- NAS recommendations
- Acceptable Knowledge is the focus of the
program, where available, to meet Compliance
Certification, Land Withdrawal Act and RCRA
requirements - This strategy may require EPA rule-making and
NMED Class 3 permit hearings
6Requirements and Considerations forEPA and NMED
Regulatory Approval
- DOE to submit RH characterization program to EPA
that meets WIPP Land Withdrawal Act and 40 CFR
191/194 requirements, and EPA approves via 40 CFR
194.8 process - New Mexico Environment Department must approve
modification to the WIPP Hazardous Waste Facility
Permit - DOE to submit to NMED
- RH Facility Modification Request
- RH Waste Analysis Plan
- NMED issues draft and final permit allowing RH
TRU waste storage and disposal
7Requirements and Considerations for EPA and NMED
Regulatory Approval (cont.)
- Informally discussed draft RH TRU
characterization process document and supporting
position papers with EPA, March 14, 2001 - Two permit modification requests to be submitted
to NMED, summer of 2001 - Independent review of performance-based approach
by NAS or outside organization is expected
8RH Shipping Casks
- RH-72B
- Outer thermal shield
- Inner/outer containment vessels with impact
limiters - 12 feet long 3.5 feet diameter
- 1-7/8 inch lead liner
- CNS 10-160B
- Carbon steel- and lead-shielded shipping cask
- Steel-encased, rigid polyurethane foam impact
liners on top and bottom - Cavity height 77 inch diameter 68 inch
- Wall thickness 4 in. including 1.875 inch lead
9Small Quantity Site Strategy
- Ship directly to WIPP is the preferred option
- Where there are site closure considerations, DOE
is continuing to examine intersite transfers - Feedback requested from State representatives on
moving forward with contingency planning for
sites with closure schedules.
10BACKUP SLIDES
11Battelle Columbus Laboratory Summary
- Shipments of 25 m3 of RH TRU waste (100-120
drums) must start by September 2001 to support
site closure schedule - TRU waste must be removed from current hot cell
building so that DD can proceed- Need to move
offsite or into a new storage building - Activities required for new building include NEPA
action, license amendment, RCRA permit, design,
and construction - Cost of permitting, NEPA analysis, design,
construction, and critical path delays 10-15
Million (one years) - Decision about new storage building needed by
June 1, 2001 - Oak Ridge and Hanford considered as receiving
sites - Ohio EPA has had previous conversations with
counterparts in both Tennessee and Washington
state - Tennessee sent a letter in February 2001 to DOE
stating they did not support receipt of RH TRU
waste from offsite until Oak Ridge begins
shipping RH TRU to WIPP - State of Washington has also sent a letter (March
2001) stating they did not support receipt of RH
TRU waste from offsite until Hanford begins
shipping RH TRU to WIPP - Oak Ridge scheduled to begin shipments of RH TRU
to WIPP in January 2003 - Hanford scheduled to begin shipments of RH TRU to
WIPP in 2011-2015 timeframe
12Energy Technology Engineering Center Summary
- Shipment of RH TRU waste (up to 8.7 m3) must
start by September 2002 to support site closure
schedule - Waste must be removed from Radioactive Materials
Handling Facility before DD can begin - CH waste must also be removed
- Current schedules for RH permit modification
supports ETECs closure schedule - Need to finalize decisions on ETEC RH TRU in
early CY 2002
13Argonne National Laboratory - East Summary
- RH waste in inventory will be shipped directly to
WIPP when permit modifications approved -
currently schedule in FY 2003 - RH waste generated in future (post-2006) will
also be shipped to WIPP directly - Mobile Vendor Units will be deployed onsite to
characterize contact-handled (CH) waste - CH characterization schedule to be completed in
December 2001
14Oak Ridge National Laboratory Summary
- Oak Ridge has large quantity of RH sludges
requiring treatment before shipping to WIPP - Foster-Wheeler contract in place to perform all
treatment and necessary characterization for
disposal at WIPP - Shipments of RH TRU scheduled to begin in January
2003 - Oak Ridge has smaller amounts of CH TRU that are
scheduled to be shipped to WIPP beginning in FY
2004
15HALFPACT CASK
16SCHEMATIC OF THE RH-72B CASK
17R H - 72B CASK