Title: Sahtu November 29, 2001 presentation


1
Mackenzie Gas Project Next Steps Toward
a Mackenzie Valley Natural Gas Pipeline APEGGA/C
SEM Joint District Meeting Luncheon Edmonton R.J
. Ottenbreit, PEng May 2003
2002-09-16 XP06432_7
2
Significant Discoveries - Onshore Gas
  • Taglu - 3 TCF
  • Discovered 1971
  • 100 Imperial Oil
  • Parsons Lake - 1.8 TCF
  • Discovered 1972
  • 75 ConocoPhillips Canada
  • 25 ExxonMobil Canada
  • Niglintgak - 1 TCF
  • Discovered 1973
  • 100 Shell Canada

3
Development Concept Overview
  • Canadian onshore gas, three anchor fields
  • Mackenzie Valley Pipeline
  • Proven technology
  • Minimize the environmental footprint
  • Producer capacity of 800-1000 MCFD
  • Aboriginal capacity up to 400-500 MCFD
  • Accessible to others
  • Utilizes ullage in existing pipelines
  • liquids to Enbridge
  • gas to TCPL

4
Mackenzie Gas Project - Phased Approach
Feasibility Study
Decision to prepare regulatory applications
Complete
Project Definition
Decision to construct
  • concurrently assess external matters
  • assess natural gas markets
  • assess reserves
  • little, if any, field work

3 - 4 years
Design and Construction
  • engineering studies
  • environmental field work
  • public consultation
  • northern benefits plans
  • regulatory applications
  • regulatory review process

3 - 4 years
Operations
  • detailed design of facilities
  • drill wells
  • purchase goods and services
  • construct pipeline and field facilities

25 years
gas sales
  • potential expansion
  • abandonment and reclamation

5
Project Definition Phase
  • Agreed on way to proceed while awaiting APG
    funding
  • Secured office space and began staffing project
    team with co-venturers
  • Broadened communications and consultation
    activities
  • opened representative offices in Fort Simpson,
    Norman Wells and Inuvik
  • Awarded engineering contract and began conceptual
    engineering
  • Initiated phased open season process with
    potential shippers
  • Continued collecting baseline environmental data
  • Developed Preliminary Information Package
  • Started development of benefits plans, access and
    related arrangements
  • Field work to study river crossings, permafrost,
    route refinement and granular sites

6
When Will Mackenzie Gas be Commercial?
  • Development can only proceed when all these
    conditions exist
  • Northern parties must be supportive of
    development, and in agreement with its benefits
  • Outlooks for natural gas markets must be
    favourable
  • Discovered onshore natural gas reserves must be
    large enough, and certain enough
  • Investor economics on a standalone basis must
    be competitive with other opportunities, and
    sufficient for the risks involved (gas reserves,
    costs, gas markets)
  • Facility plans and designs must ensure safe,
    reliable and environmentally responsible
    operations
  • Regulatory approvals must be obtainable in a
    timely manner
  • Stable and favourable fiscal terms
  • Pipeline investment costs must be financeable