Title: Diapositiva 1
1(No Transcript)
2 TIPEIL LLP-LDV/TOI/07/IT/019 First
Transnational Workshop Athens, 7-8 February
2008 Venue IEKEP - 34A Averof str. in Nea
Ionia 1st floor PROJECT WORKPLAN
3PROJECT TIMING
The Project starting date is the
15/11/2007 The Project closing date is the
14/11/2009
4WHAT IS A TOI TRANSFER OF INNOVATION PROJECT?
A ToI project aims at the transferring of a
Model within Systems related to the different
national contexts involved in the partnership
called to implement the project itself. TOI
proposals start from a product (prototype)
created during the realisation of a previous
project, considered as a good practice. Products
can include methodologies, coursewares, tools,
etc., that is, everything that is transferable on
a wide scale.
5WHAT IS A TOI TRANSFER OF INNOVATION PROJECT?
- As basic actions, a ToI proposal must imply
- the identification of a prototype
- the diversification/enlargement of the
partnership involved in the new project
(different national contexts with respect the
ones involved in the previous projects) - the adaptation of the prototype with respect to
- changes that can be occurred within the targeted
sector/system (generally the outputs achieved by
a project are based on analysis of 4-5 years
old) - new needs held by final beneficiaries (for the
same reason mentioned above and also because the
new project can be addressed to different or
wider target groups) - the creation of a wide cooperation network with
national and local institutions, organisations,
stakeholders, etc. - the direct preliminary testing of the Model
proposed by the project with beneficiaries
(experimentation of the beta version of the
Model) - the production of the definite version of the
Model to be transferred - the transfer of the definite Model on large scale
(that means to create the condition on the
territory agreements and to implement a
direct intervention involving a higher number of
beneficiaries).
6TIPEIL TARGET GROUPS
- Direct beneficiaries are included in two main
categories - operators working within training, counselling,
guidance and employment organisations, providing
these services to subjects that, for different
reasons, are in social and occupational
disadvantage -
- 2. organisations providing the services above
mentioned, with respect to 2 main typologies of
beneficiaries young and adults. - Referring to young, the organisations target are
- - Second Chance Schools/Vocational Training
centres or schools - - Training Agencies
- - Guidance/Employment centres
- Universities.
- Referring to adults
- Guidance Services/Centres
- Employment services/agencies
- Associations
- Social partners organizations
- Intermediate Companies (e.g. Temporary works
Agencies)
7TIPEIL TARGET GROUPS
- The whole of outcomes and outputs planned are
indirectly addressed to a range of potential
users as - Young with low education levels who, for example,
have left compulsory education pathways and are
attending or have attended alternative training
coursewares through which have acquired
competences and capabilities difficult to be
valorised or formally recognised by the system
and that are at risk of employment exclusion - Young and adults who have realised fragmentary
and heterogeneous working experiences, within
which have acquired capabilities and skills
potentially usable and improvable if properly
identified, measured and valorised - Adults at risk of unemployment, whose competences
acquired during their work-life-cycle do not meet
within the systems effective tools and devices to
valorise them.
8TIPEIL THE INNOVATION CONTENTS AND GOALS
TIPEIL focuses on the valorisation of competences
that young and adult workers developed within
informal and non formal contexts. The
availability of methods and tools applied to
reach this goal has been identified in the
European Inventory on validation of non formal
and informal learning. If, then, on their side
many countries have implemented specific
initiatives and worked out tools to foster the
recognition of competences acquired outside
education and training formal contexts, due to
their insufficient divulgation, it is still
necessary to strengthen processes for their wide
transfer and application. In this frame,
TIPEIL, based on the successful results achieved
within previous transnational pilot interventions
and experiences, aims at the transferring of a
Model of Digital Portfolio Training courseware
to its use addressed to the operators,
associating to this basic goal the one of
facilitating its adoption through
experimentation, training and coaching activities
addressed to operators to whom will be asked to
use the portfolio within their specific working
contexts. Main objectives are, so, the following
9TIPEIL THE INNOVATION CONTENTS AND GOALS
- Main objectives are, so, the following
- to analyse and promote the willingness to
change/adaptability of the currently practices in
use in the different national contexts, so as to
realise a real integration and permeation among
different needs and cultures - to integrate the contents, already identified and
experimented on transnational dimension, included
in the Model of digital portfolio (methodology
training courseware) on which the proposal is
based - to adapt the prototype at linguistic and
technological level, so as to widen its use and
application, starting from the organisational and
technological analysis of the different national
working contexts represented by the partnership - to transfer directly and efficaciously (through
training and coaching) the adapted prototype to a
wide range sample of organisations that, with
specific sectorial roles all interlinked (e.g.
education, training, counselling, employment,
etc), can benefit from the adoption of the Model
defined.
10WORKPLAN ARTICULATION
- Project Workplan is articulated into 9
WORKPACKAGES. - 3 of them concern the main transversal actions
-
- WP 0 Management and coordination (24 months)
- WP 8 Independent Evaluation (24 months)
- WP 9 Dissemination and Valorisation (24 months)
11WORKPLAN ARTICULATION
- The other 6 WORKPACKAGES are so articulated
-
- WP 1 (2 months) Start up - from 15/11/07 to
14/01/08 - WP 2 (4 months) Analysis of prototype
adaptability in relation to its use in different
contexts - from 15/01/08 to 14/05/08 - WP 3 (2 months) Prototype adjustment and
re-drafting (beta version) - from 15/05/08 to 14/07/08
- WP 4 (4 months) Beta version experimentation -
from 15/07/08 to 14/11/08 - WP 5 (3 month) Dissemination, evaluation and
model adaptation (final version) from 15/11/08 to
14/02/09 - WP 6 (8 months) - Final Model Transfer - from
15/02/2009 to 14/10/2009 - WP 7 (1 month) Final Conference - from
15/10/2009 to 14/11/2009
12WP 1 Start up
(2 months) from 15/11/07 to 14/01/08
13Aims
- To fix the operational and logistic conditions
necessary to the activities start up - To share the working plan in terms of activities,
tasks and responsibilities - To finalize the agreements among the Contractor
and all partners - To share Parameters and Indicators for quality
control, Monitoring Plan and related tools - To share project internal and external
communication plan - To plan and realise tools and channels to be
used for project internal and external
communication - To start up the project dissemination towards
partners networks
14Expected outcomes/outputs
- Identify internal and external communication
instruments and modalities - Creation of project graphic design
- Creation of project website
- Realisation of the 1st Partnership Transnational
Workshop in Athens - Preparatory work documents and Workshop minutes
- Working plan detailed form, describing activities
and liabilities of each partner - Execution of an external communication plan
- Project presentation brochure
- Sub-contracts between partners and Coordinator
- Financial Guarantee (Promoter)
15Role and tasks of partners involved
- P1 - Ce.Ri.S.
- Relations with the National Agency relevant to
project administrative issues. - Agreements with partners (Subcontracts)
- Drafting of internal Monitoring Plan and relevant
instruments - Cooperation in the organization and animation of
1st Transnational Workshop - P2 - IEKEP
- Organization of the 1 partnership workshop (GR)
- P7 - TRUST
- Realisation and production of project Brochure
(IT/EN) - Project website planning, design and realisation
of project graphic design - ALL PARTNERS
- Contracts with Coordinator
- Internal Monitoring Plan Validation
- Draft and transfer of information to be published
on project website - Project website links activation
- Dissemination of information related to the
project within their internal institutional
website - Start up mailing list drafting
- Participation to 1 Partnership Workshop in Rome
16WP 2 Analysis of prototype adaptability in
relation to its use in different contexts
(4 months) from 15/01/08 to 14/05/08
17Aims
- To verify the original prototype (e.g.
transferability towards targets and new
countries, also considering existing rules and
regulations such as Europass, citizen leaflet,
competences analysis) in order to avoid its
redundancy with respect to existing tools. - To identify possible margins of adaptation with
reference to its use - (organizational and technological assets
analysis of the identified centers) - To analyse the availability in changing the
existing practices. - To create a map of potential beneficiaries of the
experimentation and transfer actions planned. - To start-up a process to involve direct or
indirect beneficiaries of project
results/outcomes
18Activities
- Realisation of two main research activities.
- 1. The first, propaedeutical to the second,
relates to the development of a 3 days working
Laboratory, to be held in Rome (IT). - It is necessary to share contents and methodology
of the prototype on which the project is based
(digital portfolio training course) among all
partners. - To the Lab must participate
- Delegates who were in attendance at the 1st
workshop (GR) - 1-2 experts, identified by each partner, for
their expertise in guidance and counselling,
employment, creation and management of
technological informative systems. - The Laboratory will be a working session
composed by groups of experts coming from the 4
countries involved. Each group will have specific
internal competences integrating the others,
necessary to reach the proposed objectives (from
a methodological, content and technical point of
view). - The Lab will be chaired by P6- DPSS 38
representatives and will be articulated as
follows
19Activities
The Lab will be chaired by the University
representatives (P6) and will be articulated as
follows
- - a general informative session to introduce the
prototype features, (1 day) focusing on
contents, technological support, organizational
conditions allowing its use in the current
prototype version - - a discussion session (focus group), (2 days)
aimed at - Receiving a feedback on the product
- Collecting information on the contexts where it
can be transferred - Collecting contributions useful to realise the
next field analysis (interviews). - 2. the second activity (research-action), will be
aimed at the starting up of beneficiaries
involvement in the project, through the
realisation of de visu interviews with the
potential prototype user. - For each Country will have to be run at least 4
interviews (16 in total) with operators working
in - - Second opportunity Schools/vocational training
- - Training Agencies
- - Vocational training centers
- - Universities
- - Associations
- Social partners organizations
- - Intermediate Companies (e.g.Temporary works
Agencies)
20Expected outcomes/outputs
- Lab working material and minutes
- Interview grid Format
- 4 National Study
- 1 Comparative Study
- Information to adapt the prototype on
technological and content terms, according to the
specificities of each national context involved
21Role and tasks of partners involved
P1 - Ce.Ri.S. Management, coordination and
monitoring of research and dissemination
activities Cooperation in the Organization of the
Laboratory P7 - TRUST Informatization of
mailing list produced by all partners and editing
of Newsletter n.1 (on website) Updating project
website Agreement with the expert in charge of
independent evaluation P6 DPSS 38 Management
and animation of the Laboratory to be held in
Rome Scientific supervision of research
activities and quality results P2 IEKEP P3
ETEO P4 ESTIA- P5 SOLCO - P6 DPSS 38 P7
TRUST Realisation of interviews addressed to
operators Drafting of National reports
22Role and tasks of partners involved
P1 Ce.Ri.S. - P5 SOLCO - P6 DPSS 38 P7 TRUST
Work out of Lab working material and minutes and
interview grid format Drafting of Comparative
Report (IT-EN) synthesizing Laboratory and
research outcomes, including information related
to the prototype adjustment, both from a
technological and content point of view,
according to the features of the national
contexts involved. ALL PARTNERS Participation to
the working Lab in Rome Cooperation in the
dissemination of project outcomes/products,
according to activities, modalities and
instruments provided for in the proposed
evaluation and dissemination plan Drafting of
mailing lists and contributions for the
Newsletter n.1
23WP 3 Prototype adjustment and re-drafting (beta
version)
(2 months) from 15/05/08 to 14/07/08
24Aims
- To adjust and re-draft the prototype (digital
portfolio training course) from a linguistic,
technological and content point of view -
- To disseminate project interim products and
outcomes, by a considerable number of
target-entities.
25Activities
The activities will be focused on the development
and production on informatics support, of the
beta version of the Model, according to the
outcomes of all research actions and analysis
realised up to now.
26Expected outcomes/outputs
Beta version of the Model (Portfolio training
model) on informatics support (CD Rom in all
partnership languages EN)
27Role and tasks of partners involved
P1 Ce.Ri.S. Management, coordination and
monitoring of project activities P7 -
TRUST Production of Model beta version (Portfolio
training model) Updating of project website
and Mailing lists P2 IEKEP P3 ETEO P4
ESTIA- P5 SOLCO - P6 DPSS 38 Cooperation in
the model beta version creation (Integration,
updating and translation of Portfolio contents
training model) ALL PARTNERS Cooperation in the
dissemination of project results/products,
according to activities, modalities and tools
provided for in the proposed evaluation and
dissemination plan Mailing lists Updating
28WP 4 Beta version experimentation
(4 months) from 15/07/08 to 14/11/08
29Aims
- To experiment the adjusted Model on a
representative sample of different typologies of
entities, as previously identified on the map, in
the 4 Countries involved in the partnership. - To disseminate interim products and outcomes
achieved, by a considerable number of
target-entities. - To involve direct and indirect beneficiaries of
project products/outcomes.
30Activities
- The Experimentation will be performed on 2/3
entities representative of each category chosen
with reference to target (e.g. schools,
Universities, etc.). - Each partner will have
- to identify the beneficiary-organisations
(Creation of a Map) - to monitor the experimentation phase during its
implementation by the chosen subjects - to tutor the operators in the use of the
Portfolio. -
- The Experimentation activity will be articulated
in two phases - 1. Partners will identify a group of operators,
within the entities where the experimentation
will be executed. To such operators will be
granted 2-days training sessions focused on the
use of the portfolio (1-day front session and
1-day session dedicated to simulations, analysis
and study of situations that might occur in
praxis. - Such action is unavoidable for the execution of
the subsequent phase.
31Activities
2. Successively, for 4 days the trained
operators, accompanied by a coach pertaining to
partner organization, will apply the tool
(digital portfolio) with their beneficiaries-users
. The coaching action will be supported by the
use of a grid for the recording of
operators-users dynamics. The grid will be filed
by the coach during each portfolio creation and
the information collected will be synthesized in
a short outcomes report. On the fifth day
operators and coach will discuss experimentation
outcomes and (if the case) will formulate
possible suggestions related to modifications and
improvements that might be brought to the tool in
its final version. During the experimentation
it is foreseen to produce not less than 5
portfolios for each Country.
32Expected outcomes/outputs
- Contents and didactical material for the 2-days
training session to operators - Dynamic operator/user observation grid and
protocol related - National synthesis report on outcomes and
experimentations trend - Compared experimentation report (approximately 20
Portfolios) - Project Interim Report (for National Agency)
33Role and tasks of partners involved
P1 Ce.Ri.S. Management, coordination and
monitoring of project activities Project Interim
Report P7 - TRUST Updating project
website Mailing lists integration Production of
materials to realise the training sessions
(didactical support) Publication of Newsletter
n.2 on website P6 DPSS 38 Scientific
supervision of experimentation activities and of
outcomes quality Work out of the dynamic
operator/user observation grid (Format) Drafting
and identification of contents, supports and
didactical materials to ealise the training
sessions.
34Role and tasks of partners involved
P2 IEKEP P3 ETEO P4 ESTIA - P5 SOLCO - P6
DPSS 38 P7 TRUST Realisation of activities
aimed at experimenting the Model (beta version)
on local context (identification of entities,
training and coaching) and drafting of National
reports. P1 Ce.Ri.S. - P5 SOLCO - P6 DPSS 38
P7 TRUST Comparative analysis report on
experimentation outcomes (IT-EN) ALL
PARTNERS Cooperation in the dissemination of
project products/outcomes, according to
activities, modalities and instruments provided
for in the proposed evaluation and dissemination
plan Mailing lists updating Drafting Newsletter
n.2 contributions Respect of all the
administrative tasks required to submit the
Interim report to the National Agency
35WP 5 Dissemination, evaluation and model
adaptation (final version)
(3 month) from 15/11/08 to 14/02/09
36Aims
- To adapt and ri-draft the model beta version
(digital portfolio training course) from a
linguistic, technological and contents point of
view, according to experimentation outcomes. - To share possible difficulties encountered during
the activities realised - To verify outcomes performance and expected
results - To share the management and realisation plan
related to the following activities - To disseminate products and outcomes achieved, by
an increasing number of beneficiaries
37Activities
- The phase begins with the realisation of the 2nd
partnership Transnational Workshop and of the 1st
Project Dissemination Seminar (France). - The meeting will be organized within 14 months
from the project start-up and will represent an
important occasion for the partnership to - analyse and share the difficulties encountered
during the experimentation phase - verify the achievement of project outcomes.
- The 1-day session workshop will be functional
both for the preparation of the Dissemination
Seminar to be held on the following day, and for
drafting and sharing operative suggestions useful
for the management and execution of subsequent
adjustment and transfer activities.
38Activities
The 1- day Dissemination Seminar will be focused
not only on the project general presentation, but
also on the sharing and disseminating of the
outcomes achieved, represented mainly by the
Model (portfolio training course) in its final
version. Participants, representatives of all
target groups identified (either those already
involved in the experimentations either those
potentially interested) will be encouraged to
intervene in working groups and round tables that
will typify the seminar trend. In this way,
considering that France will not be actively
involved in the transfer phase of the Model final
version, it will be possible to strengthen its
dissemination also within this national
context. In the meantime the final version Model
will be developed and created on informatics
support, in all partnership national languages.
39Expected outcomes/outputs
- Model final version (Portfolio training model)
on informatics support (CD Rom in all partners
languages EN) - Preparatory materials and workshop Minutes
- Divulgation materials and seminar interventions
Abstract
40Role and tasks of partners involved
In this phase University of Rome, Ceris, TRUST,
Solco e IEKEP will be primarily involved. P1
Ce.Ri.S. P7 TRUST Management, coordination and
monitoring of project activities Support in the
organization and animation of 2nd Transnational
Workshop and of 1st Dissemination Seminar
(France) Production of Model final version
(Portfolio training module) Website and Mailing
list updating P4 ESTIA Organization of 2nd
Transnational Workshop and 1st Dissemination
Seminar P2 IEKEP P3 ETEO P4 ESTIA - P5
SOLCO - P6 DPSS 38 P7 TRUST Cooperation in
final version Model creation (integration and
translation of Portfolio training model
contents) ALL PARTNERS Participation to 2nd
Transnational Workshop and 1st Dissemination
Seminar Cooperation in dissemination of project
outcomes/products Mailing list updating
41WP 6 Final Model Transfer
(8 months) from 15/02/2009 to 14/10/2009
42Aims
To Transfer the final version of the model
(Digital Portfolio training course) to a wider
number of operators and organisations.
43Activities
- The transfer activity structure is similar to the
one provided for in the experimentation phase,
but shall include - The execution on two national contexts (IT/GR)
- The involvement of a wider sample of
beneficiaries - A longer implementation phase.
- The Transfer will be realised within not less
then 10 organisations (representative of each
category chosen with respect to targets), for
each partner involved (tot. 20 at least). - Also in this case, each partner involved (IT/GR)
will have to - identify the beneficiary-organisations (Creation
of a Map) - monitor the experimentation phase during its
implementation by the chosen subjects - tutor the operators in the use of the Portfolio.
44Activities
On the whole, the activity will be articulated in
two phases. 1.Partners will identify a group of
operators to which will be granted a 5-days
training session focused on the use of the
portfolio (1-day front session and 4-days
session dedicated to simulations, analysis and
study of situations that might occur in
praxis. Such action is propaedeutical to the
subsequent. 2. During approximately 15/20 days
the trained operators accompanied by a coach
(pertaining to partner organization) will apply
the tool (digital portfolio) with their
beneficiaries-users. At the end of the transfer
at least 10/20 portfolios for each Country shall
be produced.
45Expected outcomes/outputs
At the end of the Transfer phase must be
available in total 20/40 Portfolios (10/20 for
Italy and 10/20 for Greece)
It is possible to foresee the collection of filed
Portfolios in a database that could be integrated
into existing informative systems already
available in centers where the transfer has been
executed.
46Role and tasks of partners involved
P1 Ce.Ri.S. Management, coordination and
monitoring of project activities P7
TRUST Project website updating Publication of
Newsletter n.3 on website P5 SOLCO - P6 DPSS 38
Scientific supervision of transfer activities
and of outcomes quality P1 Ce.Ri.S. - P2 IEKEP
- P5 SOLCO - P6 DPSS 38 P7 TRUST Execution of
activities aiming to transfer the final Model in
national contexts (entities identification,
training and coaching) ALL PARTNERS Cooperation
in dissemination of project outcomes/products Mail
ing lists updating Drafting of Newsletter n.3
contributions
47WP 7 Final Conference
(1 month) from 15/10/2009 to 14/11/2009
48Aims
- To examine outcomes reached in the execution
process. - To identify strength and weak aspects
- To identify transferability margins and
conditions - To identify instruments and modalities for the
project follow up - To accomplish to obligations provided for in the
Agreement with the National Agency
49Activities
Final conference in Rome, presentation of
outcomes and products, sharing and examining
solutions finalized to enlarge network of
potential users
50Expected outcomes/outputs
- The final outputs of the project to be presented
during the Final Conference are - CD Rom including (around 2000 copies)
- Portfolio Prototype and related tools (protocols
of use - handbook) in all partnership languages
English - Training Module prototype in three languages
guidelines (IT-GR-EN) - Eventually, database of the portfolios produced
- External evaluation report
- Project website
- Project Final Report
51Role and tasks of partners involved
P1 Ce.Ri.S. Management, coordination and
monitoring of project activities Drafting and
presentation of project Final report P7 -
TRUST Publishing of Newsletter n.4 on website
Production and masterization of Final CD Rom
(2000 copies) P1 Ce.Ri.S. - P5 SOLCO - P6
DPSS 38 P7 TRUST Cooperation in the
organization of the project final Conference to
be held in Rome P2 IEKEP P3 ETEO P4
ESTIA- P5 SOLCO - P6 DPSS 38 Participation to
project Final Conference ALL PARTNERS Cooperatio
n in dissemination of all project
outcomes/products Respect of all administrative
tasks expected for the submitting to the National
Agency of the project Final Report Drafting
contributions of Newsletter n.4