Title: Summary:


1
Status of Control Module integration
  • Summary
  • LCM integration PRR
  • (in particular integration rehearsal of last
    week)
  • Preparation for xCM production

2
Control Module production
  • It consists of the following processes

Reception
(transportation)
Storage
Component level
Integration
Module level
Test
Packing (storage)
(transportation)
3
Control Module production scenario
  • All activities under definition based on the
    following considerations
  • Time constraints (schedule request one working
    LCM produced in two days)
  • Manpower needs (one person?)
  • Safety requirements power grounding during
    functional tests, ESD protection, fibre handling
  • Quality Control approach detailed procedure for
    each operation, development of tools
  • Traceability test needs

Target Full system defined and working in time
for the construction of the MILOM modules
(according to the current schedule by end of
June 2004)
LCM integration test for LCM PRR necessary step
to check the overall design of the module from
the integration point of view and in particular
to spot out all possible (minor) modifications to
the module components before the mass productions
start
4
LCM integration tests for PRR
  • First test performed in week 12 (March) report
    available at
  • http//www.ba.infn.it/circella/LCM/LCM_int_first
    _report.pdf
  • Complete rehearsal of the integration performed
    in week 16 (last week) procedure and report
    available at
  • http//www.ba.infn.it/circella/LCM/LCM_integrati
    on_test_prr_10.pdf
  • http//www.ba.infn.it/circella/LCM/LCM_int_secon
    d_report.pdf

Conclusion after both tests NOT READY
(but not so far away from readiness)
5
LCM PRR integration test report
  • Difficulties concerned
  • Missing or wrong specifications on screw sizes,
    screwing torque, thread locker decisions made
    on the site
  • Not all components available the nylon ring and
    the 1 M? resistor for connection to the flange, a
    few screws, the plastic tubes and their brackets
    were missing
  • spare parts (most from the PSL) recycled or
    adapted
  • 3. Not all boards in final configuration
  • - glue problem on the backplane
  • - LCM_CLOCK without fibre tray
  • - cooling plates of the crate out of
    specifications?
  • not possible to test the final LCM
    configuration
  • 4. Integration supports not available
  • not possible to test the final procedure
  • Most serious problem electrical contact between
    crate and titanium (flange tube)

6
Module integration (summary)
0. (Get all components and tools at hand) 1.
Assemble a complete module before making any
tests 2. Power and optical margin test check
that the voltage and current values are
acceptable when powering up the module with a
test board (SUMO) inserted between the power box
and the crate and that the optical transmission
work with proper attenuators inserted along on
the optical fibres. Then remove the SUMO and
mount the power box on the module 3. Functional
test
7
LCM integration procedure (rehearsal of)
(0. Get all proper components and tools at hand)
Result step 0 not all components available ( a
few specification errors)
  • assemble the crate (backplane included), and fix
    the gas venting tube to it

Option fix the fibre spiral tube as well!
  • Comments
  • no supports needed for this step
  • it is not convenient (or possible?) to mount the
    spiral tube at this step

8
  • Result step 1
  • backplane excess of glue on coaxial cables,
    coaxial cables not labelled
  • ground cables from backplane what is the ideal
    position?
  • insertion of the coaxial cables in the trays of
    the backplane holders difficult
  • brackets for the plastic tubes can not be
    mounted without modifying the crate

LCM integration test (details)
possible modifications to the crate and backplane
9
LCM integration procedure (rehearsal of)
  • Fix the crate to the titanium flange

flange
  • Comments
  • preferred orientation is horizontal (supports
    needed)
  • no (more) alignment holes in the flange and
    couronne 1

10
  • Result step 2
  • difficult alignment of flange and crate
    (rehearsal made with crate vertical due to
    missing supports)
  • difficult insertion of the kapton ring
  • missing 1 M? resistor
  • wrong screws used for the resistor (due to
    missing specifications)
  • difficult to get crate and flange isolated (due
    to flanges washers? plastic inserts of the
    screws?)
  • improve documentation
  • develop integration supports
  • fix the nylon rings to the crate?
  • check again all screws with torque
    specifications
  • modifications to flange or crate?

11
LCM integration procedure (rehearsal of)
(old version support)
3. then the (flangecrate) block is fixed on its
support
Comment support not available during this test
12
LCM integration procedure (rehearsal of)
Power box
SUMO test board
4. the crate is connected to the power box
through a power supply test board (SUMO Supply
Monitor)
Comment SUMO board not used during the test
5. ...then we insert the boards one at a time
13
  • Result step 5
  • fibre spiral tube not initially fixed to crate.
    It needs to be fixed to the table and elongated
    up to 70-80 cm
  • wrong screws used for DAQ and CLOCK cooling
    bases (due to missing
  • specifications)
  • improve documentation
  • develop integration supports

14
LCM integration procedure (rehearsal of)
Power box
SUMO test board
6. when all boards are inserted we fix the fibre
spiral tube to the crate, then we make all
connections to the test bench (power, fibres,
flange connectors) and make the power and optical
power margin tests
Option we mount at least one of the cooling
plates before the poweroptical power margin
and/or the functional tests
Comment step 6 not made during the rehearsal
15
LCM integration procedure (rehearsal of)
7. remove the SUMO board and fix the power box
to the crate 8. functional tests!!
Comment steps 7-8 not made during the rehearsal
16
LCM integration procedure (rehearsal of)
9. (assuming the test is ok) prepare for shipping
(old version LCM)
17
What to do at the line integration site
10. If necessary, remove the protection from the
bottom flange 11. Install/replace the o-rings of
the bottom flange 12. Install the titanium
cylinder and mount the container on the line
Comment only step 12 relevant for this rehearsal
Result step 12 contact between crate and
titanium container! Solved by putting kapton tape
on the short edges of the cooling plates
18
PBS and bar-code
  • General formula for traceability
  • PBSNumber/VersionNumber.SerialNumber
  • (rule one individual PBS number used to identify
    only components which are always completely
    interchangeable)

Is this THE rule? Are there exceptions?
  • Notes added after the meeting
  • the rule above is no longer endorsed by the
    Steering Committee (therefore the discussion of
    page 22 needs to be updated)
  • the traceability format remains valid, with the
    SerialNumber to be a unique number for ONE object
    of a given PBS (i.e., the SerialNumber increases
    independently of the VersionNumber)

19
LCM configurations
  • There are 3 kinds of LCMs (leaving aside the
    MILOM and IL needs)
  • (a) LCM connected to 3 OMs
  • (b) LCM connected to 3 OMs and a LED beacon
  • (c) LCM connected to 3 OMs and an acoustic
    receiver
  • (d) LCM connected to sound velocimeter/CTD

Proposal - let us define a version number to
discriminate among them 1 for LCM (a) 2 for LCM
(b) 3 for LCM (c) 4 for LCM (d) (5, 6, ... for
future needs 0 for the no-version option)
Note there is indeed one PBS number for all
LCMs and MLCMs
20
MLCM configurations
  • There are 2 kinds of MLCMs (leaving aside the
    MILOM and IL needs)
  • (a) MLCM connected to 3 OMs
  • (b) MLCM connected to 3 OMs and a LED beacon

Proposal - let us define a version number to
discriminate among them 1 for MLCM (a) 2 for
MLCM (b) (3, 4, 5, ... for future needs 0 for
the no-version option)
Note there is indeed one PBS number for all
LCMs and MLCMs (so the LCM and MLCM versions
should be enumerated together)
21
SCM configurations
  • There are 2 kinds of SCMs (leaving aside the
    MILOM and IL needs)
  • (a) SCM connected to acoustic TX/RX, pressure
    sensor and sound velocimeter
  • (b) SCM connected to the instruments in (a) a
    laser beacon

Proposal - let us define a version number to
discriminate among them 1 for SCM (a) 2 for SCM
(b) (3, 4, 5, ... for future needs 0 for the
no-version option)
22
PBS updates
  • Suggested changes
  • crates the current PBS has only 2.1.01 LCM_CRATE
    gt we would need two PBS numbers for LCM_CRATE
    and MLCM_CRATE
  • backplanes the current PBS has only 2.1.02
    LCM_BACK and 2.2.02 SCM_BACK gt we would need
    three numbers for LCM_BACK-1 (for LCM-V1 and
    LCM-V3), LCM_BACK-2 (for LCM-V2), and LCM_BACK-3
    (for LCM-V4) 2 numbers for MLCM_BACK-1 (for
    MLCM-V1) and MLCM_BACK-2 (for MLCM-V2) and 2 for
    SCM_BACK-1 (for SCM-V1) and SCM_BACK-2 (for
    SCM-V2). Then, we will add more numbers if/when
    needed
  • LCM flange the current PBS has only 1.3.2
    LCM_CONTAINER gt we would need three different
    numbers for the different flanges (for the three
    LCM configurations). Should we also introduce
    different PBS numbers for the flanges and the
    other parts of the containers, as for the SCM
    case?
  • LCM_DAQ/SC the current PBS has only 2.1.17
    LCM_DAQ/SC gt we would need three different
    numbers for MLCM_DAQ/SC, LCM_DAQ/SC and
    SCM_DAQ/SC
  • MLCM_DWDM the current PBS has only 2.1.16
    MLCM_DWDM gt we would need EITHER 5 different PBS
    numbers OR the version number used to specify the
    different wavelengths (or are there other
    options?)
  • SCM_REP the current PBS has only 2.2.04 SC_REP
    gt we would need two different numbers for
    SCM_REP1 (serving 3 sectors) and SCM_REP2
    (serving 2 sectors)
  • LPB the current PBS has only 2.2.11 POWER_BOX.
    It is indeed the same object used inside the
    LCM/MLCM/SCM, but in case of the xLCM it will be
    powered at 380 V, in the SCM it needs to be
    powered at 48V the difference is made by the
    connector gt shall we give a PBS number to the
    connector and its cable?
  • h) should we also worry about the different SCM
    flanges?

See notes on pages 18, 19, 20
Further suggestion double-check all labels and
avoid using numbers in labels when not strictly
needed (so LCM_BIDICON gt MLCM_BIDICON
SCM_WDM1 gt SCM_WDM SCM_BACK1 gt
SCM_BACK-1/SCM_BACK-2 )
23
LCM main components
  • LCM-V1 (configuration with just 3 OMs) is
    composed of
  • - 1 LCM_CRATE PBS-2.1.1 ()
  • - 1 LCM_BACK-1 PBS-2.1.2 ()
  • - 1 POWER_BOX PBS-2.1.11 ()
  • - 1 titanium flange PBS-1.3.2 () the rest of
    the container will be installed at the level of
    line integration
  • - 1 COMPASS_MB PBS-2.1.3
  • - 3 ARS_MB PBS-2.1.4
  • - 1 LCM_DAQ/SC PBS-2.1.17 ()
  • - 1 LCM_CLOCK PBS-2.1.7

Note PBS-related issues exist for items marked
()
  • Then,
  • LCM-V3 (configuration with 3 OMs and an acoustic
    receiver) comprises in addition
  • - 1 ACOUST_RX_PREAMP PBS-2.1.8
  • - 1 ACOUST_RX_DSP PBS-2.1.9
  • - 1 ACOUST_RX_CPU PBS-2.1.10
  • LCM-V2 (configuration with 3 OMs and a LED
    beacon) comprises in addition
  • - a fourth ARS_MB PBS-2.1.4 (but we have to
    replace LCM_BACK-1 with LCM_BACK-2)
  • for LCM-V4 LCM_BACK-1 should be replaced with
    LCM_BACK-3)
  • Beware the flange is different for each
    configuration

24
MLCM main components
  • MLCM-V1 (configuration with just 3 OMs) is
    composed of
  • - 1 MLCM_CRATE PBS-2.1.1 ()
  • - 1 MLCM_BACK-1 PBS-2.1.2 ()
  • - 1 POWER_BOX PBS-2.1.11 ()
  • - 1 titanium flange PBS-1.3.2 () the rest of
    the container will be installed at the level of
    line integration
  • - 1 COMPASS_MB PBS-2.1.3
  • - 3 ARS_MB PBS-2.1.4
  • - 1 MLCM_DAQ/SC PBS-2.1.17 ()
  • - 1 LCM_CLOCK PBS-2.1.7
  • - 1 MLCM_DWDM PBS-2.1.16 ()
  • - 1 MLCM_SWITCH PBS-2.1.18
  • - 1 (M)LCM_BIDICON PBS-2.1.05
  • Then,
  • MLCM-V2 (configuration with 3 OMs and a LED
    beacon) comprises in addition
  • - a fourth ARS_MB PBS-2.1.4 (but we have to
    replace MLCM_BACK-1 with MLCM_BACK-2)
  • Beware the flange is different for the two
    configurations

Note PBS-related issues exist for items marked
()
25
SCM main components
  • SCM-V1 (configuration without a laser beacon) is
    composed of
  • - 1 SCM_CRATE PBS-2.2.01
  • - 1 SCM_BACK-1 PBS-2.2.02 ()
  • - 1 POWER_BOX PBS-2.1.11 ()
  • - 1 titanium flange PBS-1.2.6.2 ()
  • - 1 COMPASS_MB PBS-2.1.3
  • - 1 SCM_DAQ/SC PBS-2.1.17 ()
  • - 1 SCM_CLOCK PBS-2.2.05
  • - 1 SCM_WDM PBS-2.2.03 ()
  • - 1 SCM_REP1 1 SCM_REP2 PBS-2.2.04 ()
  • - 1 SCM_DWDM PBS-2.2.16
  • - 1 ACOUST_RXTX_EM PBS-2.2.07
  • - 1 ACOUST_RXTX_PREAMP PBS-2.2.08
  • - 1 ACOUST_RXTX_DSP2 PBS-2.2.09
  • - 1 ACOUST_RXTX_DSP1 PBS-2.2.10
  • - 1 ACOUST_RXTX_CPU PBS-2.2.11
  • - 1 ACOUST_RXTX_POW PBS-2.2.12

Note PBS-related issues exist for items marked
()
  • Then,
  • SCM-V2 (configuration with a laser beacon)
    comprises in addition
  • - 1 ARS_MB PBS-2.1.4 (but we have to replace
    SCM_BACK-1 with SCM_BACK-2)
  • Beware the flange is different for the two
    configurations

26
Control Module minor components (1)
  • For integration of each xCM the following
    components are also needed
  • 1. small parts for the crate assembly, namely
  • 1.1 the screws to fix couronne 1 to the titanium
    flange
  • 1.2 the plastic inserts for these screws
  • 1.3 the nylon rings to be put between couronne 1
    and the flange for LCM/MLCM
  • 1.4 the screws to fix the LPB to couronne 2
  • 1.5 the mini-screws to mount the backplane into
    its support bars
  • 1.6 the bolts to fix the ground connections from
    the backplane to the crate
  • 1.7 the screws to fix the backplane to couronne 2
  • 1.8 the brackets to install the two plastic tubes
    (with screwswashers)
  • 1.9 the screws for the cooling bases of
    LCM_DAQ/SC and LCM_CLOCK (LCM/MLCM/SCM),
    MLCM_DWDM and MLCM_SWITCH (MLCM), SCM_DWDM and
    SCM_WDM (SCM)

27
Control Module minor components (2)
  • Then we need also
  • 2. the 1 MO resistor to be installed between the
    crate and the flange for LCM/MLCM (with its
    screws)
  • 3. the LPB connector terminated by the wires to
    be soldered to the backplane (with its screws)
  • 4. the HV cable for the LPB (with the screws for
    the connector)
  • 5. the gas venting tube and the fibre spiral tube
  • 6. the thread locker(s)
  • 7. the thermal gel for the cooling plates

28
Component reception assumptions
  • Very strong recommendation
  • Every single board should arrive to the xCM
    integration site ready to be integrated in a
    Control Module
  • It implies that at the xCM integration sites
    there will be
  • - no modifications to any board
  • - no wire or component soldering
  • - no check of board configuration

29
Implications for component delivery to the xCM
integration sites
  • We expect that
  • the titanium flange arrives with all cables
    terminated with the connectors to plug to the
    backplane it should have no o-ring (or, at
    least, no final o-ring) and possibly it should
    be provided with proper protections for the
    connectors and the inner surface
  • the backplanes arrive equipped with all
    components properly installed (as needed!),
    including the power wires and the connector to
    plug to the LPB, the coaxials and any other cable
  • the LPB arrives equipped with its HV connector
    and wires
  • each board arrives exactly in the configuration
    it should be (i.e., as identified by its
    traceability label PBSNumber/VersionNumber.Serial
    Number)
  • for all components we expect to receive an
    accompanying test report and to be able to trace
    the product history through the bar code label
    (we will use it as well to update the history of
    the integrated modules)
  • - ... (this list will be updated according to
    the integration test results)

30
Component reception at the xCM integration site
  • Therefore we need that
  • - each component is accompanied by a proper test
    report ( a PBS compliance certificate)
  • - traceability is possible through the bar code
    label
  • Actions upon reception
  • visually inspect the components
  • check the accompanying documentation
  • interact with the database to update the product
    history

31
Component storage at the xCM integration site
  • - Standard laboratory conditions needed for
    storage and integration
  • ESD protection required for all sensitive
    components (i.e., electronics boards and LPB) at
    all times
  • storage room needs under evaluation (most
    serious requirement from mechanical pieces)

32
Packing (and delivery)
  • Transportation logistics provided by IN2P3
    Cellule Logistique
  • Flange transportation box will be used for module
    delivery

33
Work in progress...
  • In progress (due for xCM PRR)
  • PBS list
  • component configuration (namely, define possible
    changes)
  • integration procedure
  • integration supports and tools (all or just what
    is essential?)
  • documentation

Target complete rehearsal has to be made in time
for LCM PRR
34
Work to be done...
  • To be done (due for end June for LCM)
  • definition of intermediate (power, optical power
    margin) tests
  • transportation boxes for components and modules
  • storage containers/conditions
  • bar code traceability (requires reader and
    software)
  • complete integration table
  • define and implement test benches!
  • define test scenario (including failure modes,
    module repair line)
  • documentation

35
Critical items...
  • Whats critical
  • Quality Control directives needed (in time for
    PRR?)
  • Test bench status unsatisfactory (needed for
    production)
  • the Pisa group can contribute more
  • no MLCM training currently possible
  • possible conflict in Bari for finalization of the
    SCM and MLCM test benches

36
Implications
  • Should the LCM PRR wait to have the full Quality
    Control system implemented?
  • Is the integration of the MILOM LCMs really
    needed in July? (SCM and MLCM due in September)
  • Can we enable the Pisa group to work on the
    module integration and on the development of the
    test bench at Pisa? (needed onshore clock
    system, ethernet fibre connection, a complete LCM)

37
SCM test bench development (ongoing work at Bari)
  • General definition essentially done
  • Implementation delay due to unexpected problem
    with the ethernet link
  • Implementation essentially stopped because
  • - acoustics system control is not possible with
    the DAQ/SC software
  • - lack of detailed documentation on other tests
  • Current status of the test bench
  • - it manages SC and clock communications with
    the SCM
  • - it can drive the SCHarness through the state
    machine
  • - it can query and decode SC data
  • all in an integrated Labview software

38
LCM test bench development (ongoing work at
Catania and Pisa)
  • General definition started
  • Getting the LCM to acquire data was a tough job,
    due to poor documentation
  • Current status of the test bench
  • - it manages DAQ/SC and clock communications
    with the LCM
  • - it can drive the DAQ/SCHarnesses through their
    state machines
  • - it can query and decode SC data
  • - it can drive data acquisitions with emulated
    signals from a pulser
  • all in an integrated Labview software

39
MLCM test bench development
  • Definition essentially linked to the LCM case
    (except for the MLCM-LCM communications and
    ethernet switching)
  • Implementation should inherit both from the SCM
    and LCM test benches (not yet defined what to
    inherit from which test bench...)
  • Hardware for the MLCM-LCM ethernet connections
    purchased but not yet integrated