Title: Student System Upgrade


1
Student System Upgrade
  • ECAB Meeting
  • 13 September 2006

2
Student System Upgrade - ECAB MeetingStatus
Report
  • Introduction
  • Project started in June with setting out the
    basics, facilities, recruitment of staff etc
  • 50 internal and external staff interviewed, now
    are 6 under contract and 4 CQU staff, 15 more to
    come from various divisions
  • Many meetings
  • Project Board established
  • Advisory Group established
  • Facilities are organised
  • Principles
  • Prince 2 methodology
  • ITIL Framework
  • Transparency
  • Communication
  • Website

3
Student System Upgrade - ECAB MeetingStatus
Report
  • Governance
  • 1. The Project Management Team
  • Project Board (Exec Business), Senior User and
    Senior Supplier)
  • Project Manager
  • The Executive is ultimately responsible for the
    project
  • Development of the project Business case
  • Project organization structure and plans
  • Monitoring and Control of progress
  • Problem referral
  • Formal Closure
  • Post project review
  • Senior Users are responsible for any products
    supplied by users, eg requirements and matching
    of proposals to requirements
  • User resources
  • Ensuring that project outcomes meet the user
    requirements
  • Ensuring that project outcomes provide expected
    user benefits

4
Student System Upgrade - ECAB MeetingStatus
Report
  • Governance (cont)
  • Senior Supplier
  • - The Senior Supplier needs to achieve the
    results required by the senior User
  • The Project Manager
  • - Day to day management of the project
  • 2. Project Assurance
  • - Project Control that the reported progress is
    substantiated
  • 3. Project Support
  • - Assistance to Project Manager, eg Quality
    officer, Training, Compliance

5
Student System Upgrade - ECAB MeetingStatus
Report
  • Activities during last period
  • Assessed functionality against Manage Graduation
    instruction sheets written for PS V7.6
    functionality
  • Continued with Graduation Fit/Gap
  • Completed Direct Admission and Equity
    Scholarships process flows, end user to review,
    due 18/09, documentation in progress
  • Undergraduate Admissions Officer to provide the
    flows asap
  • Continued work on Cashiering Issue Paper and
    Collection processing
  • Contact with other Universities
  • Continued work on Graduation Issue Paper
  • Continued work on OneStop Processing Issue Paper
  • Continued work on CS V8.9 System Strategy Paper
  • Contacted Student Financials re Invoice Issue
    Paper

6
Student System Upgrade - ECAB MeetingStatus
Report
  • Activities during last period (cont)
  • Patched Demo Environment V8.9 ready for testing
    and comparison
  • Agreement to demonstrate V8.9 for C_MS staff
  • Meeting with Oracle re Planning phase under
    contractual agreement (ASC)
  • Hardware Contract signed and accepted
  • Bulk of first 3 chapters of upgrade guide
    completed
  • Contacted agents re candidates for short term
    staffing relief
  • Decision to go ahead with Oracle Solution Centre
    (Planning phase), contract ready for signature
  • Decision to establish Training Lab in Bldg 5,
    work commenced
  • Demo of selected 8.9 functionality to C_MS
    Divisional Managers
  • Finalised Business cases following Project Board
    Comments
  • First Advisory Group Meeting

7
Student System Upgrade - ECAB MeetingStatus
Report
  • Results
  • Completed Business Cases x 2
  • Data cleansing scripts run and provided to BAs

8
Student System Upgrade - ECAB MeetingStatus
Report
  • Setbacks/Challenges
  • Patched environment ready patches contain ANZ
    functionality required for Fit/Gap
  • New Unix Cobol compiler for demo environment
    installed (approx 4 hr delay)
  • Installation of Windows Cobol Compiler now
    installed (approx 2 hr delay)
  • 6 Cobols currently not compiling (both Windows
    and Unix) GSC case to be logged

9
Student System Upgrade - ECAB MeetingStatus
Report
  • Risks Assessment Mitigation
  • ITD Date of arrival for new hardware not set
    Meeting with Systems Admin re mitigation next
    week
  • ITD Timelines are tight - require regular
    updates of timeframes upcoming events to enable
    and better workload management

10
Student System Upgrade - ECAB MeetingStatus
Report
  • Planned Activities Short term
  • Continue with Fit/Gap analysis of the Graduation
    Process
  • Continue familiarisation with PeopleSoft Version
    8.9
  • Commence Fit/Gap analysis for Equity
    Scholarships, after review by end users
  • Liaise with faculty end users for feed back on
    amended process flows for Graduations
  • Testing of patched demo environment
  • Resolution of Cobol compile issues with GSC
  • Hardware provisioning planning
  • Automation of data cleansing script execution for
    period delivery

11
Student System Upgrade - ECAB MeetingStatus
Report
  • Planned Activities Long term
  • Complete priority issue papers due in October
  • Complete key business process reviews for ASC
    planning workshop
  • Any other planning required for ASC planning
    workshop
  • Commence Fit/Gap document for Curriculum
    Management and Transfer Credit after review by
    end users
  • Continue to liaise with Faculty, FSD and SA end
    users for feed back on amended process flows
  • Familiarisation with PeopleSoft Version 8.9
  • Implementation of new hardware
  • Export of Data Cleansed environment for Oracle
    Solution Centre
  • Provisioning of new environments
  • Advisory Group to be assisted by a Self Service
    developer to clarify the requirements in terms of
    Data Bases
  • Preliminary start of Planning Phase 9 October

12
Student System Upgrade - ECAB MeetingStatus
Report
  • Staff
  • Currently 8 staff, next week 10 and in October
    20, whereof 7 contractors so far
  • Planning of extraction of staff from divisions,
    mainly ITD and backfilling
  • Training Manager attached to the Project Team
  • Position Descriptions to be amended to fit the
    individuals