Title: SS CDM Cogeneration in Egypt Additionality
1SS CDM Cogeneration in Egypt - Additionality
Tunis August 27-28, 04
- Ihab Elmassry, M. Sc. CEM, CDGP
- Cummins Power Generation, UK
- Email imassry_at_link.net
2Cogeneration
- Cogeneration is the simultaneous generation of
usable heat and power, usually electricity, in a
single process from the same fuel.
3Plant Self Generation Concept
Base electrical kWh supplied Gas Gen-set
4Additionality test (Proposal on CDM Additionality
Tests, Lex de Jonge Sandra Grener)
Project is not additional
Has construction of the project started?
Was the project construction started before 1
Jan, 2000?
Was CDM taken into consideration since the early
stages of project development
Was the project construction starting date before
both date of registration 31 Dec. 2005?
Is there documentation to this effect?
Is execution of the project based on a direct or
indirect legal obligation?
5Check one of the options 3a or 3b for barrier
testing?
Project is not additional
- 3b do one or more of the following barriers
exists - Investment
- Technological
- Practice
- others
3a determine financial or economical barrier
(IRR, .. Etc)
Project is less eco attractive
Are many projects recently implemented without
CDM?
Project is additional
- Have one or more of the following barriers
recently changed fundamentally - Investment
- Technological
- Practice
- others
6Cogeneration
- Whey the non project is more likely?
7I. Investment/financial barrier
- A cogeneration project is relatively a capital
intensive project. The cost of a cogeneration
project may be varied from fraction of millions
up to tenth of millions depends on the size and
the type of the cogeneration unit. - There is no clear financing mechanism for
environmental and/or energy efficiency and/or
demand side management projects. - Banks and leasing companies interest rates are
high.
8I. Investment/financial barrier (cont.)
- Subsidy that imposed on electricity and energy
prices which resulted in low return on investment
for cogeneration projects. - Relatively high simple payback periods, in best
cases it is not less than 6 years.
9Example Debt/Equity 100/0
10Example Debt/Equity 50/50
Base Case
11Example Debt/Equity 0/100
Base Case
12II. Practice
- Lack of knowledge about the conducting
techno-economic feasibility studies and risk
assessment for cogeneration projects. - Lack of knowledge on energy efficiency equipment
13III. Institutional
- Absence of governmental incentives such as low
bank interest rate and advantageous customs,
taxes and customs duties. - The reluctance of the utility to purchase the
excess of electricity produced by the small
producers. It offers a very low selling back
price. - The lack of awareness of cogeneration technology
and its benefits to Egypt,
14III. Institutional (cont.)
- The lack of long-term plans supported by the
government for cogeneration promotion. - No cogeneration power purchase agreement
- Cogen-End user contractual issues
- Low selling back tariff
- No official written procedure for interconnection
requirements
15IV. Technological
- Few number of small scale cogeneration projects
are already installed, this leads to operation
performance risk