Title: Intelligence Community Acquisition Best Practices: NGA Earned Value Management
1Intelligence Community Acquisition Best
Practices NGA (Earned Value Management)
- Presentation to Defense Intelligence Acquisition
Conference - Peggy Poindexter
- Acquisition Business Office (AB)
- National Geospatial-Intelligence Agency (NGA)
- 15 May 2007
2Topics for Discussion
- Background
- IC EVM Council
- NGA EVM Best Practices
- Contract Implementation Review (CIR)
- IC Guide to the Evaluation and Surveillance of
Earned Value Management Systems (EVMS)
3Background
- NGA uses Earned Value Management (EVM) on Major
Systems acquisitions - Earned Value Management supports NGA program
management by effectively integrating the work
scope of a program with its schedule and cost
elements for optimum program planning and
control. - EVM is an Industry Best Practice
ANSI/EIA-748-A, Earned Value Management Systems
4Managing Without Earned Value Information
Example I Budgeted 5 Widgets at 100 Hrs Per
Widget. At the End of the Month, 400 Hours Had
Been Expended.
5EARNED VALUE - AN OBJECTIVE MEASURE OF WORK
ACCOMPLISHMENT
Example I plan to build 5 widgets this month.
Each widget should take 100 hrs. I will measure
earned value based on the work accomplished i.e.
3 widgets completed.
BUDGET EARNED ACTUAL PLAN VALUE
500 300 400
(3 WIDGETS 100 HOURS)
6Managing WITH Earned Value Information
7IC EVM Council
8IC EVM Council History Purpose
- Identified need for IC forum to collaborate and
share EVM information - Briefed the IC Acquisition Council (ICAC) (Jan
2004) - Established working Group to evaluate need for IC
EVM Council - Members CIA, DIA, NGA, NRO, NSA
- Drafted and coordinated IC EVMC charter
- Agreed upon and signed (Aug 2004)
- IC EVM Council Purpose
- Provide a venue for collaboration and recognition
of Government application and industry
implementation of EVM compliance with ANSI/EIA
748-A
9IC EVM Council Functions
- Serve as focal point for EVM within the IC on EVM
approach, policy and guidelines - Advocate EVM to IC Industry partners
- Discuss Government and Industry EVM concerns
- Share information on tools, lessons learned,
reviews and reporting - Collaborate on guidelines for process reviews and
approving contractors' systems including
validation and continued acceptance
10EVM Best PracticeContractImplementation Review
(CIR)
11What is a CIR?
- The Contract Implementation Review (CIR) provides
insight into - Contractor management processes used to execute
the program - How those processes develop the performance
measurement baseline (PMB) i.e. work execution
plan - How different processes are applied across the
programs lifecycle - Overall process maturity
The CIR is an integral part of program start-up
and a key stepping-stone to understanding the
Integrated (cost, schedule, technical)
Performance Baseline
12What is the Scope of the CIR?
- Processes reviewed at the CIR may include
- Program management
- Technical management/Lifecycle development
- Risk Management
- Supply Chain Management
- Supplier management/Materials
- Earned Value Management
- Other related management control processes
13What are the Outcomes of the CIR?
- Confidence in contractor capabilities to deliver
integrated (cost, schedule, technical
performance) acquisition outcomes - Identify process risks and opportunities,
management challenges, and any expectation gaps - Improved understanding of how the Contractor
conducts business - Understand the relationship of the technical
baseline/technical performance metrics with the
EVM implementation
14A CIR is not
- Pass or fail review
- Milestone decision authority review
- Audit
- CMMI review
- EVM system review
15EVM Best PracticeThe IC Guide to the Evaluation
and Surveillance of EVMS
16Background
- The EVM Industry Standard, ANSI-EIA-748-A
- Defines 32 Guidelines for structuring effective
management control systems - Provides minimum prescription on the
implementation of these guidelines - Is referenced in both FAR and DFARS clauses for
contractual implementation of EVM
ANSI/EIA-748-A, Earned Value Management Systems
17Background
- The basic tenets of the 32 EVM Guidelines are
- Plan all work scope for the program through
completion - Assign finite pieces of work to a responsible
person or organization for control of technical,
schedule and cost objectives. - Integrate program work scope, schedule and cost
objectives into a plan against which
accomplishment can be measured. - Control changes to the plan.
- Objectively assess work accomplishment.
- Compare actual costs incurred in accomplishing
the completed work with its planned value. - Analyze significant variances from the plan,
forecast impacts, and prepare an estimate at
completion based on performance to date and work
to be performed.
18IC Guide to the Evaluation and Surveillance of
EVMS
- IC Guide developed in accordance with the IC EVM
Councils Charter - Purpose of IC Guide is to ensure
- Consistent and uniform approach between IC
Mission Partners in the evaluation and
surveillance of contractor EVM systems - The IC Guide recognizes and builds upon the
Industry NDIA EVMS Intent Guide
19IC Guide to the Evaluation and Surveillance of
EVMS
- IC Guide provides the acquisition community
- Insight into each guideline and its
implementation - Information on how to evaluate the contractors
implementation of each guideline - The qualities and products inherent in an
effective implementation - Provides a consistent tie-back across the
Intelligence Community to each guidelines intent
20IC Guide to the Evaluation and Surveillance of
EVMS
- The new IC Guide is an unprecedented and new body
of knowledge in the EVM Community - IC Guides format for each EVMS Guideline
provides - What it Means
- IC Implementation Guidance
- Contribution to Program Management
- Qualities of Effective Implementation
- Typical Products of Implementation
- What Should the EVM System Description Cover
- Review Steps
- Glossary of Terms (Appendix A)
- Data Trace Formats (Appendix B)
- Intent Paragraphs of the NDIA Intent Guide
(Appendix C)
21NATIONAL GEOSPATIAL-INTELLIGENCE AGENCY