Title: Wastewater Master Plan San Francisco Public Utilities Commission Department of Environment
1WastewaterMaster PlanSan Francisco Public
Utilities CommissionDepartment of Environment
March 13, 2006
2Dry Weather
North Point Outfalls
North Point Facility
Channel T/S
BAYSIDE DRAINAGE
WESTSIDE DRAINAGE
Bay Outfall
67 MGD
17 MGD
Southeast Plant
Oceanside Plant
Southwest Ocean Outfall
3Wet Weather
North Point Outfalls
North Point Facility
150 MGD
Channel T/S
BAYSIDE DRAINAGE
WESTSIDE DRAINAGE
Bay Outfall
250 MGD
65 MGD
Southeast Plant
Oceanside Plant
Southwest Ocean Outfall
110 MGD (decant)
4Past Master Plans
1993 Oceanside Plant
1850 Brick sewers constructed
1899 Master Plan
1974 Master Plan
1935 Master Plan
2000
1800s
1952 Southeast Plant
1932 McQueen Secondary Treatment Plant (Golden
Gate Park)
5Wastewater Treatment
Raw
Primary Effluent
Secondary Effluent
6Annual Flows
Decanted Combined Sewer Discharge 2,500
MG (6.6)
Decanted to SWOO 1,300 MG (3.3)
Primary Treatment 3,600 MG (9.3)
Secondary Treatment 30,800 MG (80.7)
Prior to WW System Improvements
After Implementation of 1974 MP
7Annual TSS Loads
To Islais Creek 230 tons (0.5)
To Outfalls 2,800 tons (5.7)
Decanted Combined Sewer Discharge 940 tons
(1.9)
Prior to WW System Improvements
Removed 45,600 tons (92)
After Implementation of 1974 MP
81974 Master Plan Improvements
9Oceanside WPCP
10Southeast WPCP
11North Point Wet Weather Facility
12Transport Storage Box
13Problems and Issues
- Aging Infrastructure
- Flooding
- Seismic Reliability
- Biosolids
- Overflows into the Bay and Ocean
- Southeast Treatment Plant
14Old Pipes and Buildings
Digester roof collapse at Southeast Treatment
Facility
Example of Sewer Corrosion
15Flooding
Cayuga Street, Feb. 2004
Street Backup
16Current Flood Prone Areas
Storm Watch Map
17Seismic Reliability
18Biosolids (Solid Wastes)
- Over 70 of our Biosolids is shipped to Solano
County.
- In 2007 the Solano ordinance that regulates
Land Application expires.
19Overflows in to Bay and Ocean
Baffle Screen
Solids Settling
20Wet Weather CSO Discharge
8 overflows in Yr 1997-1998 due to El Nino
21Regulatory Issues
22Southeast Treatment Plant
Highway 280
Evans Avenue
Jerrold Street
Residential/Commercial Areas
Phelps Street
23 Collection System Odor Complaints 2001-2002
363 odor complaints
24Wastewater Master Plan Schedule
2006
2007
Jan
Feb
Mar
Apr
May
Jun
July
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
1. Project Introduction
2. Identify Evaluate Conceptual Alternatives
3. Evaluate Viable Alternatives
Draft Master Plan
4. Recommend Best Apparent Alternative
Project Phase
Jan 10
SFPUC Commission Workshops
Neighborhood Presentations
Technical Advisory Committee Meetings
Citizen Advisory Committee Meetings
Public Workshops
25Master Planning Environmental Review Schedule
2005
2008
2007
2009
2006
Master Planning Element
Technical/Engineering Analysis Environmental
Documentation Public Involvement
Final WWMP Final EIR
Best Apparent Program
Draft WWMP
26Guiding Principles - WWMP
- Protection of Public Health and Safety
- Protection and enhancement of the natural
environment - Open and transparent planning process
27Evaluation Criteria
- Environmental/ Social/ Cultural
- Water Impacts
- Land Impacts
- Air Impacts
- Use of Resources/Sustainability
- Land
- Fuel and Electricity
- Chemicals
- Materials (Construction, OM)
28Evaluation Criteria
- Functional and Technical
- Reliability/ Redundancy
- Ease of Operation/ Implementation
- Performance
- Regulatory Compliance
- Reuse/Disposal Issues
- Economic
- Capital and OM Costs
- Life Cycle Costs
- Cost Benefit Ratio
- Rate Impacts
29Conservation of Natural Resources
30Think Outside the Box
Recycled Water at Harding Park
Pipe installation at Lake Merced
31Think Outside the Box
Roof of City Hall in Atlanta, Georgia
Permeable Sidewalks
32Next Steps
- Form Interdepartmental Working Group
- Park Rec
- Port
- Dept. of the Environment