Contractor Outreach Event - PowerPoint PPT Presentation

1 / 81
About This Presentation
Title:

Contractor Outreach Event

Description:

Contractor Outreach Event – PowerPoint PPT presentation

Number of Views:152
Avg rating:3.0/5.0
Slides: 82
Provided by: laur415
Category:

less

Transcript and Presenter's Notes

Title: Contractor Outreach Event


1
Contractor Outreach Event May 13, 2009
2
SAFETY MESSAGE
3
AGENDA
4
Dulles Transit Partners Project Overview
  • Howard Menaker
  • Communications and Outreach Manager

5
Dulles Metrorail ExtensionAt a Glance
  • 23-mile new Metrorail line branching off the
    Orange Line after East Falls Church
  • 11 new stations
  • 5 in Phase 1 11.6 miles
  • 6 in Phase 2 11.5 miles
  • Phase 1 East Falls Church to Wiehle Avenue in
    Reston
  • Phase 2 Wiehle Avenue through Dulles
    International Airport to Ashburn
  • Seamless integration with current 106-mile system

5
6
Route Map
6
7
Construction Has Started
  • Phase 1 construction started along Route 123 at
    International Drive.
  • Phase 1 Completion date is July 2013

7
8
PREPARING FOR METROS ARRIVAL TO TYSONSUtility
Relocation Continues
  • Utilities include electric power, communication,
    water and sewer lines
  • Working with businesses and residents to provide
    information about impacts
  • Utility relocation will
    continue through 2009

8
9
Utility Relocation
9
10
Construction
10
11
Construction
11
12
Construction
12
13
Tysons East
13
14
Tysons Central 123
14
15
Tysons Central 7
15
16
Tysons West
16
17
Wiehle Avenue
17
18
Keeping the community informed
  • Almost 600 community and business outreach
    project briefings given over last
    2 years
  • Regular updates continue to businesses and
    residents via e-mail, fax
    and mail
  • Project, State and County working
  • with employers on transportation planning
  • 24-Hour Emergency HOTLINE
  • (877) 585-6789
  • Project Office located in Tysons Corner
  • Were in this together!

18
19
DBE PROGRAM
  • Felicia Bell
  • Subcontracts Manager, DBE Liaison

20
DBE Program
  • DBE Project Goal of 10 percent.
  • Two (2) agencies issue DBE certifications
    applicable to the DTP DBE Program
  • Metropolitan Washington Airports Authority (MWAA)
  • Virginia Department of Minority Business
    Enterprise (VDMBE)
  • Reciprocity agreement in place between VDMBE,
    MWAA, MDOT, and WMATA/DDOT

21
DBE Program
  • MEETING THE GOAL
  • Joint ventures, partnering, LLCs, etc. are
    accepted on this Project.
  • In order to have your partnership count as 100
    percent DBE, the DBE must be controlling 51 (or
    more) of the partnership, joint venture, etc.
  • MEETING THE GOAL as a non-DBE firm
  • DBE utilization must be illustrated within the
    response to the RFP (including potential DBEs and
    potential subcontract values).
  • Proof of certification should be included within
    the RFP response
  • You are required to use good faith efforts to
    solicit and utilize DBEs (with certifications
    applicable to this Program)
  • Issue a subcontract that is equal to or greater
    than the DBE goal specified in the RFP/contract
    or issue multiple subcontracts that are equal to
    or greater than the DBE goal specified in the
    RFP/contract.
  • Only the dollars contracted and paid to the
    subcontracted DBE will count towards the
    specified goal.

22
DBE CERTIFICATION AGENCIESDULLES CORRIDOR
METRORAIL PROJECT
  • Metropolitan Washington Airports Authority (MWAA)
  • DBE Certification Application Website Address
  • http//www.mwaa.com/business_information/contract
    ing_opportunities/equal_opportunity_programs/ldbe_
    dbe_certification
  • Virginia Department Minority Business Enterprise
    (VDMBE)
  • DBE Certification Application Website Address
  • http//www.dmbe.virginia.gov/dbecert.html

23
23
Disadvantaged Business Enterprise Outreach
Contract Compliance
Korey Gray
Washington Metropolitan Area Transit Authority
Prepared by
The Department of Corporate Strategy
Communications Office Of Community
RelationsDisadvantaged Business Enterprise (DBE)
Program
24
24
Disadvantaged Business Enterprise Outreach
Contract Compliance
Purpose of DBE Compliance
  • Recruit and Maintain DBE Enterprises.
  • Foster Strong Ties Between the DBE Community and
    Large Business Enterprises.
  • Empower DBE Enterprises to participate on large
    pieces of work.
  • Opportunities to Include the Following Trade
    Areas
  • Construction
  • Supplies and Equipment
  • Professional Services

25
25
Disadvantaged Business Enterprise Outreach
Contract Compliance
  • Five Elements to an Effective Compliance Plan
  • Setting Appropriate Utilization Goals
  • Analyzing Eligible Opportunities
  • Comprehensive Outreach
  • Community Involvement
  • Robust Monitoring and Tracking

26
26
Disadvantaged Business Enterprise Outreach
Contract Compliance
Setting Appropriate Goals
  • Goal Setting for DBE Utilization
  • Good Faith Efforts in DBE Outreach
  • Contractual/ Flow Down Requirements
  • Training for All Participants Primes/Lower
    Tiers
  • Mandatory Reporting

27
27
Disadvantaged Business Enterprise Outreach
Contract Compliance
Good Faith Efforts
A conscious effort to aggressively seek DBE
participation and to clearly document the effort
made toward fulfilling the DBE goal. The
contractor has the responsibility of fulfilling
the DBE goal or showing their good faith efforts
to do so.
28
Necessary and Reasonable Steps
28
Disadvantaged Business Enterprise Outreach
Contract Compliance
Use the correct WMATA DBE Directory The current
WMATA DBE Directory is on our website
www.metroopensdoors.com Contact all the DBEs in
the appropriate NAICS code. Documentation of the
contacts made and submitted to the DBE/ Contract
Compliance Office.
29
29
Disadvantaged Business Enterprise Outreach
Contract Compliance
Looking Ahead
  • Bus I Garage Project 100M
  • Bus II Garage Project 10M
  • Economic Stimulus Projects 200M
  • Rail Yards Project 100M
  • Red Line Rehab Project 100M

30
30
Disadvantaged Business Enterprise Outreach
Contract Compliance
31
METROPOLITAN WASHINGTON AIRPORTS AUTHORITYDBE
PROGRAM
Richard Gordon Manager Equal Opportunity Programs
32
DBE Certification Requirements
49 CFR Part 26 states that a business concern
must be
  • A for-profit, small business which is at least 51
    percent owned by one or more socially and
    economically disadvantaged persons, and
  • Whose management and operations are controlled by
    one or more of the socially and economically
    disadvantaged owners.

33
DBE Certification Requirements
  • Groups defined by 49 CFR Part 26 as socially and
    economically disadvantaged are
  • Black Americans
  • Hispanic Americans
  • Native Americans
  • Subcontinent Asian Americans
  • Asian-Pacific Americans
  • Women, and
  • Other individuals who can individually prove
    social and economic disadvantage.

34
Reciprocity
  • A Memorandum of Understanding (MOU) has been
    established between
  • The District Department of Transportation (DDOT)
  • Washington Metropolitan Area Transit Authority
    (WMATA)
  • The Maryland Department of Transportation (MDOT)
  • The Commonwealth of Virginia Department of
    Minority Business Enterprise (VDMBE)
  • The Metropolitan Washington Airports Authority
    (MWAA)
  • The MOU was established to lessen the duplicative
    efforts and facilitate the transfer of
    information among the parties and improve the
    certification process for applicants seeking DBE
    certification in the District of Columbia,
    Maryland and Virginia

35
Reciprocity
  • If a DBE has received Home State Certification
    and seeks DBE certification from a Reciprocal
    Certification Agency, the Parties will adhere to
    the following procedures
  • The Reciprocal Certification Agency will require
    the DBE to submit all of the following
  • Completed Uniform Certification Application form,
    including the Affidavit of Certification
  • Personal Net Worth Statement
  • Individual Federal Tax Return for the latest tax
    year
  • Firms Federal Tax Return for the latest tax
    year and
  • Copy of the latest letter of certification
    received by the DBE from its Home State

36
Reciprocity
  • The Reciprocal Agency will request copies of the
    most recent onsite and/or investigation report
    from the Party granting Home State Certification
    to the DBE.
  • The Reciprocal Agency will make whatever further
    inquiries and requests it deems necessary for its
    decision making process.
  • The Reciprocal Agency will have the discretion to
    take any of the following actions
  • Certify the DBE in reliance on the certification
    decision of the Home State
  • Make an independent certification decision based
    o documentation provided by the Home State,
    augmented by any additional information it
    obtains or
  • Proceed with its ordinary DBE application process
    without regard to the action taken by any other
    Party. The Reciprocal Agency will notify the
    Home State in writing within 30 days of taking
    this action.

37
Virginia Megaprojects
  • Carolyn Wolcott
  • VA Megaprojects GEC Civil Rights Manager

38
The Role of the GEC
  • General Engineering Consultant (GEC)
  • Management and administration of the 6 billion
    Virginia
  • Megaprojects program
  • Program administration
  • Project management
  • Quality assurance

39
What are the Megaprojects?
  • Megaprojects are large-scale projects
    distinguished by cost, complexity and the
    potential impact on the community.
  • Collectively, these projects represent several
    billion dollars in significant transportation
    improvements all long overdue.
  • When completed, they will offer travelers more
    choices to reach their destinations.

40
The Projects
  • Dulles Metrorail Extension
  • Telegraph Road Interchange
  • I-95 Widening
  • Fairfax County Parkway Extension
  • I-495 (High Occupancy Toll) HOT Lanes
  • I-95/395 HOT Lanes

41
Telegraph Road Interchange Prime Contractor CK
Constructors
  • Final major contract of the Woodrow Wilson Bridge
    project
  • Rebuild the I-95 interchange at Telegraph Road
  • Provide uninterrupted traffic flows and safer
    pedestrian access
  • Widen two miles of I-95/495 Capital Beltway

42
Telegraph Road work zone
River crossing
Telegraph Road
US Route 1
MD-210
I-295
43
I-95 Widening Prime Contractor Shirley
Contracting
  • Add a fourth lane in each direction of I-95
  • Additional capacity will complement gains already
    achieved by the Springfield Interchange project

44
I-95 Widening project schedule
  • Construction began March 2008 and will end in
    2011.
  • The contract value is 123 million.

45
Fairfax County Parkway Extension / BRACPrime
Contractor Cherry Hill Construction
  • Fairfax County Parkway (4 phases)
  • Final two miles of Fairfax County Parkway
  • Interchange at the Engineer Proving Ground access
    road
  • Extension of Boudinot Drive with one ramp to
    southbound Parkway
  • First two phases cost 117 million, phases 3 and
    4 are unfunded
  • Estimated completion late 2010
  • I-95 Access Ramps to the Engineer Proving Ground
    (EPG)
  • Proposed ramps would reduce traffic volume on the
    Fairfax County Parkway and allow more
    efficient travel when Fort Belvoir realignment
    takes effect.
  • The cost is to be determined
  • Construction timeline mid-2009 to 2011

46
I-495 High Occupancy Toll Lanes Prime Contractor
- Fluor-Lane LLC
  • Two new lanes in each direction
  • First-time introduction of High Occupancy Vehicle
    (HOV) access to the Capital Beltway
  • Pedestrian and bicycle access
  • Replace more than 260 million of aging
    infrastructure, including more than 50 bridges
    and overpasses

11
47
I-495 Project Overview
  • Improved sound wall protection for adjacent
    neighborhoods
  • Construction of Springfield Interchange
    connection to create a seamless HOV network
  • Improved connection for I-66 regular lanes
  • Three new access points to economic hub Tysons
    Corner

48
I-95/395 HOV/Bus/HOT LanesPrime Contractor
Fluor-Lane LLC
  • Expand existing 28-mile I-95/395 HOV lanes from
    two to three lanes
  • Extend HOV to Stafford and Spotsylvania
  • Improve HOV service with new access points,
    increased enforcement and improved incident
    response
  • Provide new choice for drivers to pay toll on
    occasion for faster more reliable travel
  • Create seamless regional HOV network
  • 195 million concessionaire payment to fund
    transit improvements such as Park Ride lots,
    new buses and bus routes

49
  • Northern section
  • Expands existing High Occupancy Vehicle (HOV)
    lanes from two to three lanes
  • Existing HOV system plus nine mile extension
    Eads Street to Garrisonville Road
  • Southern section
  • Extends HOV/HOT system south to Massaponax,
    Spotsylvania County

50
DBE/SWaM Participation Goals
  • Dulles Metrorail Extension 10/None
  • Telegraph Road Interchange 15/25
  • I-95 Widening 15/Voluntary Participation
  • Fairfax County Parkway Extension 10/15
  • I-495 HOT Lanes 15/25
  • I-95/395 HOT Lanes Not Yet Determined

51
Total DBE and SWaM Commitments on these
MegaProjects to date(approximately)300,000,000
More opportunities are on the horizon!
52
BREAK
  • 230 245

53
LABOR RELATIONS
  • Nick Fiore
  • Labor Relations Manager

54
LABOR RELATIONS OVERVIEW
  • National Heavy Highway Agreement that covers
    Phase I of the DCMP and is applicable to DTP and
    union contractors only.
  • Does not apply to non-union or merit shop
    contractors and you are not required to sign any
    local agreements
  • DTP may subcontract work to non-union or merit
    shop contractors to the lowest prequalified,
    responsive, responsible bidder.
  • Allows for maximum participation of DBEs.

55
LABOR RELATIONS OVERVIEW
  • DTP Direct Hire of Skilled Craft Workers
  • Will be provided by various craft unions
    utilizing their referral process. DTP will not
    direct hire at the gate.
  • Non-union or merit shop contractors hire craft
    worker based on their individual company
    policies.

56
LABOR RELATIONS OVERVIEW
  • Davis Bacon Wage Rates
  • All contractors, at a minimum, are required to
    comply with and pay the pre-determined
    Davis-Bacon wage/fringe benefits rates as well as
    all D-B recognized holidays and vacations in
    effect at the time of the contract award.
  • Wage Determinations are usually contained with
    the Request for Proposal.
  • All contractors and their sub tier contractors
    must submit weekly certified payrolls.
  • Need to ensure that all workers performing work
    on the project are classified correctly
  • Penalties for non compliance may include fines,
    liquidated damages and debarment from bidding on
    federal work.

57
LABOR RELATIONS OVERVIEW
  • Drug Alcohol Testing Required
  • Pre hire, random, reasonable suspicion and post
    accident.

58
SAFETY
  • Bruce Colvin
  • Environmental Safety and Health Manager

59
ENVIRONMENTAL, SAFETY, AND HEALTH
  • Project Policy Zero Accidents and Zero Incidents
  • Reasons for Bidder Disqualification
  • Accident rates higher than national average
  • Poorly written or missing Safety Program
  • Fatalities within the past three years
  • Companies that prioritize ESH have a better
    opportunity of being selected

60
ENVIRONMENTAL, SAFETY, AND HEALTH
  • Safety professionals support the team in
    preventing accidents and injuries.
  • A single accident could severely impact a small
    company.
  • What should a small company do?
  • Hire a Safety Professional
  • Use a Safety Consultant
  • Budget for effective staff training
  • Set policies and make ESH a priority

61
INSURANCE
  • Linda Lopez
  • Project Risk Manager

62
Contractor Controlled Insurance Program
(CCIP)Overview
  • The Terms of the CCIP Insurance Manual are part
    of the Subcontract, and apply to sub-tier subs at
    all levels
  • Sections 1 and 2 comprise the CCIP Overview and
    Contacts
  • Generally, all Subcontractors on-site full time
    are Enrolled status subs and off-site or
    part-time subcontractors are Excluded status
    subs.
  • Waivers for Enrolled or Excluded status must
    be in writing from the DTP Project Risk Manager

63
Contractor Controlled Insurance Program
(CCIP)Insurance Coverage
  • Section 3 describes Insurance Coverage provided
    in the CCIP
  • Coverage includes Workers Compensation,
    Commercial General Liability, Builders Risk, and
    Marine Cargo insurance.
  • Coverage is very broad, with appropriate limits
    for a large public works project
  • Section 4 describes Subcontractor-provided
    insurance requirements.
  • All subs of all tiers must provide their own Auto
    Liability and Contractors Equipment Insurance

64
Contractor Controlled Insurance Program
(CCIP)Subcontractor Responsibilities
  • Section 5 details subcontractor CCIP
    responsibilities and represent a contractual
    commitment
  • During estimate preparation, Aon Forms 1 and 2
    must be completed to affirm that no costs covered
    by CCIP insurances are included in the bid price
  • No deductibles are assessed, therefore no
    deductible costs should be included the bid price
  • Bid price is subject to audit to ensure CCIP and
    other costs are excluded from pricing

65
Contractor Controlled Insurance Program
(CCIP)Subcontractor Responsibilities
  • Enrollment must be completed before access to the
    site is permitted
  • Simple online enrollment process
  • All Enrolled subcontractors of all tiers must use
    the online system
  • Excluded sub-tier contractors must also be
    reported online, and their Certificate of
    Insurance submitted to CCIP Administrator for
    review and acceptance
  • Payroll for all Enrolled subs must be reported
    online monthly

66
Contractor Controlled Insurance Program
(CCIP)Claim Reporting
  • All claims must be reported the DTP Risk Manager
  • CCIP claims will be managed by DTP
  • Non-CCIP claims, (e.g. Auto Liability) must be
    reported to DTP Risk Manager, but managed by
    subcontractor
  • DTP has an aggressive Return-to-Work policy for
    all workers to ensure minimal financial impact to
    our team of employees

67
QUALITY ASSURANCE
  • Dinesh Kansal
  • Project Quality Manager

68
DCMP Quality Management System (QMS) Requirements
69
ISO 9001 Quality Management System Requirements
  • Design Control
  • Document Control
  • Procurement Activities
  • Inspection Testing
  • Control of Non-conformances
  • Calibration of Measurement Testing Equipment
  • Personnel Training
  • Quality Audits

70
QMS Implementation By Subcontractors
  • Project Specific Quality Plan
  • Cover full scope of work
  • Applicable to Partners/Subcontractors
  • Reviewed by DTP
  • Inspection Test Plan (ITP)
  • DTP MWAA Witness Hold Points
  • Quality Activities Subject to DTP/MWAA
    Surveillances/Audits
  • Constraint Regarding Commencement of Construction
    Activities

71
BID OPPORTUNITIES
  • Chad Bordovsky
  • Subcontracts Administration Manager
  • Cheryl Hatcher
  • Project Procurement Manager

72
Request for Proposal Requirements
  • Prequalification Requirements
  • Package-specific prequalification questionnaires
    are issued for some of the subcontract packages.
    Suppliers and subcontractors are pre-qualified
    based on
  • Financial Responsibility
  • Safety Program and Statistics
  • Technical Qualifications
  • Available Capacity/Resources
  • Excluded Parties List
  • Bonding Requirements
  • Bid Bonds are required on some subcontract
    packages.
  • Performance and Payment Bonds are required on all
    construction subcontracts.

73
Request for Proposal Requirements
  • Pricing Documentation
  • Certified pricing documentation will be required
    prior to award for all subcontracts valued at 5M
    or more.
  • Insurance Submittals
  • Insurance certificates
  • QA-QC
  • QA-QC plan is required on some of the subcontract
    packages
  • DBE Requirements
  • DBE goals are set for all major packages
  • ESH
  • Safety plans and statistics are required for all
    packages
  • Key Personnel
  • Resumés and relevant experience must be provided
    for identified key personnel
  • Construction Equipment and Manpower
  • Identify construction equipment and manpower
    capabilities

74
Federal Requirements
  • Buy American Act
  • Clean Water
  • Lobbying
  • Certification Contracts, Grant Loans
  • Retention of Records
  • Federal Transit Administration (FTA)
  • Davis Bacon and Copeland (Labor)
  • Certified Payrolls (Submitted with Invoices)

75
Construction Subcontract Packages
76
Construction Subcontract Packages
77
Construction Subcontract Packages
78
Purchasing Packages
Engineered Items Commodity Items
79
Purchasing Packages
Engineered Items Commodity Items
80
Purchasing Packages
Engineered Items Commodity Items
81
  • Thank You!
Write a Comment
User Comments (0)
About PowerShow.com