Title: Cost reflectivity of investment proxies
1Cost reflectivity of investment proxies
- CAP131 Working Group (2)
- 27 October 2006
2Action
- Action
- To explore the cost reflectivity of various
proxies for infrastructure investments, which
need to be supported bya user commitment - Aim
- To establish whether there are more
cost-reflective investment proxies than TNUoS
tariffs and consider whether these are better
when assessed against the Applicable CUSC
Objectives
3Process Map
Identify groups of projects that require similar
system reinforcements
Establish unit capital investment costs (/kW)
for groups
Compare annual investment proxy to capital
investment costs
Express as a number of years of the investment
proxy
Calculate average spread between project groups
as measure of cost reflectivity
4Investment costs for groups
- Several groups of projects considered, where each
group requires similar transmission investments - represents a sample of 25GW of generation
- Investments consider a range of scenarios within
group - One investment group is illustrated below
- Gradient gives average capital investment cost in
/kW
5Investment proxies considered
- All proxies been derived from the TNUoS model
- Retained 3/kW p.a. de-minimis for local
substation works - Nodal investment proxies
- full tariffs
- locational tariffs
- Zonal investment proxies
- full TNUoS tariffs
- locational TNUoS tariffs
- re-zeroed TNUoS differential tariffs (no
residual)
Removes the revenue recovery adjustmentsi.e. the
residual
Establishes alternative electrical centre of
system(see next slides)
6Why consider re-zeroing?
- Additional generation triggers reinforcement to
load centres - DCLF model establishes a system centre (the
slack node) - The slack node is the most interconnected node
and is arbitrarily assigned an incremental cost
of zero (0MWkm) - The real incremental cost at the slack node
is not zero - Investment required to transfer the marginal MW
to the load
7Is Thorpe Marsh an appropriate centre?
Thorpe Marsh isthe slack node (SN)
B7
B8
8Effect of different zero pointsAlternative
zero-points considered
- Investigated the effect of considering different
zero points - Have considered
- Peninsula (Zone 21, -5.53 /kW)
- Central London (Zone 16, -1.97 /kW))
- South Yorkshire North Wales (Zone 14, 0.31
/kW) - The aim is to identify which zero-point provides
the best fit to actual investment costs incurred
Contains the slack node, Thorpe Marsh
tariffs presented exclude the residual element
9Effect of different zero pointsInvestment
proxies with different zero points
10Effect of different centres of loadIdentifying
the most appropriate zero point
Zonal TNUoS with no locational component, with
different zero points
Standard deviation is used as a measure of cost
reflectivity
Central London gives best fit to investment costs
11Zonal investment proxies
12Nodal investment proxies
- Where possible, the nodal marginal km at the node
where generation is expected to connect has been
converted to a tariff by considering - re-referencing quantity
- security factor
- expansion constant
- Has not been applied to all projects, as nodes do
not presently exist within transport model - analysis covers 19GW of sample pool (25GW)
same parameters used tocalculate zonal tariffs
13Establishing number of years of proxy
- For each group, actual investment costs (/kW)
are compared with applicable investment proxy
(/kW) - where a zonal proxy has been used, the zone that
best represents projects within a group has been
used
Range of annual proxies tested
ActualCapitalCost (/kW)
Annual ProxyCost (/kW)
Number of years ofproxy
across all investmentgroups
Average and St. Dev.
14Analysis resultsZonal Nodal investment proxies
15Observations
- Nodal approach does not add extra
cost-reflectivity - no smoothing for lumpiness of a nodal cost
- adds complexity to the methodology for little
return - Trade-off between number of years of the
investment proxy and the magnitude of that proxy - low number of years, high proxy cost
- high number of years, low proxy cost
16Wider assessment of investment proxies
- Cost reflectivity is not an applicable CUSC
objective, it is part of facilitating competition - Important, therefore, to consider other criteria
against which the investment proxies should be
assessed - transparency of methodology to derive proxy
- ease for both Users and National Grid to
determine commitment - ease of application to new entry points i.e.
nodes that dont exist - others?
17Wider assessment a starter for ten
18Conclusions
- TNUoS tariffs provide a reasonable investment
proxy - TNUoS tariffs without the residual re-centred
on Central London provides a more cost reflective
investment proxy - However, would require additional arrangements to
overcome transparency issues and could be
confusing for new entrants