Cost reflectivity of investment proxies - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Cost reflectivity of investment proxies

Description:

Zonal TNUoS with no locational component, with different zero points ... where a zonal proxy has been used, the zone that best represents projects within ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 19
Provided by: AdamB56
Category:

less

Transcript and Presenter's Notes

Title: Cost reflectivity of investment proxies


1
Cost reflectivity of investment proxies
  • CAP131 Working Group (2)
  • 27 October 2006

2
Action
  • Action
  • To explore the cost reflectivity of various
    proxies for infrastructure investments, which
    need to be supported bya user commitment
  • Aim
  • To establish whether there are more
    cost-reflective investment proxies than TNUoS
    tariffs and consider whether these are better
    when assessed against the Applicable CUSC
    Objectives

3
Process Map
Identify groups of projects that require similar
system reinforcements
Establish unit capital investment costs (/kW)
for groups
Compare annual investment proxy to capital
investment costs
Express as a number of years of the investment
proxy
Calculate average spread between project groups
as measure of cost reflectivity
4
Investment costs for groups
  • Several groups of projects considered, where each
    group requires similar transmission investments
  • represents a sample of 25GW of generation
  • Investments consider a range of scenarios within
    group
  • One investment group is illustrated below
  • Gradient gives average capital investment cost in
    /kW

5
Investment proxies considered
  • All proxies been derived from the TNUoS model
  • Retained 3/kW p.a. de-minimis for local
    substation works
  • Nodal investment proxies
  • full tariffs
  • locational tariffs
  • Zonal investment proxies
  • full TNUoS tariffs
  • locational TNUoS tariffs
  • re-zeroed TNUoS differential tariffs (no
    residual)

Removes the revenue recovery adjustmentsi.e. the
residual
Establishes alternative electrical centre of
system(see next slides)
6
Why consider re-zeroing?
  • Additional generation triggers reinforcement to
    load centres
  • DCLF model establishes a system centre (the
    slack node)
  • The slack node is the most interconnected node
    and is arbitrarily assigned an incremental cost
    of zero (0MWkm)
  • The real incremental cost at the slack node
    is not zero
  • Investment required to transfer the marginal MW
    to the load

7
Is Thorpe Marsh an appropriate centre?
Thorpe Marsh isthe slack node (SN)
B7
B8
8
Effect of different zero pointsAlternative
zero-points considered
  • Investigated the effect of considering different
    zero points
  • Have considered
  • Peninsula (Zone 21, -5.53 /kW)
  • Central London (Zone 16, -1.97 /kW))
  • South Yorkshire North Wales (Zone 14, 0.31
    /kW)
  • The aim is to identify which zero-point provides
    the best fit to actual investment costs incurred

Contains the slack node, Thorpe Marsh
tariffs presented exclude the residual element
9
Effect of different zero pointsInvestment
proxies with different zero points
10
Effect of different centres of loadIdentifying
the most appropriate zero point
Zonal TNUoS with no locational component, with
different zero points
Standard deviation is used as a measure of cost
reflectivity
Central London gives best fit to investment costs
11
Zonal investment proxies
12
Nodal investment proxies
  • Where possible, the nodal marginal km at the node
    where generation is expected to connect has been
    converted to a tariff by considering
  • re-referencing quantity
  • security factor
  • expansion constant
  • Has not been applied to all projects, as nodes do
    not presently exist within transport model
  • analysis covers 19GW of sample pool (25GW)

same parameters used tocalculate zonal tariffs
13
Establishing number of years of proxy
  • For each group, actual investment costs (/kW)
    are compared with applicable investment proxy
    (/kW)
  • where a zonal proxy has been used, the zone that
    best represents projects within a group has been
    used

Range of annual proxies tested
ActualCapitalCost (/kW)
Annual ProxyCost (/kW)
Number of years ofproxy


across all investmentgroups
Average and St. Dev.
14
Analysis resultsZonal Nodal investment proxies
15
Observations
  • Nodal approach does not add extra
    cost-reflectivity
  • no smoothing for lumpiness of a nodal cost
  • adds complexity to the methodology for little
    return
  • Trade-off between number of years of the
    investment proxy and the magnitude of that proxy
  • low number of years, high proxy cost
  • high number of years, low proxy cost

16
Wider assessment of investment proxies
  • Cost reflectivity is not an applicable CUSC
    objective, it is part of facilitating competition
  • Important, therefore, to consider other criteria
    against which the investment proxies should be
    assessed
  • transparency of methodology to derive proxy
  • ease for both Users and National Grid to
    determine commitment
  • ease of application to new entry points i.e.
    nodes that dont exist
  • others?

17
Wider assessment a starter for ten
18
Conclusions
  • TNUoS tariffs provide a reasonable investment
    proxy
  • TNUoS tariffs without the residual re-centred
    on Central London provides a more cost reflective
    investment proxy
  • However, would require additional arrangements to
    overcome transparency issues and could be
    confusing for new entrants
Write a Comment
User Comments (0)
About PowerShow.com