Monthly 2_25 Page 15 - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Monthly 2_25 Page 15

Description:

This task was completed. The ASPERA-3 Lead Mech. Eng. ... SwRI ELS FM/FS. Delivery. Prototype Design. Prototype Layout. Prototype Fabrication & Testing ... – PowerPoint PPT presentation

Number of Views:50
Avg rating:3.0/5.0
Slides: 16
Provided by: johnsc4
Category:
Tags: fm | monthly | page | task

less

Transcript and Presenter's Notes

Title: Monthly 2_25 Page 15


1
Monthly Status Report Report due 2/25/00 Schedule
statused as of Feb. 11, 2000
2
Project Status Summary
  • Technical
  • Dec Jan Feb

Programmatic Dec Jan Feb
Schedule Dec Jan Feb
Resources Dec Jan Feb
Detailed Description (for items identified as
yellow or red)
  • We do not see any problems at this time either
    technical, schedule, resources or programmatic.
    We are still on schedule though the schedule is
    tight. Over the last month we brought on
    additional personnel to help solve our resource
    concern.
  • Latest project photos are available on Aspera-3
    web site.

3
Problem and Concern Summary
PProblem CConcern RResolved
4
Accomplishments of the Last Month -ELS
  • Nearly finalized bench test of the HVPS (will be
    complete by 2/25/00).
  • Completed the bench test of the of the prototype
    Front End Electronics (FEE). Only one cut /
    jumper is needed to board. We are now evaluating
    using prototype board (bought with Certs) for
    flight.
  • Finalized the machining of the housing, tophat
    plate and inner deflection plate. Delivered
    these parts (and samples) to Walton Plating for
    coating.
  • Mechanical analysis temporarily put on hold due
    to personnel priorities. Preliminary results
    have been generated.
  • Continued discussions with Walton Plating. Lead
    Mech. Eng. delivered parts to Walton the first
    week in February. Held discussions with Walton
    and MSSL re jigs, fixtures, shipping, schedules,
    etc. We are still negotiating the final cost.
  • Got the Astrid EGSE up and running. The Astrid
    EGSE will be modified to become the ELS EGSE.

5
Accomplishments of the Last Month - IMA
  • Completed layout of the two printed circuit
    boards (anode / amplifier board digital board).
  • Received quote for fabrication of prototype
    boards. Boards to be ordered (w/ certs) 2/25/00.
  • Finalized the mechanical design of IMA detector
    subassembly.
  • Mass estimate looks good.

6
Accomplishments of the Last Month - Data
Reduction Software
  • Ordered Software Development System Computer
    Hardware and Software
  • Configured On-Line Document Management System and
    Began Submission Process
  • Provided Technical Assistance for EPO Web
    Information
  • Began Implementation of Basic Web Tools for IDFS
    Information Gathering
  • Continued Defining IDFS Web Tools
  • Gathered Latest Information for Data System
    Interface Document
  • Continued work on Project Data Management Plan
  • Identified IDFS Example and Provided IDFS
    Documentation to PDS
  • Held monthly ASPERA-3 Software Status Meeting
    (Feb. 15, 2000)

7
Major Reviews / Meetings
  • Two major ASPERA-3 reviews / meetings were held
    during the last month
  • ASPERA-3 review held in Kiruna attended by
    science and engineering
  • Mars Express Data System Review held at ESOC
    attended by software personnel
  • The Kiruna review was a thorough detailed design,
    interface, and status review of all of our
    hardware activities.
  • Minutes and Action Items were assigned and are
    being tracked by IRF PM.
  • Minutes of Meeting are available.

8
Planned Activities for the Next Month - ELS
  • Finish bench testing of HVPS.
  • Mate HVPS to FEE and check for electrical
    compatibility.
  • Perform fit check of housing, HVPS and FEE.
  • Finalize mechanical analysis report.
  • Begin cabling for ELS vacuum tests.
  • Begin modification of the Astrid EGSE to use for
    ELS. Test EGSE with prototype ELS FEE as stim
    source.

9
Planned Activities for the Next Month - IMA
  • Receive and populate circuit boards.
  • Finalize fabrication of IMA prototype mechanical
    parts.
  • Finalize the mechanical analysis.
  • Begin design of the IMA EGSE.

10
Planned Activities for the Next Month - Data
Reduction Software Tasks
  • Set up ASPERA-3 Processing and Archiving Facility
    (APAF) Lab and Configure APAF Network and Servers
  • Complete ASPERA-3.org Web Site Documentation
  • Continue Technical Assistance for EPO Web
    Information
  • Continue Implementation of IDFS Web Tools
  • Continue to Define IDFS Information Gathering
    Tools
  • Update Data System Interface Document Based on
    Latest Information
  • Continue work with PDS on Project Data Management
    Plan
  • Release Next Revision of Software Development
    Plan

11
Problem and Concern Status (cont.)
  • Set up the Project Management Web Site
  • The site is set up with rules established among
    the team. We still need to issue passwords to
    people outside the project but the Web site is up
    and running and is no longer a concern.
  • MOU / SOW with MSSL for UV coating
  • Still in work. All of the details have been
    worked out except the dollar amount that is being
    asked for by MSSL. Our Lead Mechanical Engineer
    visited MSSL last month and has worked out all
    technical details. MSSL price is higher than they
    originally quoted and that we currently have
    budgeted. They are still looking at ways to
    reduce cost.

12
Problem and Concern Status (cont.)
  • Get ELS EGSE up and running
  • Thanks to multiple emails, we made great progress
    on the GSE over the last month. The Astrid EGSE
    is currently running but has not yet been fully
    tested. During the next month we, will hook the
    ELS Prototype FEE to the GSE and verify its
    functionality.
  • Finish ELS prototype parts for delivery to
    plating first week in February
  • This task was completed. The ASPERA-3 Lead Mech.
    Eng. delivered all of the prototype parts that
    require UV coating to MSSL during the last month.
    They are now being prepped for coating.

13
Problem and Concern Status (cont.)
  • Getting final contract in Place by March 1, 2000
  • We have submitted a March 1 - 31 proposal to
    obtain additional time for contract
    difinitization. We hope that this will ultimately
    lead to closure on the final contract.
  • Fabrication of IMA MCP Holder
  • The fabrication of the ELS MCP holder is a minor
    concern. It is a rather simple subassembly that
    has lots of flight heritage. Our concern has to
    do with the tight machining tolerances that we
    feel are needed.

14
Schedule Summary
  • Total float on the tasks in the schedule has not
    changed very much since last month.
  • Mechanical (IMA MCP holder) is the critical path
    (16 days plus). As with last month
  • Schedule still has 21 days slack at the end
    (DEL0050) in addition to float shown for each
    task
  • FEE HVPS have 20 days each allotted for mods
    after prototype testing.
  • All flight activity is completely serial with
    prototype activities. We can (will) do
    activities in parallel to maintain schedule.
  • We did modify the flow of activities to better
    reflect the current thinking regarding the
    prototype coating task.
  • IMA Detector subassembly mechanical tasks are now
    driving the hardware tasks.
  • Software activities are on schedule.
  • Full-up schedule is available on the ASPERA-3 Web
    site.

15
ASPERA-3 PHASE B/C/D MASTER SCHEDULE
2003
2002
2001
2000
1999
J
J
A
S
O
N
D
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
M
A
MAJOR MILESTONES / REVIEWS
ASPERA CDR
ASPERA PDR
SwRI ELS IMA Delivery to IRF
IRF ELS IMA Delivery to ESA
ESA LAUNCH
KEY
INSTRUMENT DEVELOPMENT
ELS PDR
SwRI ELS FM/FS Delivery
CDR
MAJOR MILESTONE
STM
ELS
- Electron Spectrometer Imager
SUMMARY
Mechanical
SCHEDULED START
P
Design
F
SCHEDULED COMPLETION
P
Detail Design
EARLY START/COMPLETION
F
P
LATE START/COMPLETION
Mechanical Fabrication
RESERVES
F
Microchannel Plates (MCPs)
CRITICAL PATH
F
P
MCPs Avail
MCP Procurement
P PROTOTYPE
F FLIGHT
MCP Characterization
Structural Thermal Model (STM) Fabrication
STM Test Delivery
STM Delivery
Electrical
HV Power Supply (HVPS)
P
HVPS Design
F
P
HVPS Layout
F
HVPS Fabrication
F
P
HVPS Testing
F
P
Anode Assemby
P
Anode Board Design Modifications
F
Anode PWA Layout
P
F
P
Anode Fabrication
F
P
Anode Testing
F
Sensor Integration Test
Sensor Assembly
P
F
Sensor Bench Test
F
P
ELS FM/Flt. Spare Delivery to IRF
Sensor Testing Characterization (_at_ SwRI)
P
ELS Calibration (_at_ IRF) Delivery to ESA
IMA
- Ion Mass Analyzer Imager
IMA PDR
SwRI IMA FM/FS Delivery
Prototype Development
CDR
IMA Definition
Prototype Design
Prototype Layout
Prototype Fabrication Testing
Flt. Model / Flt. Spare Development
FM/FS Design Modification
FM/FS Layout
FM/FS Fabrication Assembly
MCP Need Date
MCPs Reqd
IMA FM/Flt. Spare Delivery to IRF
FM Sensor Characterization (_at_ SwRI)
IMA Calibration (_at_ IRF) Delivery to ESA
IMA FM/FS IT
Processing Software
Software Concept Requirements
Virtual Instrument Design
Virtual Instrument S/W Coding
Virtual Instrument S/W Testing
S/W Integration w/Sensor Calibration
Instrument Support
Engineering Support
Science Planning Support
Software Development Support
Southwest Research Institute
Orig Approval 6/25/99
Rev None
Approval John Scherrer, Project Mgr.
Last Change 8/13/99
Denotes a Change/Slip
Status As Of 2/25/00
Write a Comment
User Comments (0)
About PowerShow.com