Title: Projects of Note
1Projects of Note
- Singapore International Water Week22-26 June 2009
2Hyperlinks to Projects of Note
- SINGAPORE
- Changi NEWater Plant
- Lower Seletar Waterworks
- Jurong Membrane Bioreactor Plant
- SingSpring Desalination Plant
- Chestnut Avenue Waterworks
- Upgrading of the Choa Chu Kang Waterworks
- AUSTRALIA
- Bundamba Advanced WTP, Stage 1A
- W2W Alliance
- Eastern Treatment Plant Tertiary Upgrade Project
Phase 1 - Wanneroo Groundwater Treatment Plant
- HONG KONG
- Tai Po Water Treatment Works and Aqueducts
Project - Water Mains Rehabilitation Project Stages 1, 2
- Tai Hang Tung Storm Water Storage Tank
- Kai Tak Storm Water Transfer Tunnel
- Wan Chai East and North Point Sewerage Project
- Drainage Master Plans
- Engineering Strategy on Total Water Management
for Hong Kong
- USA
- Lake Pleasant Water Treatment Plant
- Columbia Heights Membrane Filtration Plant
- Scottsdale Water Campus
3Changi NEWater Plant Client Sembcorp Utilities
- 228 MLD NEWater plant in Singapore
- Design-Build-Own-Operate
- Singapores fifth and largest recycled plant
- Unique design that reduces land use and minimizes
construction costs - Advanced water treatment processes MF/UF-RO-UV
technologies
?
SINGAPORE
4Changi NEWater Plant Client Sembcorp Utilities
- The major design elements are equalization tanks,
feedwater pump and MF feed pumps - Water treatment facilities include in-line
micro-strainers, mircofiltration (MF), two-pass
reverse osmosis (RO), and UV NEWater storage
tanks - NEWater pumping station as part of the PUB
handover facilities, chemical feed storage
facilities, and associated electrical and control
facilities
?
SINGAPORE
5Changi NEWater Plant Client Sembcorp Utilities
- BV's roles include
- Detailed engineering design services
- Startup support and commissioning
?
SINGAPORE
6Lower Seletar Waterworks Client PUB
- 273 MLD waterworks and ancillary facilities in
Singapore - First plant in Singapore to use on-site
generation of chlorine - If pressure membranes are selected, it would be
the largest in the world for drinking water
application
?
SINGAPORE
7Lower Seletar Waterworks Client PUB
- BV's roles include
- Study
- Design
- Construction supervision
?
SINGAPORE
8Jurong Membrane Bioreactor (MBR) Plant Client
PUB
- 68 MLD MBR plant in Singapore
- Largest MBR plant in Singapore and one of the
most significant in the Asia Pacific region
?
SINGAPORE
9Jurong Membrane Bioreactor (MBR) Plant Client
PUB
- BV's roles include
- Study
- Design
- Construction supervision
?
SINGAPORE
10SingSpring Desalination Plant Client SingSpring
- 136 MLD desalination plant in Singapore
- Build-Own-Operate
- Feedwater TDS 28,000-35,000 mg/l
- First pass seawater RO partial second pass
brackish water RO - Brine disposal ocean
?
SINGAPORE
11SingSpring Desalination Plant Client SingSpring
- Open seawater intake structure
- Two separate inlet channels equipped with
mechanical rake coarse screens - 3D digital rendering of pipe gallery design
AS BUILT
PRELIMINARY DESIGN, 3D RENDERING
?
SINGAPORE
12SingSpring Desalination Plant Client SingSpring
- DAF facility removes oil, grease, and suspended
solids prior to primary gravity sand filters - Dechlorination chemicals added upstream and
downstream of the cartridge filters leading to
the RO plant - pH adjustments also required downstream of
cartridge filters
?
SINGAPORE
13SingSpring Desalination Plant Client SingSpring
- First pass RO removes dissolved solids from the
flow - Second pass RO reduces boron level in treated
water - Treated water tanks pump treated water into the
main transmission line - Energy recovery system minimizes operating costs
- Pelton wheel system with pressure exchange energy
recovery
?
SINGAPORE
14SingSpring Desalination Plant Client SingSpring
- BV's roles include
- Pilot testing
- Design
- Permitting
- Construction services
- OM assistance
?
SINGAPORE
15Chestnut Avenue Waterworks Client PUB
- 273 MLD water treatment plant in Singapore
- Grand Prize 2003 Design Excellence Awards,
ACES - Distinction Water Treatment Plant of the Year,
2003 Global Water Awards - At the time was the largest potable water
treatment facility in the world incorporating
membrane filtration - Enhanced coagulation using alum followed by
immersed ultra-filtration membranes
?
SINGAPORE
16Chestnut Avenue Waterworks Client PUB
- The plant is a perfect example of the application
of sound but simple engineering design and
out-of-the box thinking to meet the site
challenges of limited footprint and energy costs
?
SINGAPORE
17Chestnut Avenue Waterworks Client PUB
- BV's roles include
- Study
- Design
- Construction supervision
- Commissioning
?
SINGAPORE
18Upgrading of the Choa Chu Kang Waterworks
Client PUB
- 364 MLD water treatment plant in Singapore
- Maximizes hydraulic profile to reduce energy
consumption - One of the largest retrofit of an immersed
membrane plant in the world whilst the plant was
still in production - Cutting-edge application of gravity-driven
membranes
?
SINGAPORE
19Upgrading of the Choa Chu Kang Waterworks
Client PUB
- Undertook feasibility study into upgrading the
364 MLD works for compliance with WHO drinking
water standards - The process options study included combinations
of membrane filtration, ozonation, BAC,
chlorination, hydrogen peroxide dosing - Pilot plant trials were carried out on membranes
and the lessons applied to inform the detailed
design - BV carried out cost estimation for all options
?
SINGAPORE
20Upgrading of the Choa Chu Kang Waterworks
Client PUB
- BV's roles include
- Design
- Construction supervision
- Commissioning
?
SINGAPORE
21Bundamba Advanced Water Treatment Plant, Stage
1A (BV and Thiess Joint Venture) Client
Western Corridor Recycled Water Pty Ltd.
- 66 MLD AWTP in Queensland, Australia
- BV/Thiess joint venture in alliance with
Western CorridorRecycled Water - 2007 Global Water Project of the Year - Global
Water Intelligence - Largest recycled water plant in southern
hemisphere - First application of 450mm (18) diameter Reverse
Osmosis membranes on a large scale
?
AUSTRALIA
22Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
- The team that worked on Bundamba AWTP had to meet
a very aggressive schedule by any standard
worldwide
?
AUSTRALIA
23Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
- By end of July 2007 over 15,600 m3 of concrete
had been poured, MF/RO commissioning started and
over 730,000 staff hours had been clocked up on
site since inception
?
AUSTRALIA
24Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
- The Bundamba AWTP is the first application of 450
mm diameter (18-in) RO membranes on a large scale - It is also the first full scale water reclamation
facility designed to meet stringent nitrogen
disinfection and emerging contaminant quality
parameters
?
AUSTRALIA
25Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
- The team successfully delivered first water at
the end of August 2007, faster than many thought
possible
?
AUSTRALIA
26Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
- The main treatment steps of ultrafiltration
(UF) membranes, reverse-osmosis (RO) membranes
followed by advanced oxidation using UV
irradiation and hydrogen peroxide make up the
first large scale Indirect Potable Reuse (IPR)
Scheme in Australia
?
AUSTRALIA
27Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
- Black Veatch/Thiess Joint Venture executed the
project outside of historical and regional
boundaries using a truly Integrated Global
Workforce to enable detailed design to be
completed to support the ambitious schedule
?
AUSTRALIA
28Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
- Safety record on Stage 1A of the Bundamba AWTP
was exemplary. In September 2007 the project
exceeded 1 million person hours of work with not
one lost time injury
?
AUSTRALIA
29W2W Alliance Client Water Corporation of
Western Australia
- A 352M to upgrade the three largest wastewater
treatment plants in Perth, Australia - EPC contract
- Process expertise, integrated global workforce
for engineering delivery, global procurement,
planning and scheduling construction and
commissioning in operational plants
?
AUSTRALIA
30W2W Alliance Client Water Corporation of
Western Australia
- The odour control facilities will be the first
in WA to implement bio-scrubber technology to
reduce the chemical requirements in the odour
scrubbing process
?
AUSTRALIA
31W2W Alliance Client Water Corporation of
Western Australia
- BV's roles include
- Engineering, Procurement, Construction
- Commissioning services
?
AUSTRALIA
32Eastern Treatment Plant Tertiary Upgrade Project
Phase 1 Option Design, Costing and Assessment
Client Melbourne Water
- ETP is one of the largest wastewater treatment
plants in Australia - Currently an activated sludge plant producing
Class C effluent - The Tertiary Upgrade will up to 700 MLD of
secondary effluent to Class A standard - Upgrade will use tertiary filtration and enhanced
disinfection treatment processes - Aesthetic parameters will also be addressed
?
AUSTRALIA
33Eastern Treatment Plant Tertiary Upgrade Project
Phase 1 Option Design, Costing and Assessment
Client Melbourne Water
- BV's roles include
- Trials plant evaluation and process design
- Preliminary engineering design
- Cost-estimation - Capex and Opex
- Options evaluation and assessment
AUSTRALIA
?
34Wanneroo Groundwater Treatment Plant Client
Water Corporation of Western Australia
- 225 MLD facility in Australia
- Engineer-Procure-Construct
- Employs conventional aeration, coagulation,
sedimentation and dual media filtration processes
to treat source water
Photo credit http//water-technology.net
?
AUSTRALIA
35Wanneroo Groundwater Treatment Plant Client
Water Corporation of Western Australia
- The Project Cost at completion was within 1 of
the budgeted EPC Cost - Clear program milestones and careful advance
planning of plant shutdowns and tie-ins to the
existing operating plant resulted in completion
of the construction phase in early November 2001,
the target date - BVs roles include
- Design
- Construction
- Commissioning management
AUSTRALIA
?
36Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
- Ultimate capacity of 1200 MLD in Hong Kong, SAR
- Global Grand Prize in the Design Category IWA
Project Innovation Awards in 2006 - Installation of aerated biological filtration,
one of the largest in the world - First major use of dissolved air flotation (DAF)
in Hong Kong
HONG KONG
?
37Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
- Major water treatment works, pumping stations,
reservoirs and associated aqueducts study to
maximise treatment capacity within the available
site, leading to detailed design, preparation of
tender documents and construction supervision
HONG KONG
?
38Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
- Pilot plant work to verify use of biological
filtration for ammonia removal - Primary service reservoir 40 000 m3, ultimate
capacity 200 000 m3 - Design criteria include for seismic conditions,
design takes account of steeply sloping ground
and congested site
HONG KONG
?
39Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
- Contract management including supervision of
works on site, programme and progress control,
control of interim and final payments, design
amendments for unforeseen conditions, claims
review and assessment, forecast of final
contract price - Project management, including procurement,
programme control, continuous review of
contractors progress, Critical Path analysis,
document control
HONG KONG
?
40Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
- BV's roles include
- Investigation
- Design
- Construction supervision
HONG KONG
?
41Water Mains Rehabilitation Project Stages 1 and 2
Client Water Supplies Department
- A total of 1,030 km of watermains in Stage 1, 2
and 4 respectively from 2000 to 2015 - 540 km of watermains for rehabilitation in Hong
Kong, SAR - Pipe sizes ranging from DN20 up to DN2300
- Use of innovative techniques, including the
largest swagelining operation ever undertaken in
Asia, BV is replacing and rehabilitating Hong
Kong watermains and saving time and costs - Use of trenchless technology (on-line rehab) for
over 7km of large trunk watermains installed
under an existing live road tunnel - Condition assessment of watermains using
intrusive techniques
HONG KONG
?
42Water Mains Rehabilitation Project Stages 1 and
2 Client Water Supplies Department
- For Stage 1 77 km of watermains in New
Territories North - For Stage 2
- 130 km of watermains on Hong Kong Island, Lantau
Island and Cheung Chau - 160 km of watermains in the New Territories East
- 250 km of watermains in the New Territories West
- For Stage 4 413 km of watermains in New
Territories
HONG KONG
?
43Water Mains Rehabilitation Project Stages 1 and 2
Client Water Supplies Department
- BV's roles include
- Investigation
- Design
- Construction supervision
HONG KONG
?
44Tai Hang Tung Storm Water Storage Tank Client
Drainage Services Department
- Underground reinforced concrete storage tank in
Hong Kong, SAR - Pumping station
- Connections to the existing upstream and
downstream drainage systems - A unique triple weir inlet
- A vehicular access tunnel for maintenance
purposes and landscaping works - Awarded the Hong Kong Institution of Engineers
Innovation Award for the Construction Industry
2001 2002
HONG KONG
?
45Tai Hang Tung Storm Water Storage Tank Client
Drainage Services Department
- BVs roles include
- Design
- Construction supervision
HONG KONG
?
46Kai Tak Storm Water Transfer Tunnel Client
Drainage Services Department
- 5 m diameter 1.5 km long mixed ground tunnel and
450 m long culverts in Hong Kong, SAR - Stormwater transfer for up to 40 m3/s
HONG KONG
?
47Kai Tak Storm Water Transfer Tunnel Client
Drainage Services Department
- BV's roles include
- Design
- Construction supervision
HONG KONG
?
48Wan Chai East and North Point Sewerage Project
Client Drainage Services Department
- Upgrade of existing trunk sewerage system in a
very dense urban area in Hong Kong, SAR - 225 mm to 1.2 m diameter 14 km long gravity sewer
depths ranging from 1.5 m to 6 m, approximately 1
km by tunneling method and 2.5 km by trenchless
rehabilitation method
HONG KONG
?
49Wan Chai East and North Point Sewerage Project
Client Drainage Services Department
- Use of innovative trenchless technology reduced
the size of construction site areas - Major infrastructure improvements with minimal
disruption to the public while significantly
decreasing some existing environmental pollution
problems
HONG KONG
?
50Wan Chai East and North Point Sewerage Project
Client Drainage Services Department
- BV's roles include
- Preliminary and detailed design
- Construction supervision
HONG KONG
?
51Drainage Master Plans Client Drainage Services
Department
- Yuen Long, Kam Tin, Ngau Tai Mei and Tin Shui Wai
DMP Study - Upgrade options to prevent flooding from the
secondary and local drainage systems feeding the
large main drainage nullahs - Database / GIS system development to form part of
an Asset Management System for the Drainage
Services Department - Implementation of a pilot Real Time Flow
Monitoring System that measures river flow and
depth at twelve locations - Velocity was measured using Time of Flight
technology
HONG KONG
?
52Drainage Master Plans Client Drainage Services
Department
- DMP Study in Sha Tin Tai Po
- Large WSD facilities such as Jubilee Reservoir,
Lower Shing Mun Reservoir and the Plover Cove and
High Island water transfer tunnel systems - Investigations of river and open channel systems
as well as the urban piped stormwater drainage
systems in the new towns - Data collection included flow, topographical and
CCTV systems, while the analysis was carried out
using MIKE 11 and HydroWorks computer models - Improvement options to remove hydraulic
weaknesses in the system were tested on the
models, and the preferred option was taken to the
preliminary design stage - Development of an Asset Management System (AMS)
which began in the Yuen Long and Kam Tin DMP
HONG KONG
?
53Drainage Master Plans Client Drainage Services
Department
- DMP Study in Tuen Mun Sham Tseng
- Upgrade of the secondary and local drainage
systems to the required standard - The DMP was supported by an AMS, specially
adapted for use in the Tuen Mun and Sham Tseng
area
HONG KONG
?
54Drainage Master Plans Client Drainage Services
Department
- DMP Study in Sai Kung, East Kowloon and Southern
Lantau - Study areas ranged from the typical rural Country
Park areas of Sai Kung and Southern Lantau to the
dense commercial, industrial and residential
areas of East Kowloon - The rivers in the study were modelled by MIKE 11
and the urban networks were modelled by
HydroWorks - Introduction of Flood Hazard Assessment, Benefit
Cost Analyses, Flood Risk Mappings and Overland
Flow - Modelling for any proposed major drainage
improvement schemes
HONG KONG
?
55Engineering Strategy on Total Water Management
(TWM) for Hong Kong Client Water Supplies
Department
- To formulate a long-term strategy for balanced
supply and demand of raw water to support the
sustainable development in Hong Kong - All major options of water demand and supply
management measures were considered and evaluated
in terms of (a) quantity (b) cost (c)
environmental impact and (d) public acceptance
Photo credit Hong Kong Water Supplies Department
HONG KONG
?
56Engineering Strategy on Total Water Management
(TWM) for Hong Kong Client Water Supplies
Department
- Recommendation of an integrated strategy for TWM
programme Water Demand Management Side - Enhancing public education on water conservation
- Promotion of use of water saving device
- Active water asset management and leakage control
by the Government - Extension of seawater for toilet flushing
- Water Supply Management Side
- Protection of water resources
- Water reclamation such as non-potable use of
reclaimed water, grey-water reuse and rainwater
harvesting - Development of seawater desalination
Photo credit Hong Kong Water Supplies Department
HONG KONG
?
57Engineering Strategy on Total Water Management
(TWM) for Hong Kong Client Water Supplies
Department
- BV's roles include
- Study
- Public consultation
- Develop preliminary implementation plans and
programmes for proposed TWM measures
Photo credit Hong Kong Water Supplies Department
HONG KONG
?
58Lake Pleasant Water Treatment Plant Client City
of Phoenix
- Innovative solutions for North Americas largest
design-build-operate project - 80 mgd of quality, reliable drinking water for
400,00 households - State-of-the-art process system flocculation,
ozonation, post-filtration granular activated
carbon contractors and ultra-violet
disinfection - 3D object oriented engineering program
USA
?
59Lake Pleasant Water Treatment Plant Client City
of Phoenix
- BV's roles include
- Design Build Operate (DBO)
USA
?
60Columbia Heights Membrane Filtration Plant
Client Minneapolis Water Works
- Largest ultrafiltration plant in the Western
hemisphere - 260 MLD ultrafiltration (UF) membrane water
treatment system - Membrane facility includes new pumping systems,
chemical dosing systems and all ancillaries
within the same building and integrated with
existing coagulation/ flocculation, settling
systems
USA
?
61Columbia Heights Membrane Filtration Plant
Client Minneapolis Water Works
- Architecturally attractive building that blends
into surroundings - 3D technology enables virtual-reality client
reviews and interactions - Training of utility staff on membrane process
- Won the prestigious Water Project of the Year
award at the 2006 Global Water Awards for this
project
PRELIMINARY DESIGN, 3D RENDERING
AS BUILT
USA
?
62Columbia Heights Membrane Filtration Plant
Client Minneapolis Water Works
- BV's roles include
- Design-Bid-Build
USA
?
63Scottsdale Water Campus Client City of
Scottsdale
- WPP for discharge to water supply systems
- 71 MLD AWTP for irrigation and used for
irrigation with excess injected into on-site dry
wells for aquifer recharge - MF/UF and RO membrane plants
- Pilot program led to signification improvements
in energy usage and performance
USA
?
64Scottsdale Water Campus Client City of
Scottsdale
- Membrane micro and ultrafiltration, thin film
reverse osmosis and advanced disinfection - Process design for zero discharge 45 MLD
nitrification / denitrification reclamation
facility - Grand Prize for Excellence in Environmental
Engineering with the American Academy of
Environmental Engineers (AAEE)
USA
?
65Scottsdale Water Campus Client City of
Scottsdale
- BV's roles include
- Detailed design, inclusive of pilot plant trials
USA
?