Projects of Note - PowerPoint PPT Presentation

1 / 65
About This Presentation
Title:

Projects of Note

Description:

Tai Po Water Treatment Works and Aqueducts Project. Water Mains ... Scottsdale Water Campus. Hyperlinks to Projects of Note. B&V - 3. Changi NEWater Plant ... – PowerPoint PPT presentation

Number of Views:411
Avg rating:3.0/5.0
Slides: 66
Provided by: SWA151
Category:

less

Transcript and Presenter's Notes

Title: Projects of Note


1
Projects of Note
  • Singapore International Water Week22-26 June 2009

2
Hyperlinks to Projects of Note
  • SINGAPORE
  • Changi NEWater Plant
  • Lower Seletar Waterworks
  • Jurong Membrane Bioreactor Plant
  • SingSpring Desalination Plant
  • Chestnut Avenue Waterworks
  • Upgrading of the Choa Chu Kang Waterworks
  • AUSTRALIA
  • Bundamba Advanced WTP, Stage 1A
  • W2W Alliance
  • Eastern Treatment Plant Tertiary Upgrade Project
    Phase 1
  • Wanneroo Groundwater Treatment Plant
  • HONG KONG
  • Tai Po Water Treatment Works and Aqueducts
    Project
  • Water Mains Rehabilitation Project Stages 1, 2
  • Tai Hang Tung Storm Water Storage Tank
  • Kai Tak Storm Water Transfer Tunnel
  • Wan Chai East and North Point Sewerage Project
  • Drainage Master Plans
  • Engineering Strategy on Total Water Management
    for Hong Kong
  • USA
  • Lake Pleasant Water Treatment Plant
  • Columbia Heights Membrane Filtration Plant
  • Scottsdale Water Campus

3
Changi NEWater Plant Client Sembcorp Utilities
  • 228 MLD NEWater plant in Singapore
  • Design-Build-Own-Operate
  • Singapores fifth and largest recycled plant
  • Unique design that reduces land use and minimizes
    construction costs
  • Advanced water treatment processes MF/UF-RO-UV
    technologies

?
SINGAPORE
4
Changi NEWater Plant Client Sembcorp Utilities
  • The major design elements are equalization tanks,
    feedwater pump and MF feed pumps
  • Water treatment facilities include in-line
    micro-strainers, mircofiltration (MF), two-pass
    reverse osmosis (RO), and UV NEWater storage
    tanks
  • NEWater pumping station as part of the PUB
    handover facilities, chemical feed storage
    facilities, and associated electrical and control
    facilities

?
SINGAPORE
5
Changi NEWater Plant Client Sembcorp Utilities
  • BV's roles include
  • Detailed engineering design services
  • Startup support and commissioning

?
SINGAPORE
6
Lower Seletar Waterworks Client PUB
  • 273 MLD waterworks and ancillary facilities in
    Singapore
  • First plant in Singapore to use on-site
    generation of chlorine
  • If pressure membranes are selected, it would be
    the largest in the world for drinking water
    application

?
SINGAPORE
7
Lower Seletar Waterworks Client PUB
  • BV's roles include
  • Study
  • Design
  • Construction supervision

?
SINGAPORE
8
Jurong Membrane Bioreactor (MBR) Plant Client
PUB
  • 68 MLD MBR plant in Singapore
  • Largest MBR plant in Singapore and one of the
    most significant in the Asia Pacific region

?
SINGAPORE
9
Jurong Membrane Bioreactor (MBR) Plant Client
PUB
  • BV's roles include
  • Study
  • Design
  • Construction supervision

?
SINGAPORE
10
SingSpring Desalination Plant Client SingSpring
  • 136 MLD desalination plant in Singapore
  • Build-Own-Operate
  • Feedwater TDS 28,000-35,000 mg/l
  • First pass seawater RO partial second pass
    brackish water RO
  • Brine disposal ocean

?
SINGAPORE
11
SingSpring Desalination Plant Client SingSpring
  • Open seawater intake structure
  • Two separate inlet channels equipped with
    mechanical rake coarse screens
  • 3D digital rendering of pipe gallery design

AS BUILT
PRELIMINARY DESIGN, 3D RENDERING
?
SINGAPORE
12
SingSpring Desalination Plant Client SingSpring
  • DAF facility removes oil, grease, and suspended
    solids prior to primary gravity sand filters
  • Dechlorination chemicals added upstream and
    downstream of the cartridge filters leading to
    the RO plant
  • pH adjustments also required downstream of
    cartridge filters

?
SINGAPORE
13
SingSpring Desalination Plant Client SingSpring
  • First pass RO removes dissolved solids from the
    flow
  • Second pass RO reduces boron level in treated
    water
  • Treated water tanks pump treated water into the
    main transmission line
  • Energy recovery system minimizes operating costs
  • Pelton wheel system with pressure exchange energy
    recovery

?
SINGAPORE
14
SingSpring Desalination Plant Client SingSpring
  • BV's roles include
  • Pilot testing
  • Design
  • Permitting
  • Construction services
  • OM assistance

?
SINGAPORE
15
Chestnut Avenue Waterworks Client PUB
  • 273 MLD water treatment plant in Singapore
  • Grand Prize 2003 Design Excellence Awards,
    ACES
  • Distinction Water Treatment Plant of the Year,
    2003 Global Water Awards
  • At the time was the largest potable water
    treatment facility in the world incorporating
    membrane filtration
  • Enhanced coagulation using alum followed by
    immersed ultra-filtration membranes

?
SINGAPORE
16
Chestnut Avenue Waterworks Client PUB
  • The plant is a perfect example of the application
    of sound but simple engineering design and
    out-of-the box thinking to meet the site
    challenges of limited footprint and energy costs

?
SINGAPORE
17
Chestnut Avenue Waterworks Client PUB
  • BV's roles include
  • Study
  • Design
  • Construction supervision
  • Commissioning

?
SINGAPORE
18
Upgrading of the Choa Chu Kang Waterworks
Client PUB
  • 364 MLD water treatment plant in Singapore
  • Maximizes hydraulic profile to reduce energy
    consumption
  • One of the largest retrofit of an immersed
    membrane plant in the world whilst the plant was
    still in production
  • Cutting-edge application of gravity-driven
    membranes

?
SINGAPORE
19
Upgrading of the Choa Chu Kang Waterworks
Client PUB
  • Undertook feasibility study into upgrading the
    364 MLD works for compliance with WHO drinking
    water standards
  • The process options study included combinations
    of membrane filtration, ozonation, BAC,
    chlorination, hydrogen peroxide dosing
  • Pilot plant trials were carried out on membranes
    and the lessons applied to inform the detailed
    design
  • BV carried out cost estimation for all options

?
SINGAPORE
20
Upgrading of the Choa Chu Kang Waterworks
Client PUB
  • BV's roles include
  • Design
  • Construction supervision
  • Commissioning

?
SINGAPORE
21
Bundamba Advanced Water Treatment Plant, Stage
1A (BV and Thiess Joint Venture) Client
Western Corridor Recycled Water Pty Ltd.
  • 66 MLD AWTP in Queensland, Australia
  • BV/Thiess joint venture in alliance with
    Western CorridorRecycled Water
  • 2007 Global Water Project of the Year - Global
    Water Intelligence
  • Largest recycled water plant in southern
    hemisphere
  • First application of 450mm (18) diameter Reverse
    Osmosis membranes on a large scale

?
AUSTRALIA
22
Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
  • The team that worked on Bundamba AWTP had to meet
    a very aggressive schedule by any standard
    worldwide

?
AUSTRALIA
23
Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
  • By end of July 2007 over 15,600 m3 of concrete
    had been poured, MF/RO commissioning started and
    over 730,000 staff hours had been clocked up on
    site since inception

?
AUSTRALIA
24
Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
  • The Bundamba AWTP is the first application of 450
    mm diameter (18-in) RO membranes on a large scale
  • It is also the first full scale water reclamation
    facility designed to meet stringent nitrogen
    disinfection and emerging contaminant quality
    parameters

?
AUSTRALIA
25
Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
  • The team successfully delivered first water at
    the end of August 2007, faster than many thought
    possible

?
AUSTRALIA
26
Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
  • The main treatment steps of ultrafiltration
    (UF) membranes, reverse-osmosis (RO) membranes
    followed by advanced oxidation using UV
    irradiation and hydrogen peroxide make up the
    first large scale Indirect Potable Reuse (IPR)
    Scheme in Australia

?
AUSTRALIA
27
Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
  • Black Veatch/Thiess Joint Venture executed the
    project outside of historical and regional
    boundaries using a truly Integrated Global
    Workforce to enable detailed design to be
    completed to support the ambitious schedule

?
AUSTRALIA
28
Bundamba Advanced Water Treatment Plant, Stage 1A
(BV and Thiess Joint Venture) Client Western
Corridor Recycled Water Pty Ltd.
  • Safety record on Stage 1A of the Bundamba AWTP
    was exemplary. In September 2007 the project
    exceeded 1 million person hours of work with not
    one lost time injury

?
AUSTRALIA
29
W2W Alliance Client Water Corporation of
Western Australia
  • A 352M to upgrade the three largest wastewater
    treatment plants in Perth, Australia
  • EPC contract
  • Process expertise, integrated global workforce
    for engineering delivery, global procurement,
    planning and scheduling construction and
    commissioning in operational plants

?
AUSTRALIA
30
W2W Alliance Client Water Corporation of
Western Australia
  • The odour control facilities will be the first
    in WA to implement bio-scrubber technology to
    reduce the chemical requirements in the odour
    scrubbing process

?
AUSTRALIA
31
W2W Alliance Client Water Corporation of
Western Australia
  • BV's roles include
  • Engineering, Procurement, Construction
  • Commissioning services

?
AUSTRALIA
32
Eastern Treatment Plant Tertiary Upgrade Project
Phase 1 Option Design, Costing and Assessment
Client Melbourne Water
  • ETP is one of the largest wastewater treatment
    plants in Australia
  • Currently an activated sludge plant producing
    Class C effluent
  • The Tertiary Upgrade will up to 700 MLD of
    secondary effluent to Class A standard
  • Upgrade will use tertiary filtration and enhanced
    disinfection treatment processes
  • Aesthetic parameters will also be addressed

?
AUSTRALIA
33
Eastern Treatment Plant Tertiary Upgrade Project
Phase 1 Option Design, Costing and Assessment
Client Melbourne Water
  • BV's roles include
  • Trials plant evaluation and process design
  • Preliminary engineering design
  • Cost-estimation - Capex and Opex
  • Options evaluation and assessment

AUSTRALIA
?
34
Wanneroo Groundwater Treatment Plant Client
Water Corporation of Western Australia
  • 225 MLD facility in Australia
  • Engineer-Procure-Construct
  • Employs conventional aeration, coagulation,
    sedimentation and dual media filtration processes
    to treat source water

Photo credit http//water-technology.net
?
AUSTRALIA
35
Wanneroo Groundwater Treatment Plant Client
Water Corporation of Western Australia
  • The Project Cost at completion was within 1 of
    the budgeted EPC Cost
  • Clear program milestones and careful advance
    planning of plant shutdowns and tie-ins to the
    existing operating plant resulted in completion
    of the construction phase in early November 2001,
    the target date
  • BVs roles include
  • Design
  • Construction
  • Commissioning management

AUSTRALIA
?
36
Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
  • Ultimate capacity of 1200 MLD in Hong Kong, SAR
  • Global Grand Prize in the Design Category IWA
    Project Innovation Awards in 2006
  • Installation of aerated biological filtration,
    one of the largest in the world
  • First major use of dissolved air flotation (DAF)
    in Hong Kong

HONG KONG
?
37
Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
  • Major water treatment works, pumping stations,
    reservoirs and associated aqueducts study to
    maximise treatment capacity within the available
    site, leading to detailed design, preparation of
    tender documents and construction supervision

HONG KONG
?
38
Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
  • Pilot plant work to verify use of biological
    filtration for ammonia removal
  • Primary service reservoir 40 000 m3, ultimate
    capacity 200 000 m3
  • Design criteria include for seismic conditions,
    design takes account of steeply sloping ground
    and congested site

HONG KONG
?
39
Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
  • Contract management including supervision of
    works on site, programme and progress control,
    control of interim and final payments, design
    amendments for unforeseen conditions, claims
    review and assessment, forecast of final
    contract price
  • Project management, including procurement,
    programme control, continuous review of
    contractors progress, Critical Path analysis,
    document control

HONG KONG
?
40
Tai Po Water Treatment Works and Aqueducts
Project Client Water Supplies Department
  • BV's roles include
  • Investigation
  • Design
  • Construction supervision

HONG KONG
?
41
Water Mains Rehabilitation Project Stages 1 and 2
Client Water Supplies Department
  • A total of 1,030 km of watermains in Stage 1, 2
    and 4 respectively from 2000 to 2015
  • 540 km of watermains for rehabilitation in Hong
    Kong, SAR
  • Pipe sizes ranging from DN20 up to DN2300
  • Use of innovative techniques, including the
    largest swagelining operation ever undertaken in
    Asia, BV is replacing and rehabilitating Hong
    Kong watermains and saving time and costs
  • Use of trenchless technology (on-line rehab) for
    over 7km of large trunk watermains installed
    under an existing live road tunnel
  • Condition assessment of watermains using
    intrusive techniques

HONG KONG
?
42
Water Mains Rehabilitation Project Stages 1 and
2 Client Water Supplies Department
  • For Stage 1 77 km of watermains in New
    Territories North
  • For Stage 2
  • 130 km of watermains on Hong Kong Island, Lantau
    Island and Cheung Chau
  • 160 km of watermains in the New Territories East
  • 250 km of watermains in the New Territories West
  • For Stage 4 413 km of watermains in New
    Territories

HONG KONG
?
43
Water Mains Rehabilitation Project Stages 1 and 2
Client Water Supplies Department
  • BV's roles include
  • Investigation
  • Design
  • Construction supervision

HONG KONG
?
44
Tai Hang Tung Storm Water Storage Tank Client
Drainage Services Department
  • Underground reinforced concrete storage tank in
    Hong Kong, SAR
  • Pumping station
  • Connections to the existing upstream and
    downstream drainage systems
  • A unique triple weir inlet
  • A vehicular access tunnel for maintenance
    purposes and landscaping works
  • Awarded the Hong Kong Institution of Engineers
    Innovation Award for the Construction Industry
    2001 2002

HONG KONG
?
45
Tai Hang Tung Storm Water Storage Tank Client
Drainage Services Department
  • BVs roles include
  • Design
  • Construction supervision

HONG KONG
?
46
Kai Tak Storm Water Transfer Tunnel Client
Drainage Services Department
  • 5 m diameter 1.5 km long mixed ground tunnel and
    450 m long culverts in Hong Kong, SAR
  • Stormwater transfer for up to 40 m3/s

HONG KONG
?
47
Kai Tak Storm Water Transfer Tunnel Client
Drainage Services Department
  • BV's roles include
  • Design
  • Construction supervision

HONG KONG
?
48
Wan Chai East and North Point Sewerage Project
Client Drainage Services Department
  • Upgrade of existing trunk sewerage system in a
    very dense urban area in Hong Kong, SAR
  • 225 mm to 1.2 m diameter 14 km long gravity sewer
    depths ranging from 1.5 m to 6 m, approximately 1
    km by tunneling method and 2.5 km by trenchless
    rehabilitation method

HONG KONG
?
49
Wan Chai East and North Point Sewerage Project
Client Drainage Services Department
  • Use of innovative trenchless technology reduced
    the size of construction site areas
  • Major infrastructure improvements with minimal
    disruption to the public while significantly
    decreasing some existing environmental pollution
    problems

HONG KONG
?
50
Wan Chai East and North Point Sewerage Project
Client Drainage Services Department
  • BV's roles include
  • Preliminary and detailed design
  • Construction supervision

HONG KONG
?
51
Drainage Master Plans Client Drainage Services
Department
  • Yuen Long, Kam Tin, Ngau Tai Mei and Tin Shui Wai
    DMP Study
  • Upgrade options to prevent flooding from the
    secondary and local drainage systems feeding the
    large main drainage nullahs
  • Database / GIS system development to form part of
    an Asset Management System for the Drainage
    Services Department
  • Implementation of a pilot Real Time Flow
    Monitoring System that measures river flow and
    depth at twelve locations
  • Velocity was measured using Time of Flight
    technology

HONG KONG
?
52
Drainage Master Plans Client Drainage Services
Department
  • DMP Study in Sha Tin Tai Po
  • Large WSD facilities such as Jubilee Reservoir,
    Lower Shing Mun Reservoir and the Plover Cove and
    High Island water transfer tunnel systems
  • Investigations of river and open channel systems
    as well as the urban piped stormwater drainage
    systems in the new towns
  • Data collection included flow, topographical and
    CCTV systems, while the analysis was carried out
    using MIKE 11 and HydroWorks computer models
  • Improvement options to remove hydraulic
    weaknesses in the system were tested on the
    models, and the preferred option was taken to the
    preliminary design stage
  • Development of an Asset Management System (AMS)
    which began in the Yuen Long and Kam Tin DMP

HONG KONG
?
53
Drainage Master Plans Client Drainage Services
Department
  • DMP Study in Tuen Mun Sham Tseng
  • Upgrade of the secondary and local drainage
    systems to the required standard
  • The DMP was supported by an AMS, specially
    adapted for use in the Tuen Mun and Sham Tseng
    area

HONG KONG
?
54
Drainage Master Plans Client Drainage Services
Department
  • DMP Study in Sai Kung, East Kowloon and Southern
    Lantau
  • Study areas ranged from the typical rural Country
    Park areas of Sai Kung and Southern Lantau to the
    dense commercial, industrial and residential
    areas of East Kowloon
  • The rivers in the study were modelled by MIKE 11
    and the urban networks were modelled by
    HydroWorks
  • Introduction of Flood Hazard Assessment, Benefit
    Cost Analyses, Flood Risk Mappings and Overland
    Flow
  • Modelling for any proposed major drainage
    improvement schemes

HONG KONG
?
55
Engineering Strategy on Total Water Management
(TWM) for Hong Kong Client Water Supplies
Department
  • To formulate a long-term strategy for balanced
    supply and demand of raw water to support the
    sustainable development in Hong Kong
  • All major options of water demand and supply
    management measures were considered and evaluated
    in terms of (a) quantity (b) cost (c)
    environmental impact and (d) public acceptance

Photo credit Hong Kong Water Supplies Department
HONG KONG
?
56
Engineering Strategy on Total Water Management
(TWM) for Hong Kong Client Water Supplies
Department
  • Recommendation of an integrated strategy for TWM
    programme Water Demand Management Side
  • Enhancing public education on water conservation
  • Promotion of use of water saving device
  • Active water asset management and leakage control
    by the Government
  • Extension of seawater for toilet flushing
  • Water Supply Management Side
  • Protection of water resources
  • Water reclamation such as non-potable use of
    reclaimed water, grey-water reuse and rainwater
    harvesting
  • Development of seawater desalination

Photo credit Hong Kong Water Supplies Department
HONG KONG
?
57
Engineering Strategy on Total Water Management
(TWM) for Hong Kong Client Water Supplies
Department
  • BV's roles include
  • Study
  • Public consultation
  • Develop preliminary implementation plans and
    programmes for proposed TWM measures

Photo credit Hong Kong Water Supplies Department
HONG KONG
?
58
Lake Pleasant Water Treatment Plant Client City
of Phoenix
  • Innovative solutions for North Americas largest
    design-build-operate project
  • 80 mgd of quality, reliable drinking water for
    400,00 households
  • State-of-the-art process system flocculation,
    ozonation, post-filtration granular activated
    carbon contractors and ultra-violet
    disinfection
  • 3D object oriented engineering program

USA
?
59
Lake Pleasant Water Treatment Plant Client City
of Phoenix
  • BV's roles include
  • Design Build Operate (DBO)

USA
?
60
Columbia Heights Membrane Filtration Plant
Client Minneapolis Water Works
  • Largest ultrafiltration plant in the Western
    hemisphere
  • 260 MLD ultrafiltration (UF) membrane water
    treatment system
  • Membrane facility includes new pumping systems,
    chemical dosing systems and all ancillaries
    within the same building and integrated with
    existing coagulation/ flocculation, settling
    systems

USA
?
61
Columbia Heights Membrane Filtration Plant
Client Minneapolis Water Works
  • Architecturally attractive building that blends
    into surroundings
  • 3D technology enables virtual-reality client
    reviews and interactions
  • Training of utility staff on membrane process
  • Won the prestigious Water Project of the Year
    award at the 2006 Global Water Awards for this
    project

PRELIMINARY DESIGN, 3D RENDERING
AS BUILT
USA
?
62
Columbia Heights Membrane Filtration Plant
Client Minneapolis Water Works
  • BV's roles include
  • Design-Bid-Build

USA
?
63
Scottsdale Water Campus Client City of
Scottsdale
  • WPP for discharge to water supply systems
  • 71 MLD AWTP for irrigation and used for
    irrigation with excess injected into on-site dry
    wells for aquifer recharge
  • MF/UF and RO membrane plants
  • Pilot program led to signification improvements
    in energy usage and performance

USA
?
64
Scottsdale Water Campus Client City of
Scottsdale
  • Membrane micro and ultrafiltration, thin film
    reverse osmosis and advanced disinfection
  • Process design for zero discharge 45 MLD
    nitrification / denitrification reclamation
    facility
  • Grand Prize for Excellence in Environmental
    Engineering with the American Academy of
    Environmental Engineers (AAEE)

USA
?
65
Scottsdale Water Campus Client City of
Scottsdale
  • BV's roles include
  • Detailed design, inclusive of pilot plant trials

USA
?
Write a Comment
User Comments (0)
About PowerShow.com