Title: Building Capacity in RE Sector
1Building Capacity in RE Sector
- 19th-Apr-2006
- South Asia Conference on Renewable Energy 2006
2Structure for the discussion
- Rationale for building capacity
- Potential and factors impacting Renewable Energy
- Framework for promoting RE
- Renewable Purchase Standards
- Pricing Issues
- Technical issues
- CDM and other issues
- Way forward and challenges
3Rationale for building capacity through renewable
Electricity for all
Environmental benefits
Energy Security
- Both On Off Grid options
- Diverse presence throughout the country
- Promote local Industries Generate rural
employment - Household electrification by 2012
- 80.3 of villages electrified and 43.52 of
households electrified - 7.28 crore households need to be electrified
- RE offers opportunities to reduce dependency on
oil, coal, and gas - Resources available within the country thereby
no externalities with respect to Access,
Availability cost - To achieve self-sufficiency for energy
requirement - Natural resources (including Coal) to deplete by
2050
- Addresses the threats associated with global
warming - The cost of pollutants is not charged to the
conventional generator - International Energy Prices (UK) Emission costs
turn out to be 6.7 to 14.7 of electricity
price. - World Bank study- Avoided cost for local
emissions natural resource accounting to a tune
of 50 paise/kWh
To meet energy gaps/targets through self
sufficiency and environmental protection
4Evolution of Renewable Energy-Internationally
- Last two decades of learning has shown that
penetration of renewables is - Dependant on the public policy framework
regulations - Dependant on the market models evolved by various
stakeholders - Dependant on the technology robustness
- Various governments have implemented incentive
schemes to stimulate the market to achieve these
targets - Feed-in tariffs
- Simplistic, transparent, popular most
successful - Fiscal incentives and investment subsidies
- Market based mechanism through certificates,
quota, higher returns and reducing technology
cost - Many governments through public policy have fixed
targets/goals - EU 12 by 2010
- India 10 by 2012
- China 10 by 2020
5Potential and status India
- Wind energy
- Well matured industry among the RE sector
- Estimated Gross and Technical potential are
45,000 MW and 13,390 MW respectively - 8 states have more than 1,000 MW gross potential
- Installed capacity as on Sep06 is 4,228 MW
- Small Hydro
- Estimated potential in India is 15,000 MW
- 4,026 sites mapped across the country till now
- Installed capacity as on Dec04 is 2,184 MW
- Biomass Cogen
- Estimated potential of 3500 MW
- Potential exists in sugar producing states (UP,
Mah) - Installed capacity of 574 MW
- Biomass power
- Estimated potential of 16,500 MW
- Potential existing across the states
- Installed capacity of 760 MW (as on Dec 04)
- Waste to energy
- Estimated potential of 6928 MW
- High potential existing in the country as a
result of rapid urbanization - Installed capacity of 151 MW
- Solar photovoltaic
- Potential in India is 20 MW/Km2
- Potential of solar PV generation is among all the
states of the country - Installed capacity of 191 MW
Huge potential still untapped
6Factors impacting RE projects- India
- Regulatory framework
- Regulatory Purchase Standards (RPS)
- Tariff for RE projects
- Wheeling charges and loss allocation
- Policy framework
- 80 accelerated depreciation
- Section 80 IA benefits under IT Act
- Electricity Act, Electricity Policy and NTP
- Subsidy for rural electrification
- Infrastructural and other factors
- Grid connectivity/strengthening
- Intermittency issue (Wind)
- CDM framework
- Carbon credits under the Kyoto Protocol
- Sharing mechanism
7Enabling framework
8Provision for renewables under EA 2003- RPS
- EA 2003 provides a special place for renewables
under Sec. 86(i)e - Mandatory for all SERCs to fix a minimum
percentage of procurement by distribution
companies - Several SERCs have fixed the quantum for
renewables and tariffs for renewable energy
projects as under - Possible factors for determination of
trajectory/quota - Total potential for renewable energy generation
- Quantum of renewable energy being already
generated - Tariff for renewable energy
- Projecting energy requirement
- Impact on the overall power purchase cost of the
Discoms
Methodology for determination of RPS Different
approach followed by different States
9Provision for renewables under EA 2003- RPS
- Factors/issues under consideration
- Common approach/methodology?
- Review of targets according to requirement and
potential - One percentage or Minimum and maximum percentages
to be defined - Whether DISCOMs/State should be free to procure
RE power from other DISCOMs/State in case of
non-availability of RE sources within their own
distribution area/State - Should off-grid RETs be included in the RPS?
10Tariff- Philosophy behind tariff determination
for RE projects
- Cost plus method Section 62 of the EA Act
- Simplistic and most widely accepted
- Most of the SERCs relied on Cost-plus method
- SERCs invited petitions for Capex, Opex,
Performance Financial benchmarks - NTP mandates CERC to issue tariff guidelines for
RE projects - Avoided cost method
- Links the tariff with highest cost of generation
- Competitive bidding
- Section 63 Tariff based on competitive bidding
- NTP also foresees that over the period tariff for
RE should be based on competitive bidding - Factors/issues under consideration
- Could avoided environmental cost be included
while determination of tariff guidelines (may be
through higher returns)? - Is it premature to introduce competitive bidding
for fresh capacity addition in RE projects?
- Different approaches adopted by different States
11Technical Issues
- Scheduling and ABT issues
- Daya-head advance scheduling is not possible
- Nature of demand and supply unknown in case of
wind generation - The utility cannot take the capacity availability
from such plants into consideration - RE projects could be excluded from ABT and
banking can continue - RERC recently allowed banking and exempted RE
projects from ABT - Is it possible to integrate small RE power plants
into the system despatch schedule? - Infrastructural issues Grid strengthening
- Who (the developer or power purchaser or the
transmission/distribution company) should bear
the cost of evacuation facility up to the nearest
receiving sub-station? - What should be the approach for deciding the
technical parameters of interconnection (e.g.
Voltage level, number of circuits,
interconnection point, etc)? - Determination of wheeling and other charges
- Accounting and quantification of TD losses while
determining wheeling charges
12Clean Development Mechanism
- CDM benefits for GHG reduction
- RE projects could get credit for the emission
reduction through the flexibility mechanisms as
per the Kyoto Protocol - Additionality clause would be critical to address
- Critical factors
- Modalities and procedure still evolving
- Some uncertainty whether the CDM benefits should
be taken in to consideration while deciding the
tariff (or using these for financing the
renewable projects) - Since, the emissions reductions would give
additional revenue to the project - However, this revenue would not be uniform across
all the projects, as CDM is a project-based
activity, and the baseline and emission
reductions vary from project to project - From the point of view of criteria of
additionality, all renewable projects may not
qualify as CDM projects. - Need for regulatory clarity as regards CDM
revenues
13Other Issues- Off-grid options
- Innovative decentralised and off-grid models for
achieving rural electrification targets (RGGV
Yojna) - Pricing/economics of off-grid supply Differs
with size, technology and load factor - Clubbing of villages- Cluster approach
- Combined generation and distribution schemes
Option of selling surplus through Grid
connectivity - Estimation of subsidy and institutional mechanism
- Capacity to pay and estimation of subsidy
- Monitoring and implementation (performance based
subsidy) - Panchayats or Rural association/cooperatives
- Financial mechanism Role of banking sector
- Need to link the banking Sector with subsidy
delivery mechanisms - Need to devise bankable schemes which would cover
the subsidy scheme too - Perhaps also a Guarantee Scheme to cover Bank
Finance
Role of Regulator in off-grid generation
14Way forward and challenges
- RPS regulations could be in place in the next one
year - For achieving the national goal of 10 by 2010 or
may be more - Dynamic and should balance the potential and
impact on retail tariffs - The emerging market model of IPP, would see large
sized projects specially in case of wind projects
- CERC guidelines for determination of tariff for
RE projects - Would be critical for building capacity in RE
sector - Exemption from competitive bidding?
- Clarity regarding technical issues (including
ABT) and sharing of CDM benefits - Achieving RE targets through implementation of
RVVN yojna in true spirit - In case of Off-grid options the role of the
Regulator requires clarity - Challenge is planning, monitoring, financing,
implementation and institutional issues
(including in disbursement of subsidy)
15Thank You
Contact Details Mobile 09820197791 www.crisil.co
m