Title: Midwest Research Institute Overview
1Midwest Research Institute
Solutions through science and technology
NCHRP Project 15-26 Passing Sight Distance
Criteria April 5, 2005
2Project Objectives
- Evaluate the design and operational criteria for
determining minimum PSD - Modify the existing criteria or develop new
criteria
3Project Scope
- PSD Criteria for Geometric Design
- AASHTO Green Book
- PSD Criteria for Marking of Passing and
No-Passing Zones - MUTCD
4Project Tasks
- Task 1 Review current PSD criteria and models
- COMPLETE
- Task 2 Review literature and research in
progress - COMPLETE
- Task 3 Identify factors that potentially
contribute to PSD requirements - COMPLETE
5Project Tasks
- Task 4 Critique PSD criteria and develop work
plan - COMPLETE
- Task 5 Prepare interim report
- COMPLETE AFTER PANEL DISCUSSIONS
6Project Tasks
- Task 6 Execute approved work plan
- WILL BEGIN WHEN AUTHORIZED
- Task 7 Prepare new or modified PSD criteria
- WILL FOLLOW TASK 6
7Project Tasks
- Task 8 Prepare final report
- WILL FOLLOW TASKS 6 7
- Task 9 Prepare and deliver final presentations
- WLL FOLLOW TASK 8
8Project Schedule
- Planned Start Date for Phase II
- 2/1/05
- Actual Start Date for Phase II
- 4/6/05 ?
- Approximately two months behind schedule
9Project Schedule
- Submit Draft Final Report
- 2/28/06
- Submit Revised Final Report
- 5/31/06
10Outline of Presentation
- Review of Current PSD Criteria
- Section 2 of interim report
- Assessment of Current PSD Criteria and
Alternative Models - Sections 3 and 4 of the interim report
11Outline of Presentation
- Potential Work Plans for Execution in Phase II
- Section 5 of interim report
- Priorities and Budget Allocations for Phase II
- Section 6 of the interim report
12PSD Design Criteria
- AASHTO Green Book
- PSD d1 d2 d3 d4
- d1 P-R time plus initial acceleration
- d2 distance traveled in left lane
- d3 clearance distance
- d4 distance traveled by opposing vehicle
2/3 d2
13PSD Design Criteria
- ASSUMPTIONS
- Passed vehicle travels at uniform speed
- Passing vehicle reduces speed and trails the
passed vehicle as it enters the passing section
(delayed pass)
14PSD Design Criteria
- Passing driver requires a short period to
perceive the passing section and begin to
accelerate - d1 maneuver time 3.6 to 4.5 sec (older field
data) - d1 acceleration rate 1.38 to 1.51 mph/sec
- (2 to 2.2 ft/sec2)
15PSD Design Criteria
- Passing is accomplished under
- delayed start
- hurried return in the face of opposing traffic
16PSD Design Criteria
- Left-lane distance (d2)
- average speed of passing vehicle during left-lane
occupancy exceeds speed of passed vehicle by 10
mph - at low speeds, passing vehicle above design
speed, passed vehicle below design speed - at speeds of 55 mph or more, both vehicles below
design speed - left-lane occupancy time 9.3 to 7.3 sec,
depending on speed (older field data)
17PSD Design Criteria
- Clearance distance (d3)
- 100 to 300 ft, depending upon speed
- Opposing vehicle distance (d4)
- d4 d2 would allow for completion of passing
maneuver without need to abort - d4 2/3 d2 will require abort in some cases
18PSD Design Criteria
- CRITIQUE
- AASHTO model is extremely conservative
- If model were d1 d2 d3 d2, passing driver
would know that no abort is required even before
beginning to pass - If model d1 d2 d3 2/3 d2, an abort is
potentially required only very early in the
maneuver
19PSD Design Criteria
- Inclusion of P-R and initial acceleration
distance (d1) is very conservative - passing maneuver could be aborted easily and
safely if opposing vehicle appears during d1 - an opposing vehicle that appears during d1 is a
long way from the passing vehicle
20PSD Design Criteria
- Ending section of adequate PSD when PSD falls
below d1 d2 d3 2/3 d2 is extremely
conservative - at the end of the section of adequate PSD, a
passing driver has almost enough sight distance
to start a pass and complete it without the need
to abort - passes can be started safety beyond this point,
if the passing driver can abort the maneuver, if
an opposing vehicle appears
21PSD Design Criteria
- Assumption of passed vehicle speed substantially
less than design speed, particularly for design
speeds of 55 mph or more, is not conservative - Assumption of constant speed differential
between passing and passed vehicles, independent
of design speed is questionable
22PSD Marking Criteria
- MUTCD
- presents warrants for no-passing zones
- passing zones merely happen where no-passing
zones are not warranted - where the distance between successive no-passing
zones is less than 400 ft, no-passing markings
should connect the zones
23PSD Marking Criteria
- There is no quantitative model for the MUTCD
criteria - MUTCD criteria were first developed in a 1940
AASHO policy
24PSD Marking Criteria
- MUTCD/1940 AASHO ASSUMPTIONS
- no P-R time needed for pass initiation because
passing driver can abort the maneuver if an
opposing vehicle appears - speed of passing vehicle is equal to 85th
percentile speed or posted or statutory speed
limit
25PSD Marking Criteria
- speed differential between passing and passed
vehicle ranges from 10 to 25 mph, with higher
speed differentials at higher speeds - speed of opposing is 5 to 15 mph less than speed
of passing vehicle, with higher speed
differentials at higher speeds - compromise between PSD values for delayed and
flying passes
26PSD Marking Criteria
- CRITIQUE
- Speed of passing vehicle equal to 85th percentile
speed or speed limit is conservative - many passing vehicles may travel faster
27PSD Marking Criteria
- Speed differential between passing and passed
vehicles that increases with increasing speed is
not conservative - it seems more likely that speed differential
would decrease as the speed of the passed vehicle
increases
28PSD Marking Criteria
- Speed of opposing vehicle less than 85th
percentile speed or speed limit seems unrealistic - Consideration of flying passes is not
conservative - Minimum 400-ft passing zones are not compatible
with delayed passes on high-speed highways
29Comparison of PSD Criteria
30Comparison of PSD Criteria
31Comparison of PSD Criteria
- AASHTO Criteria
- Driver eye height 3.50 ft
- Target height 3.50 ft (reduced from 4.25 ft in
2001) - MUTCD Criteria
- Driver eye height 3.50 ft
- Target height 3.50 ft
32International PSD Criteria
- PSD Design Criteria _at_ 100 km/h
- Australia (more than US at beginning of PSD, less
than US at end of PSD) - Austria (about the same as the US)
- Britain (less than US at beginning of PSD, much
less at end of PSD) - Canada (about the same as the US)
- Germany (slightly less than the US)
- Greece (slightly less than the US)
- South Africa (about the same as the US)
33International PSD Criteria
- PSD Marking Criteria _at_ 100 km/h
- Australia (slightly less than the US)
- Britain (less than the US)
- Canada (more than the US)
- South Africa (about the same as the US)
34Safety Performance for Passing Maneuvers
- HSIS study (1994) found that
- passing-related accidents constitute 2 of total
non-intersection accidents on rural two-lane
highways - passing-related accidents are more severe than
non-passing related accidents
35Safety Performance for Passing Maneuvers
- Fatal and serious injury accidents
- 13.9 of passing-related accidents
- 9.4 of total accidents
- Passing-related accidents are estimated to
constitute 3 of total fatal and serious injury
accidents on rural two-lane highways
36Safety Performance for Passing Maneuvers
- FARS 2003 data
- 13,000 fatal accidents/year at non-intersection
locations on rural two-lane highways - if 3 are passing-related accidents, there are
390 fatal passing-related accident per year - Not all passing-related accidents involve limited
PSD
37Safety Performance for Passing Maneuvers
- COLLISION TYPES FOR PASSING-RELATED ACCIDENTS
- Single-vehicle ROR 30
- Sideswipe, same direction 25
- Sideswipe, opp direction 7
- Rear-end 17
- Head-on 7
- Other/unknown 15
38Safety Performance for Passing Maneuvers
- Safety record of passing-related accidents is
generally good - It is unlikely that safety performance of rural
two-lane highways can be modified significantly
by changing PSD criteria - Potential cost-effectiveness of changes to PSD
criteria need be investigated
39PSD Criteria in Relation to the Good Safety
Record of Passing Maneuvers
- PSD design criteria are conservative
- PSD values used in marking criteria are more
appropriate than they seem - Short 400-ft passing zones may not be often used
for high-speed passes - Most drivers may be conservative in making
passing judgments - A buffer area is present downstream of every
passing zone
40Conceptual Presentation of the Changes in Sight
Distance Needed to Complete or Abort a Passing
Maneuver as the Passing Maneuver Progresses
AASHTO
d1 d2 d3 2/3 d2
MUTCD
41Critical Position in the Passing Maneuver
- Models based on the critical position assume that
drivers may abort the passing maneuver until the
critical position is reached
42Critical Position in the Passing Maneuver
- Critical position concept
- any passing driver who has not yet reached the
critical position must have sufficient PSD to
abort the maneuver - any passing driver who has passed the critical
position must have sufficient PSD to complete the
maneuver - any passing driver at the critical position must
have sufficient PSD to complete or abort the
maneuver
43Critical Position in the Passing Maneuver
- Two models based on the critical position provide
PSD values similar to the MUTCD - Glennon (1988)
- Hassan et al. (1996)
44Critical Position in the Passing Maneuver
- First recognized by VanValkenburg and Michael
(1971) - they called it the point of no return
- they visually identified the critical position as
occurring when the vehicles are approximately
abreast (rear bumper of passed vehicle opposite
middle of passing vehicle) - field measurements of distance traveled by the
passing vehicle from the abreast position to the
completion of the pass
45Critical Position in the Passing Maneuver
- Weaver and Glennon (1972)
- defined the critical position as the point at
which the time required to complete the maneuver
is equal to the time required to abort the
maneuver - proposed a PSD model that did not incorporate
this definition - stated that critical position occurs when
vehicles are approximately abreast
46Critical Position in the Passing Maneuver
- Harwood and Glennon (1976)
- defined the critical position as the point at
which the sight distance required to complete the
maneuver is equal to the sight distance required
to abort the maneuver - proposed a PSD model that did not incorporate
this definition
47Critical Position in the Passing Maneuver
- Lieberman (1982)
- used critical position concept in modeling PSD
- defined needed PSD as d7 PSDc
- d7 is distance to from the start of the pass to
the critical position - formulated a model to determine the relative
position of the passing and passed vehicles at
the critical position (?c) - model for ?c appears incomplete
48Critical Position in the Passing Maneuver
- Saito (1984)
- postulated that there are two possible locations
of the critical position in a passing maneuver - head-to-tail position (head of passing vehicle
opposite tail of passed vehicle) - abreast position (passing vehicle alongside
passed vehicle) - model inputs are not fully stated
49Critical Position in the Passing Maneuver
- Glennon (1988)
- formulated PSD model based on equivalent sight
distance to complete and abort a passing maneuver
from the critical position - included an explicit model to calculate the
relative positions of the passing and passed
vehicles at the critical position (?c)
50Critical Position in the Passing Maneuver
- Glennon (1988)
- included terms for the lengths of the passing and
passed vehicles - incorporated speed differential between passing
and passed vehicles that decreases as speed
increases - deceleration rate in abort maneuver 8
ft/sec2 (as opposed to 11 ft/sec2 in SSD)
51Critical Position in the Passing Maneuver
52Critical Position in the Passing Maneuver
- Harwood and Glennon (1989)
- used Glennon model with some changes in input
data from Glennon (1988) - passenger car length, 19 ft rather than 16 ft
- truck length 75 ft
- smaller speed differential for truck as the
passing vehicle - lower deceleration rate in aborting a pass, 5
ft/sec2 for a truck, as opposed to 8 ft/sec2 for
a passenger car
53Critical Position in the Passing Maneuver
54Critical Position in the Passing Maneuver
- Rilett at al. (1989)
- recommended a minimum speed for passing abort
maneuver Vd 2m - inclusion of a minimum speed substantially
lengthens PSD values - Good et al. (1991) stated that it is unreasonable
to expect that, in the face of an opposing
vehicle, the passing driver would decelerated to
Vd 2m and then continue at constant speed
55Critical Position in the Passing Maneuver
- Rilett at al. (1989)
- recommended headway after pass abort greater than
the 1 sec used by Glennon - 1 sec headway appears appropriate for passenger
cars - headway greater than 1 sec appears needed for
trucks
56Critical Position in the Passing Maneuver
- Hassan et al. (1996)
- recommended two modifications to the Glennon
model - recommended incorporation of P-R time for pass
abort decision (but this may already be part of
the Glennon model) - recommended providing PSD for pass completion
where critical position occurs with passing
vehicle ahead of passed vehicle (positive value
of ?c)
57Critical Position in the Passing Maneuver
58Critical Position in the Passing Maneuver
59Critical Position in the Passing Maneuver
60Critical Position in the Passing Maneuver
61Buffer Area Downstream of Passing Zones
62Buffer Area Downstream of Passing Zones
- Buffer area results from short zone marking
concept - passes must legally be completed prior to end of
zone - drivers can complete passes safely even if in
critical position at end of zone - used in 46 of the 50 states
63PSD Marking Criteria
- HSIS study suggests no major safety problems
associated with PSD marking criteria - Glennon and Hassan et al. models suggest that
MUTCD criteria may be about right, but for the
wrong reason - Differences between Glennon and Hassan et al.
models need to be resolved
64PSD Marking Criteria
- Cost of changing PSD criteria would be
substantial remeasuring PSD for all two-lane
roads with centerlines - Cost-effectiveness of potential changes in
marking criteria needs to be resolved -
65Potential Approach to PSD Marking Criteria
- IF SUPPORTED BY PHASE II RESULTS
- Retain MUTCD criteria
- Offer a better engineering rationale for the
MUTCD criteria based on the Glennon model, the
Hassan et al. model, or some variation of these
models
66Potential Approach to PSD Marking Criteria
- Consider need to change 400-ft minimum passing
zone length
67Short Passing Zones
- Cant accommodate delayed passes on high-speed
highways - May accommodate some flying passes
- May accommodate passing very slow-moving vehicles
tractor on the road - May not contribute much to LOS
- Do drivers use short zones legally? safely?
68Short Passing Zones
- Jones (1970)
- Texas roadways with 70-mph speed limits
- field studies at three passing zones with lengths
of 400, 640, and 880 ft - comparative data for passing zones with lengths
of 1,640 and 2,600 ft
69Short Passing Zones
- Jones (1970)
- defined passing opportunity as
- trailing vehicle within 4 car lengths (80 ft)
- appeared to be awaiting a change to pass
- average of 125 passing opportunities observed per
zone
70Short Passing Zones
71PSD Design Criteria
- What is the rationale for use of longer PSD
values in design than in marking? - Does the good safety record of passing maneuvers
indicate that current marking criteria are
sufficient for safety? - Does the use of longer PSD values in design than
in marking enhance safety? - Should the design process explicitly consider the
passing and no-passing zones that will be marked
on the completed highway?
72Potential Alternative Approaches to PSD Marking
Criteria
- 1 Retain current AASHTO Green Book criteria
- 2 Use the same PSD criteria for design as for
marking - 3 Use PSD criteria for design with a defined
relationship to PSD criteria for marking - PSD X PSDc
73Potential Alternative Approaches to PSD Marking
Criteria
- 4 - Use the same PSD criteria for design as for
marking, but count only passing sections with
specified minimum length - 5 Use longer value of PSD to define beginning
of passing section and shorter PSD to define end
of passing section
74Other Issues
75PSD for Trucks
76PSD for Trucks
77PSD for Trucks
- Glennon model may need longer headway after abort
for truck as passing vehicle - Truck can pass PC on any vertical curve where PC
can pass a truck reevaluate in light of changed
object heights
78PSD for Trucks
- PC passing truck or truck passing PC may not be a
logical design or marking scenario - would eliminate some current passing zones and
shorten others - would prohibit some passes of PCs that are safe
and are currently legal - would reduce LOS
- might encourage illegal passes
- no indication of safety benefits
79Older Drivers
- Reduced P-R time
- Reduced visual acuity
- Reduced ability to judge distances and speeds
- Less likely to travel at high speeds
- Less likely to pass
- Less aggressive
- More likely to drive passed vehicle than passing
vehicle
80PSD for Older Drivers
- FHWA Highway Design Handbook for Older Drivers
recommended using Green Book PSDs instead of
MUTCD PSDs - NCHRP Project 20-7(118) recommended caution in
implementing this Handbook recommendation
81PSD for Older Drivers
- Use of longer PSD in marking would eliminate some
current passing zones and shorten others - Older drivers would still probably be more
reluctant than younger drivers to pass - Handbook recommendation did not consider the
safety cushion provided by the buffer area
82Key Considerations in Changing PSD Criteria
- Safety considerations (effect on accident
frequency and severity) - Traffic operational considerations (effect on
level of service) - Economic considerations (benefits to compensate
for increased costs) on both existing and new
highways - Rationality and consistency of PSD criteria
(understanding and acceptance by engineers)
83Potential Phase II Work Plans
- A Benefit-cost analysis
- B Identify and analyze of passing- related
accidents - C Review accident data for field sites
- D Safety of passing maneuvers completed beyond
the end of a passing zone
84Potential Phase II Work Plans
- E Safety and operations of short passing zones
- F Field data to quantify parameters of revised
PSD models - G Application of PSD criteria to actual
terrain - H Traffic operational effects of alternative
PSD criteria
85Potential Phase II Work Plans
- I Comparison of PSD and SSD criteria
- J Guidance on determination of percentage of
roadway length with PSD
86A Benefit-Cost Analysis for Changing PSD
Marking Criteria
- Objective
- determine whether safety benefits could possibly
justify cost of remeasuring PSD - need to quantify
- cost per mile of remeasuring PSD
- number of miles of two-lane roads with marked
centerlines - number of accidents equivalent to cost of
remeasuring - number of accidents available for reduction
87BIdentification and Analysis of Passing-Related
Accidents
- Objective Conduct further evaluation of
passing-related accidents - Identify passing-related accidents in manner
similar to HSIS study - Obtain more complete severity data
- Estimate available PSD at accident sites
- Determine portion of passing zone (or no-passing
zone) where accidents occur
88BIdentification and Analysis of Passing-Related
Accidents
- Investigate involvement of trucks
- Investigate involvement of older drivers in
passing, passed, and opposing vehicles - Determine weather and pavement conditions under
which passing-related accidents occur
89CReview of Accident Data for Field Sites
- Objective
- Assure that field sites used in Work Plans D and
F do not have adverse accident experience - Determine accident experience for field sites in
Work Plan E
90DSafety of Maneuvers Completed Beyond the End of
a Passing Zone
- Objective Determine the extent and consequences
of pass completions beyond the end of a passing
zone - Sites to be used
- passing zone length 1,000 to 2,500 ft
- frequent passing activity
- no-passing zone for at least 2,000 ft downstream
of passing zone
91DSafety of Maneuvers Completed Beyond the End of
a Passing Zone
- Data to be collected
- percent of maneuvers completed in marked passing
and no-passing zones - relative positions of passing and passed vehicles
at the end of the passing zone - location of passing vehicles return to normal
lane - sight distance at return to normal lane
- traffic conflicts or severity of return maneuver
- Video recording and manual observation
92ESafety and Operations of Short Passing Zones
- Objectives Determine whether short passing
zones - create safety problems
- contribute substantially to LOS
- Sites to be used
- passing zone length 400 to 800 ft
- Data to be collected
- similar to Work Plan D
93FQuantify Parameters of Revised PSD Models
- Objective Quantify parameters of alternative
models - speed differential between passing and passed
vehicles - distance traveled by the passing vehicle from the
beginning of passing zone to the critical
position - deceleration rate use in aborting a passing
maneuver
94FQuantify Parameters of Revised PSD Models
- Data collection approach
- Video recording
- Manual observation
- Traffic classifiers or laser guns for speed
measurement
95GApplication of Revised PSD Criteria to Actual
Terrain
- Objective Investigate effects of changing PSD
design and marking criteria - Obtain plan and profile data for actual terrain
- as-built plans
- Washington HSIS data
96GApplication of Revised PSD Criteria to Actual
Terrain
- How will revised PSD criteria change
- percentage of roadway length that meets design
PSD criteria - percentage of roadway length in marked passing
zones - lengths of passing zones
- PSD available within passing zones
- Relative contributions of PSD criteria and
terrain
97GApplication of Revised PSD Criteria to Actual
Terrain
- Interviews with experienced designers
- choice of target percentage of roadway length
that meets design PSD criteria - application of design criteria
98HTraffic Operational Effects of Alternative PSD
Criteria
- Objective How will revised PSD design and
marking criteria affect the level of service on
two-lane highways? - Tool TWOPAS traffic operational computer
simulation model
99I Comparison of PSD and SSD Criteria
- Compare PSD values used in design and marking to
SSD values used in design - Compare resulting vertical curve lengths in light
of - sight distance criteria
- assumed driver eye height
- assumed object height
100J Guidance on Percentage of Roadway Length with
Design PSD
- Provide guidance or recommendations on average
frequency of passing opportunities that should be
provided on two-lane highways - dependent on traffic volumes
- dependent on vehicle mix
- needs to implement desired LOS for functional
class and terrain
101J Guidance on Percentage of Roadway Length with
Design PSD
- Added passing lanes along the road may reduce the
need for PSD to maintain LOS between passing lanes
102Project Budget
- Phase I 64,066
- Phase II 235,934
- TOTAL 300,000
103Phase I Budget
- Budgeted expenditures 64,066
- Actual expenditures (est.) 61,000
- Unexpended funds (est.) 3,066
104Allocation of Phase II Budget
105Cost Estimates for Task 7 Work Plans
- A Benefit-cost analysis of PSD 10,000
- marking revisions
- B Identification and analysis of 100,000
- passing-related accidents
- C Review of accident data for 5,000
- field study sites
- D Safety of passing maneuvers 30,000
- completed beyond the end
- of the passing zone
106Cost Estimates for Task 7 Work Plans
- E Safety and operations of 30,000
- short passing zones
- F Field data collection to quantify 50,000
- PSD models
- G Application of revised PSD 10,000
- to actual terrain
- H Traffic operational effects 15,000
- of alternative PSD criteria
107Cost Estimates for Task 7 Work Plans
- I Comparison of PSD and SSD 5,000
criteria - J Guidance on determining the 10,000
- percentage of roadway length
- with adequate PSD
- TOTAL 265,000
108Cost Estimates for Task 7 Work Plans
- Estimated cost for all 10 work plans
265,000 - Available funds for Task 7
- 181,000
- Difference
- 84,000
109Potential Modifications
- Eliminate Work Plan B entirely
- saves 100,000
- frees up 16,000 for field work
- Scale back Work Plan B to 16,000
- existing data bases only
- no videolog review
- no hard-copy accident report review