A Comparison of Capital Budgeting Techniques - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

A Comparison of Capital Budgeting Techniques

Description:

Average Accounting Return. AAR is the ratio of the Average Net ... Take the project if AAR is greater than some target ratio set by accountants. Disadvantages ... – PowerPoint PPT presentation

Number of Views:120
Avg rating:3.0/5.0
Slides: 37
Provided by: calinv
Category:

less

Transcript and Presenter's Notes

Title: A Comparison of Capital Budgeting Techniques


1
A Comparison of Capital Budgeting Techniques
  • With definitions and exemplifications

2
Capital budgeting
  • Cost/benefit analysis
  • Estimating the value of investment projects
  • Making informed choices

3
Capital Budgeting Techniques
  • A collection of methods allowing the manager to
    choose among a variety of investment projects.

4
Problem
  • Value, rank and select investment projects

5
Exemplification
6
Clarifications
  • Required rate a fair discount rate given each
    projects risk

7
Methods
  • Average Accounting Return
  • Payback
  • Discounted payback
  • Internal Rate of Return
  • Modified Internal Rate of Return
  • Net Present Value
  • Profitability Index

8
Average Accounting Return
  • AAR is the ratio of the Average Net Income to the
    Average Book Value.
  • Decision rule
  • Take the project if AAR is greater than some
    target ratio set by accountants.
  • Disadvantages
  • It has too many flaws, don't ever use it.

9
Payback period
  • PB is the time it takes to recover the initial
    cost of the investment

10
Payback period
  • Decision rule
  • Take the project with the shortest payback period
  • Disadvantages
  • Ignores time value of money
  • Ignores risk
  • Ignores cash inflows beyond the cutoff point

11
Payback period
  • In our example
  • project C 2.49 years
  • project B 3.41 years
  • project A 3.83 years
  • All three projects are viable

12
Discounted payback period
  • DPB is the time it takes to recover the initial
    cost of the investment
  • PB uses nominal CF
  • DPB uses discounted CF

13
Discounted payback period
  • Decision rule
  • Take the project with the shortest discounted
    payback period.
  • Disadvantages
  • DPB ignores cash inflows beyond the cutoff point

14
Discounted payback period
  • project A 4.94 years
  • project B 3.76 years
  • project C would need more than 5 years
  • Only A and B are viable

15
Internal Rate of Return
  • IRR is the discount rate that makes the present
    value of the project equal to its initial cost.

16
Internal Rate of Return
  • Decision rule
  • Take the project If the IRR exceeds the required
    rate of return
  • Disadvantages
  • Reinvestment rate assumption is unrealistic
  • Multiple IRR
  • IRR cannot rank mutually exclusive projects

17
Internal Rate of Return Calculation
  • Set Initial cost PV(project)?
  • 5,045 400/(1r) 1,250/(1r)2 900/(r)3
    3,000/(1r)4 1,000/(1r)5
  • r 8.

18
Internal Rate of Return
  • IRR(A) 8
  • IRR(B) 8
  • IRR(C) 5.
  • Only A and B are viable

19
Modified Internal Rate of Return
  • MIRR is the discount rate that makes the future
    value of the project equal to its initial cost.
  • MIRR requires a reinvestment rate.

20
Modified Internal Rate of Return
  • Decision rule
  • Take the project if MIRR is larger than the
    required rate.
  • Disadvantages
  • MIRR cannot rank mutually exclusive projects.

21
MIRR calculation
  • Project A
  • Set FV(at 5) 5,045(1MIRR)5
  • MIRR 7

22
MIRR calculation
  • MIRR(A) 7
  • MIRR(B) 6.54
  • MIRR(C) 5
  • Only A and B are viable

23
NPV
  • Net Present Value is the difference between the
    present value of a project and its initial cost
  • NPV PV - Initial cost

24
NPV
  • Decision rule
  • If NPV is positive, take the project.
  • Disadvantages
  • Very complex analysis, too many variables to
    forecast

25
NPVCorollary
  • Required Rate IRR ? NPV 0
  • and vice-versa.

26
NPV calculation
  • project A
  • PV 400/(1.077) 1,250/(1.077)2
    900/(1.077)3 3,000/(1.077)4 1,000/(1.077)5
  • PV5,089.36
  • NPV Present value - Initial Cost
  • NPV 5,089.36 - 5,045 44.36

27
NPV calculation
  • NPV(A) 44.36
  • NPV(B) 64.17
  • NPV(C) -148.81
  • Only A and B are viable
  • B is better because it adds more value

28
The Profitability Index
  • The profitability index is the ratio of project
    PV to initial cost
  • PI PV/Initial cost

29
The Profitability Index
  • Decision rule
  • Take the project if PI gt 1
  • Disadvantages
  • PI cannot rank mutually exclusive projects.

30
PI calculation
  • Project A
  • PI(A) PV(A)/Initial cost 5,089.36/5,045
  • PI(A) 1.0088

31
PI Calculation
  • PI(A) 1.0088
  • PI(B) 1.131
  • PI(C) 0.9846
  • Only A and B are viable

32
Why cant PI rank the projects?Exemplification
33
Why cant PI rank the projects?
  • PI(x) lt PI(y)?
  • but
  • NPV(x) gt NPV(y)?

34
Answer
  • NPV rules.
  • Always.

35
Important side note
  • In project valuation, measures of absolute wealth
    are more appropriate than measures of relative
    efficiency.

36
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com