UTILITIES DEPARTMENT
  • INFLOW INFILTRATION
  • REDUCTION
  • PROGRAM

2
What Is I I
  • Inflow
  • Inflow is clean water intrusion into the sanitary
    sewer from the surface and illegal connections
  • Downspout Connections Foundation Drain
    Connections Catch Basin/Yard Drain Connections
    Manhole Lids, etc.
  • Infiltration
  • Infiltration is clean water intrusion into the
    sanitary sewer from underground
  • Broken Sewer Pipe Separated Joints Leaking
    Manholes

3
REASONS
  • 1 Reduce amount of clean water going to the
    Wastewater Plant
  • 2 Extend the life of the Collection System
  • 3 Compliance with OEPA Directives
  • 4 Reduce/Eliminate Sewer Flooding into homes

4
Sanitary Sewer Flood Events
  • None in 2007

5
2007PROJECT STATUS
  • Foraker Ave 372,848
  • Sewer Rehab Project replacing sewer main under
    railroad tracks lining remaining sewer main
    sealing manholes Completed
  • Front Street 79,000
  • Sewer Rehab Project rehab sewer main in alley
    between Wapakoneta Ave and Main Ave replacement
    and lining work - Completed

6
SCHEDULED WORK
  • 2008
  • Garfield/Bennett Phase I - 125,000 Issue II
    Funds
  • Cul-De-Sac to first Alley to south
  • Washington Street - 75,000 II Funds
  • Main to Miami
  • 2009
  • Garfield/Bennett Phase II - 135,000 Issue II
    Funds
  • Alley to Bennett
  • SW Interceptor through Joslin Farm - 180,000
    Sewer Funds and II Funds
  • Clean, televise, and pressure grouting
  • Ohio Ave - 25,000 Sewer Funds
  • Water St to Big Four Bridge clean televise
    sewer

7
SCHEDULED WORK
  • 2010
  • Chestnut Ave - 144,000 Issue II Funds
  • From Fair Rd south 700 ft
  • Doorley Place - 44,000 II Funds
  • Main to Miami
  • Parkwood (Main to Wapak. Ave) 35,000 II Funds
  • Main to Wapak
  • 2011 - 2012
  • 2011 Ohio Ave Sewer Replacement Phase I
    180,000 Issue II Funds and Sewer Funds
  • 2012 Ohio Ave Sewer Replacement Phase II -
    300,000 Issue II Funds and Sewer Funds

8
EXAMPLE OF BROKEN SEWER LATERAL
9
EXAMPLE OF DOWNSPOUT CONNECTION
10
FUTURE
  • Federal CMOM Program (Capacity Management,
    Operation and Maintenance)
  • Continue Funding Inflow Infiltration Reduction
    Program 75,000/Yr
  • Continue Funding Total Sewer Replacement Projects
    with Issue II Funds
  • Purchase of New Sewer Televising Equipment with
    Grouting Capabilities Grouting sanitary sewers
    in-house with City crews

11
Groundwater Intrusion Into Joints
12
SEWER GROUTING