The participation of the - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

The participation of the

Description:

J Waghorn Secondees and Secondment Allowances, UKAEA. J Dalton S/T Orders and ... allowances, fees and superannuation contributions together with other charges ... – PowerPoint PPT presentation

Number of Views:54
Avg rating:3.0/5.0
Slides: 42
Provided by: ITER58
Category:

less

Transcript and Presenter's Notes

Title: The participation of the


1
The participation of the EURATOM VR
Association to the EFDA JET Experimental Campaigns
2
Outline
List of People Involved in the Preparation/Reporti
ng
Overview of the EURATOM and EFDA Structure and
how the JET Experimental Campaigns fit into it.
Review of the current (C20 C26)
Orders Notifications Task Agreement Secondmen
t
Summary of C27
Statistics for C20 C27
JET future and Concluding remarks
3
The Persons Involved
J Drake Head of RU, KTH
A Torslind JET Administrative Contact Person, VR
P Karlsson VR
J Waghorn Secondees and Secondment Allowances,
UKAEA
J Dalton S/T Orders and ISAFs, UKAEA
M Cecconello JET Scientific Contact Person, UU
M Laxåback CSU at EFDA JET E Asp
4
VR Contact Persons in JET Task Forces
S1 J Weiland S2 T Hellsten M J Weiland H T
Hellsten D G Ericsson E M Rubel DT G Ericsson T J
Weiland FT M Rubel
5
7th EURATOM Framework Programme (2007 to 2011)
Activities in the area of fusion energy within
the FP7 are carried out through several
different contracts/agreements, among them
Contracts of Association Bilateral contracts
between research organizations or bodies in all
the Member States and the Community.
European Fusion Development Agreement between
all the Associates (signatories of a contract of
association) to fully exploit the JET Facilities
and possibly other fusion devices and coordinate
the research activities.
Other multi-lateral agreements, such as the
Mobility Agreement, that promote the
collaboration and mobility of researchers between
the different research organization and
facilities.
6
Contract of Association EURATOM VR (until 2013)
The subject of the contract is the carrying out
by the Contracting Parties of activities within
the thematic area "fusion energy research" of the
FP7 as detailed in the Annual Work Programme
of the Association.
The present contract expires on 31 December 2013.
A Steering Committee shall be set up by the
Contracting Parties and shall ensure on their
behalf the proper performance of the present
Contract
The Contracting Parties assign the execution
of the research activities to which the present
Contract relates to the Research Unit.
7
Financial provisions
The contract of association specifies also the
financial provisions
(20) includes expenditure for
notification(s) relating to S/T work in support
of the exploitation of the JET Facilities
Baseline support
with an additional rate supplementing baseline
support and not exceeding a final rate of 40
for expenditure on specific co-operative
projects, which have been recommended for or
have been awarded priority status by the CCE-FU
Priority support
a rate not exceeding 40 for
at a rate of 40, Orders relating to Science and
Technology work carried out on the JET Facilities
at a rate of 100, contributions to support
actions identified in the Euratom and EFDA Work
Programmes
8
JET S/T Tasks (EFDA Art.6.3)
After approval of the EFDA Work Programme by the
EFDA Steering Committee and conclusion of Task
Agreements between the EFDA Leaders and the
Associates concerned the contracting Parties will
agree upon (i) the work to be performed by the
Associate (ii) the scientific reports (iii) the
time schedule (iv) a forecast of the actual
manpower required subdivided into
categories (v) an estimate of the total cost of
the work subdivided into various projects.
9
Staff of the Associate
Staff in the Research Unit working on the
activities defined in the Annual Work Programme
may be charged against the Contract at rates to
cover their salaries, allowances, fees and
superannuation contributions together with other
charges arising from the social legislation
currently in force.
Annual Salary Cost
Monthly Salary (sek) x 12 x 1.05 x LKB
The exchange rate to be used is the EU official
one.
Estimate done for C27.
10
Notifications
Notifications relating to S/T work in support of
the exploitation of the JET facilities under
Article 6.3 of the EFDA shall specify (i) the
work to be performed by the Associate (ii) the
scientific reports (iii) the time schedule (iv)
a forecast of the actual manpower required
subdivided into categories (v) an estimate of
the total cost of the work subdivided into
various projects.
11
European Fusion Development Agreement (until
2013)
The present Agreement is concluded to provide a
framework for coordinating activities among the
Contracting Parties for research, and for the
development and exploitation of common tools or
facilities/devices within the thematic area of
research "fusion energy" of the Euratom 7th
Framework Program.
The collective use of the JET facilities is
provided for by the JET Implementing Agreement
(JlA) and by the JET Operation Contract (JOC).
Each year, the Annual Work Programme setting
out the detailed activities to be carried out
during the following year in implementation of
this agreement shall be approved by the EFDA
Steering Committee.
12
EFDA Associate Leader for JET
The EFDA Associate Leader for JET shall be
responsible to the EFDA Steering Committee for
the collective use of the JET facilities under
the JET Implementing Agreement. In particular
he/she shall, in agreement with the EFDA Leader,
prepare the JET component of the EFDA Work
Programme and ensure that the JET activities
performed under the JET Implementing Agreement
constitutes a coherent set of activities within
the EFDA Work Programme.
The scientific program of JET under EFDA is
organized in the form of Task Forces with their
Leaders being responsible for the preparation
and execution of the campaigns the analysis and
the publication of the results co-ordinate the
staff seconded from all the European laboratories
13
EFDA Research Activities
The research activities shall be carried out
through
Task Agreements
shall form part of the Work Programme of the
participating Associations and be agreed between
the EFDA Leader and the participating
Associations.
Implementing Agreements for cooperative
activities based on the use of a facility or
a device. The Implementing Agreements shall be
concluded between the Commission and
the Associates concerned.
Implementing Agreements
Among them there is the collective use of JET
facilities.
14
Collective Use of the JET facilities
The collective use of the JET facilities shall be
described in the EFDA Work Programme. It shall
encompass the performance of the scientific and
technical tasks (S/T Tasks) and the operation of
the JET facilities in support of them.
S/T Tasks include the Experimental Campaigns and
related work and the Enhancements, as defined in
the JET Implementing Agreement (JIA) and
shall be executed by the Associates under the
supervision of the EFDA Associate Leader for JET
Individual S/T Tasks under the Contracts of
Association shall be implemented through
contracts (Orders) concluded between the
Commission and the Associate concerned and
through Notifications by the EFDA Associate
Leader for JET to the Associate(s) concerned.
15
Current EFDA JET Order
Individual Task Descriptions (ITDs) are prepared.
EFDA JET Experimental Campaigns 2008 (C20 to C25)
JW8-O-VR-29 June 2008
Expiry date 30-Sep-09
The draft Order Final Report shall be completed
by 30-Apr09.
The report should comprise the Campaigns C20 to
C25.
JW8-O-VR-29A November 2008
EFDA JET' Experimental Campaigns 2008/2009 (C20
to C27)
Expiry date 31-Dec-09
The draft Order Final Report shall be completed
by 30-Sep-09.
The report should comprise the Campaigns C20 to
C27.
16
Current EFDA JET Notifications
JW8-N-VR-27 July 2008
A total of 52 ppw
Expiry on the 30/09/09
Proposed notification for C27
A total of 100 ppw
17
EFDA JET Task Agreement
General Planning Meeting held 19-23 November 2007
Experimental Campaigns 2008 Date 22 February
2008
JW8-TA-EXP-04
focused strongly on exploitation,
including the high-level commissioning, extension
of the operating space to high power and full
scientific exploitation of the ITER-like ICRH
antenna, the qualification of integrated
operating scenarios for ITER, the preparation for
the installation of the ITER-like wall in JET
. The Experimental Campaigns of 2008 will
concentrate on 1. High level commissioning
and full scientific exploitation of new systems
and issues that could impact on the design of
ITER components 2. Qualification of integrated
operating scenarios for ITER and 3. Physics
issues essential to the efficient exploitation of
ITER.
Official Amendment not available yet.
18
C20 C27 a timeline.
CALL TO ASSOCIATIONS FOR PARTICIPATION IN
CAMPAIGNS C20-C25 OF THE JET 2008 WORKPROGRAMME
22 Oct 07
Participation in the General Task Force
Meeting for planning the JET 2008 Experimental
Campaigns
14 Dec 07
CALL TO ASSOCIATIONS FOR PROPOSALS TO PARTICIPATE
IN CAMPAIGNS C20-C25 OF THE JET 2008 WORKPROGRAMME
Proposal for S/T Orders and Notifications
29 Oct 08
CALL TO ASSOCIATIONS FOR PROPOSALS TO PARTICIPATE
IN CAMPAIGN C26 OF THE JET 2009 WORKPROGRAMME
Proposal for S/T Orders only
19
28 Nov 08
CALL TO ASSOCIATIONS FOR PARTICIPATION IN
CAMPAIGN C27 OF THE JET 2009 WORKPROGRAMME
General Planning Meeting for planning the JET C27
Experimental Campaign
13 Feb 09
EXTENSION OF CAMPAIGN C26 OF THE JET 2009
WP Extended to 7 April 2009
30 Mar 09
CALL TO ASSOCIATIONS FOR PROPOSALS TO PARTICIPATE
IN CAMPAIGN C27 OF THE JET 2009 WORKROGRAMME
20
Planning of the JET Experimental Campaigns
C20 C25
(175 S/T operation days)
Restart 30/11/07 19/03/08 HLC 25/03/08 04/04/08
C20a 07/04/08 09/05/08 C20b 12/05/08 06/06/08
C21 09/06/08 18/07/08 C22 21/07/08
29/08/08 C23 01/09/07 03/10/08 C24 06/10/08
07/11/08 C25 10/11/08 19/12/08
C26
12/01/09 06/03/09 07/04/09
(61 S/T operation days)
C27
HLC 22/06/09 03/07/09 C27a 06/07/09
14/08/09 C27b 02/09/09 02/10/09
(62 S/T operation days)
21
Secondment and Assignment of Staff
Staff participating in S/T Work in Campaign or
Enhancements oriented activities under EFDA may
be seconded for continuous periods shorter than
four weeks (i.e. 20 working days) if i)
ii) the cumulative period of secondment is at
least four weeks in the calendar year iii) the
Sending Associate agrees to take charge of all
the extra travel costs (compared with one round
trip) iv) no short stay shall be less than 5
working days.
A Secondment Agreement Plan shall be applicable
in case several staff members shall be seconded
by an Associate for Campaign related activities
for short stays
The plan shall state the total number of seconded
staff and the total number of calendar days they
are to be seconded to the JET Facilities
22
Secondment Agreement Plan (JET)
10 April 2008
Association EURATOM - VR no 21
18 staff for the total number of 1100
calendar days they are to be seconded to the JET
Facilities (C20 C25)
Association EURATOM - VR no 21 Amendment 1
21 January 2009
18 staff with specific competences for the total
number of 1082 calendar days (C20 C26)
Association EURATOM - VR no 21 Amendment 2
1 April 2009
18 staff with specific competences for the total
number of 1128 calendar days (C20 C26)
Up to date and correct!
23
Individual Secondment Agreement Form - ISAF
Changes to the ISAFs should be channel through
the Scientific Contact Person.
Monday to Friday
Working Days
Calendar Days
Monday to Sunday
Travel Days
Days of travel covered by the secondment (per
ISAF) 11 for air travel 2.5 2.5 for car travel
Secondment Days
Calendar Days Travel Days
ISAF
start/end dates possible only for working days
Secondment allowance
EURATOM VR Secondee Based on the Secondment Days
24
Changes to the ISAFs channel through the SCP!
25
C27 Experimental Campaign Overview (from
Romanelli)
17-June
6-July
14-Sep
28-Sep
14-Aug
2-Sep
2-Oct
6 weeks D (11 ERFA 37 13 cont.)
He (14 4 cont.)
H (14 4 cont.)
2 weeks Maint. Comm (NBI ? He)
D (82)
HLC (12 ERFA 1 HFPI)
NBI ? He
NBI ? H
NBI ? D
High power NBI
Restart HLC (incl. PRFA) HFPI 14 shifts 6
contingency ERFA during restart/HLC 12 shifts C
27 Planned Commissioning with plasma of
ERFA 11 shifts ( 12 in HLC) Use of new
hardware (EFCCDMV) 11 shifts Pellets 4
shifts (1 in HLC) Isotope studies L-H,
pedestal, exchange 19 shifts Last chance
disruption studies 2 shifts ILW
preparation 8 shifts RF heating scenarios
for ITER 14 shifts Transport and rotation
studies 9 shifts Fuel retention 2
shifts RF conditioning for ITER 3
shifts 83 shifts 23 contingency
26
Some Statistics
Total of 1128 secondment days
VR Participation to C20 C26
SD/P 28
SD/P 50
SD/P 91
SD/P 55
27
Total of 449 secondment days
Proposed VR Participation to C27
UU
KTH
CTH
28
Total of 1557 secondment days
Proposed VR Participation to C20-C27
LU
UU
KTH
CTH
29
Total of 1128 secondment days
VR Participation to C20 C26 per TF
TF E
TF H
TF S2
TF T
TF D
30
VR Participation to C20 C26 per Person
Secondment Days
31
VR Participation to C20 C27 per Competencies
(23 out of 58, 40 )
32
Summary of the Proposal to Participation to C27
Proposal submitted on the 21st of April
Expected answer from EFDA JET by the 8th of May
18 Persons proposed for a total of 449 secondment
days
Competencies as SC up to 4.
33

A look at the JET future and concluding remarks
34
Plan of JET exploitation beyond 2010 (Romanelli)
Experiments
  • Restart possibility for TTE-like operation

Increasing heating power, pulse length and
density range
Start 2011
Start 2012
Start 2013
Start 2014
End 2014
3w
18w
9w
12m
4w
18w
3w
9w
3w
9w
3w
9w
3w
9w
cvcv
17w
9w
TechnicalRestart
PlasmaRestart
Up to 18m
  • Commissioning of existing and new systems
  • Includes full technical commissioning of NB
    upgrade
  • Intervention
  • Intervention

Specific HLC
  • PNB reaching 35MW in safe operating modes
  • Experiments dedicated to PWI studies prior to
    intervention to remove sample tiles
  • Full power ILW-compatible scenarios
  • Dedicated ITER scenario studies
  • Possible melt-layer studies
  • Final tech preps for DT
  • DT restart (3y after start of DT technical
    preparations)
  • Plasma preparations for DT
  • DT operation
  • RF/LH dominated
  • Commissioning consistent with specific scientific
    aims
  • Start of PWI studies

35
Task Force Structure for 2011 (Romanelli)
JET TF structure in 2011 will need to be
revised EFDA SC has approved the formation of
two Task Forces for exploiting JET during Restart
with plasma, High Level Commissioning and
Experimental Campaigns in 2011 Task Force E1
will be responsible for expanding operational
domain it will have a Task Force Leader and two
Deputies with specific responsibilities. Task
Force E2 will be responsible for exploring
operational domain it will have a Task Force
Leader and two Deputies with specific
responsibilities. It may be appropriate to
establish additional Task Forces to address
specific scientific issues at a later stage.
36
JET Beyond EP2 (Romanelli)
  • Early 2008 the EFDA SC recognises the scientific
    need for full exploitation of the EP2
    enhancements and tritium operation and requests
    the EFDA Associate Leader for JET to prepare, and
    present to the EFDA Steering Committee a plan for
    the full exploitation of the EP2 enhancements and
    tritium operation. It requests the Commission to
    investigate the possibility of making adequate
    resources available within the fusion programme
    budget.
  • Facility Review Panel
  • JET needs to operate until 2015/15 at least and
    would benefit from an early installation of an
    ECRH system. Depending on the JT60-SA schedule
    JET operation for a few further years should be
    foreseen.
  • Launch of 2 feasibility studies approved by the
    EFDA SC
  • ECRH
  • Resonant Magnetic Perturbation coils
  • New divertor, LH PAM, 2nd ICRH antenna and beam
    reorientation will be evaluated internally.

37
Some questions
Is there a need for a common repository of all
the information (Contracts, Agreements, ISAFs and
so on) for the VR Association ?
who can access to what ?
set up a web page ? On which server ? Resources ?
who should be responsible for this ?
How to report the scientific output of the
participation to JET Campaigns ?
JET Pinboard only ?
List of presentation given at the different TF
Meetings ?
Number of sessions as SC/SL/DC ?
38
EURATOM
ASSOCIATION
Orders
Notifications Task Agreements
EURATOM
UKAEA
JOC
EURATOM
ASSOCIATES
JIA
EURATOM
SECONDEE
Secondment
39
(No Transcript)
40
(No Transcript)
41
Enhanced Radial Field Amplifier (ERFA) used for
plasma vertical stabilisation on fast timescales
Write a Comment
User Comments (0)
About PowerShow.com