1
DEIMOS
  • Report to the SSC
  • March 14, 2000

2
Outline
  • Thumbnail sketch of status
  • Schedule
  • Budget (not on web version)
  • Detailed status and progress
  • Concerns
  • Other Issues

3
Thumbnail sketch of status
  • Optical Assembly complete optical testing of the
    camera planned to start this week
  • Cold testing with an engineering mosaic of MIT/LL
    chips in the dewar has started.
  • Science Array with 8 epi CCDs starts assembly
    this week
  • We have fabricated all major parts of the optical
    train with the exception of grating sliders 34
    sliders 34 will complete in April
  • Major systems are being integrated onto
    structure starting testing (slitmask system,
    grating system, filter wheel.)
  • Calibration and FC light sources are last systems
    needing design

4
Scheduled Milestones
5
Critical Path
6
Camera
7
Dewar System
8
Schedule Analysis By Critical Path
  • Dewar Slip 7 weeks
  • Contingency makeup (prorated) -2 weeks
  • SPIE makeup -1 week
  • Net slip 4 weeks
  • Critical Path inefficiency (raw) 20.5w/13.5w
    1.51
  • Corrected for contingency (18.6) 1.27

9
Schedule Analysis by Tasks Completed
  • Number of task-days scheduled, 10/11/99 to
    3/14/99 (A) 1383 days
  • Number of task-days actually completed (B)
    828 days
  • Inefficiency factor (A/B) 1.67
  • Corrected for contingency (divide by 1.186)
    1.41

10
Predicted Pre-Ship Review Date
  • Optimistic current slip does not increase- 4
    weeks 12/4/00
  • Conservative critical path inefficiency factor
  • remains constant (1.51)
    15 weeks 4/4/01

11
Status and Progress
  • Camera
  • Dewar/Detectors
  • Grating System
  • Filter Wheel
  • Structure
  • Slit Mask
  • Collimator
  • Tent mirror
  • Shutter
  • Calibration System
  • FC System
  • TV System
  • Software
  • Site
  • Web site
  • Shipping

12
Camera
  • Camera is assembled
  • Optical testing is about to start

13
Camera
14
Camera Cell 1
15
Camera, cells 12
16
Camera, cells 1,2,3
17
Camera Body 3
18
Element 5 Fracture
19
Camera, cell 4
20
Camera
Spacers, filter wheel, and shutter
21
Camera
Element 9 and dewar window
22
Camera Test Stand
23
ORA Respace
  • Adjustments to multiplet spacings were less than
    0.012 in
  • Respace design has rms image diameters 0.18 -0.20
    arcsec. This is 20 better than error budget to
    this point (not all errors yet included)

24
Camera
  • Testing plan starts next week
  • Image size and aberrations
  • Interferometric tests

25
Detectors
  • Eight science-grade epi CCDs are in hand for
    first science mosaic.
  • Recent setbacks on Lot 14 high-rho CCDs have
    occurred supply is unclear

26
Dewar
  • Cooling test with dead mosaic completed
    successfully
  • Warm test with engineering mosaic completed
    successfully
  • Science mosaic with 8 epi CCDs is under
    construction
  • Cold test with engineering mosaic is starting
  • Read out noise is low
  • Electrical crosstalk is low
  • Recent leak will cause a slip of 1 week
  • Two CCDs do not work cause unknown
  • RTV window seal outgasses water onto CCDs seal
    will have to be replaced

27
Dewar
Dewar on test stand with EE mosaic
28
Dewar
CCD controller attached to dewar
29
Grating System
  • Two of 4 sliders complete and installed
  • Testing of grating slide drive in progress
  • Sliders 34 complete by end of March
  • Grating installation fixture nearly complete

30
Grating System
Sliders 12
31
Grating system
Drive System
32
Filter Wheel
  • Fabricated
  • Assembly is in progress

33
Structure
  • Rotation tests indicate that drive hardware is
    extremely good
  • Drive servo system and software are planned to
    begin in May

34
Collimator
  • Cell complete and fitted into DEIMOS structure
  • Collimator is aluminized

35
Tent Mirror
  • Attachment points have been installed on mirror
  • Piezo hardware exists
  • Mirror to be aluminized in April
  • Dummy mirror to be installed in DEIMOS for
    testing in May

36
Tent Mirror
37
Shutter
  • Assembled and tested
  • Plan to change out air cylinders to ones similar
    to ESI

38
Calibration System
  • Currently in design phase
  • System will be very simple with bulbs and
    reflectors in the forward part of instrument and
    power supplies in electronics lockers
  • Ne, Ar, He, HgCd, possibly Kr and Xe, plus quartz
    continuum lamp

39
FC Light System
  • Have fibers and plan to start testing in April
  • Requires integration with the slit mask holder
    design (April)
  • Light source is two Cu-Ar lamps (one for backup)

40
TV System
  • Design complete
  • Very similar to system used in ESI
  • Fabrication scheduled to begin in April, complete
    in May

41
Software
  • Continuing delays due to ESI and HIRES exposure
    meter
  • Kibrick working on signal chain, not software
  • Mosaic descrambing software is written
  • RTD image display tool will probably be DS9 NOAO
    RTD not needed

42
Site
  • Bi-weekly participation in team meetings
  • Channels for rails in right Naysmith platform are
    complete
  • Modifications have not yet been made to cable
    wrap on telescope (Kyle and Mark have drawings)
  • Table of contents for a Lick/CARA interface
    document have been developed

43
Web Site
  • Comprehensive design is in progress inspired by
    ESI
  • Test Data section is now archiving all test
    results in standard format

44
(No Transcript)
45
Shipping
  • Main structure can be shipped by Matson will
    require custom crate.
  • Will likely need separate marine container for
    fixtures and other large heavy parts not attached
    to main structure for shipping
  • We will air-freight optics and most electronics,
    as did ESI

46
Concerns
  • Ice condensation in dewar new mount for dewar
    window
  • Acquisition of hi-rho devices number and
    schedule
  • Stages and mechanisms needing extensive rework
  • Flexure
  • Software scheduling
  • Testing personnel
  • Ghost reflections
  • purchase of new blank for element 5