Title: BioWire Progress Report Week Eight
1BioWire Progress ReportWeek Eight
- Orr Ashenberg, Patrick Bradley, Connie Cheng,
Kang-Xing Jin, Danny Popper, Sasha Rush
TODO 4 I14033/E0434 images 6 Sequencing numbers
(X parts) 10 Images for AHL-gtreceiver
experiment 12 finish up atc sender/receiver
experiment Add atc r40/e434 experiment
2Last Week
- Determined that our YFP reporter (used in the
receiver) is defective - Re-ordered a working YFP and began reconstruction
using the new YFP - Received the receiver test construct from
BioBricks, conducted experiments - AHL to receiver
- aTc to senderreceiver
- Sequencing results
- Photolithography
3Oh YFP
- YFP Biobrick Parts
- E0030 (YFP, no degradation tags)
- E0032 (YFP, LVA)
- E0034 (YFP, AAV)
- We had been using E0032, since we want
degradation of YFP for temporal analysis - Turns out that E0032 does not glow when added to
a constitutive promoter (degradation tag too
strong?) - Reporter control experiments
4100x Phase
100x YFP Filter
I14033 E0430 Const. P(cat) YFP
I14033 E0434 Const. P(cat) YFP AAV
I14033 E0432 Const. P(cat) YFP LVA
5(Re)Building the Circuits
- Now rebuilding circuits with E0030 (YFP), E0034
(YFP AAV), and mCherry (LVA and LVA-) - Thanks Biosketch
- Lux and Las components with YFP, YFP AAV, and
mCherry LVA- will be ligated together today - Also building mCherry sender reporter
Receiver OutputPropagation Component (J06008)
6Sequencing
- Sent in completed Lux parts for sequencing
- Total of X parts (29 primers) sent in
- 4 readable sequences
- 3 okay, 1 missing an RBS
- Parts are being rebuilt with new reporters
anyways - All others returned more than 1 sequence (a lot
of background)
7Experiments
- AHL to receiver
- Is AHL working?
- Is the AHL receiver promoter working?
- aTc to senderreceiver
- Is the sender (AHL producer) working?
- Is aTc induction working (the tetR promoter)?
- Is luxI producing AHL?
- Solid media
8Experiments AHL to receiver
- AHL receiver part (I13272/J06000)
- Produces luxR constitutively
- Has EYFP after promoter lux pR, which is
upregulated by the luxR-AHL complex
9Experiments AHL to receiver
- Add AHL to receiver cells do they glow?
- Protocol
- Grow up overnight backdilute to OD600 0.1
- Add AHL solution to cells at appropriate
concentrations - Negative controls 0 AHL, AHL cells w/o
receiver - Positive controls none
- Incubate in 37C shaker for 40min
- Image
10Experiments AHL to receiver
- Add AHL to receiver cells do they glow?
- Yes!
11Experiments aTc to sender/receiver
- AHL sender part (J06001)
- Produces luxI, which in turn produces AHL, in
response to aTC
12Experiments aTc to sender/receiver
- Add aTc to sender cells, then mix with receiver
cells do receiver cells glow? - Protocol
- Grow up overnight backdilute sender to OD600
0.01, receiver to OD600 0.1 - Add aTc to sender cells and incubate in 37C
shaker for 3 hours - Add different concentrations (same volume) of
sender cells to fixed volumes of receiver cells - Incubate mixture in 37C shaker for 40min
13Photolithography
- Made a 5 µm master and two 150-350 µm masters
(more on that later). - Made PDMS negatives.
- Learned how to plasma oxiginate PDMS in order to
reduce air bubble distortion. - Made agarose stamps from the PDMS.
14Photolithography
- Issues in the cleanroom
- Non-uniformity in photoresist
- caused wafer to bake onto the mask
- changed our soft-bake and development times
- and caused variations in feature height between
150 µm and 350 µm. (We were aiming for 150 µm
features.) - Also, the agarose stamps we made had some minor
issues (levelling, user error).
15Photolithography
- With current PDMS negatives, will remake agarose
stamps to start stamping cells. - Will remake 150 µm master to increase uniformity.
- Will begin process of making 1mm master.
16This Week
- Building parts
- Test constructs for Lux, finish Las parts.
- Move finished Lux parts onto DH5alpha cells.
- Part validation/sequencing.
- Experiments
- Test receiver constructs
- Reconstruct and test LuxI sender (unexpected
fluorescence) - Photolithography
- Go into cleanroom to make 150?m and 1000?m master.
17Updated Schedule
- Week 1 (6/6) Project Choice and Design
- Week 2 (6/13) Got parts and set up tests
- Week 3 (6/20) Began building test constructs,
finished sender - Week 4 (6/27) Finish receiver, receiver
w/repressor CAD a mask - Week 5 (7/4) Continued building parts, received
mask - Week 6 (7/11) Finished Lux, Tested senders, made
PDMS molds - Week 7 (7/18) More experiments, finish Las, make
first master/PDMS/stamp, eating pizza
courtesy of Alain - Week 8 (7/25) More experiments, Meeting Their
Master - Week 9 (8/1)
- Week 10 (8/8)
- Week 11 (8/15)
- Week 12 (8/22)
- Week 13 (8/29)