Title: Machine Tolerances in Cleaning Insertions
1Machine Tolerances in Cleaning Insertions
J. Wenninger AB-OP SPS Beam Operation
- Tolerances
- Orbit stabilization
- Beam optics
2A world of collimators
- Operation without collimators (All OUT) is only
possible at the LHC with very low intensity and
around injection - One pilot-ish bunch (5 109 p) ? no quench
expected - One nominal bunch (1011 p) ? no damage, but
risk of quench - At high energy use of collimators will be
mandatory, but coarse settings are acceptable for
low intensity and during the initial phases. - This is of course independent of the collimator
design issue.
3Getting started at injection
- The available machine aperture at injection is
8.5s with a margin of - ? 4 mm closed orbit 20 b-beat mom. offset
mech. tolerances - Protection devices for injection will be set ? 7s
- ? primary collimators will be set to 5.5-6s
-
- Both absolute orbit excursions and b-beat must be
under control, or else the collimator settings of
5-6 s must be tightened even more !
4Constraints on machine changes
- The following machines changes (wrt a reference
situation) lead to a 50 degradation of the
nominal betatron cleaning efficiency - 8 b-beating
- 0.6 s orbit shift
- 50 mrad angle change
Collimation inefficiency versus position error
- Tolerances are cleary tigher if there is a
combined change of b-beat, orbit as is often
the case ! - ? may have to take a factor 2 off from those
numbers !
Note the simulations were made for an older
version (2002) of the cleaning system !
5Orbit tolerances for the LHC
- With time demands for orbit stabilization have
poped up everywhere around the LHC. A more or
less exhaustive list - Cleaning section IR3/7 lt ? 0.3 s 70
mm - TCDQ absorber in IR6 lt ? 0.5 s 200 mm
- Q-meter and transverse damper in IR4 ?
200 mm - Injection points IR2/IR8 200 mm
- Injection protection devices IR2/IR8 lt ? 0.5
s ? 500 mm (?) - Stabilization for collisions
- TOTEM experiment IR5 20 mm (!!!)
- Protection global orbit 500 mm
rms - e-cloud() global orbit lt1000 mm
rms ?
7 TeV
Note the expected BPM systematic errors
intensity (pilot ? nominal bunch) ?100
mm bunch length changes (injection flat top)
?100 mm ?
Presently studied at the SPS
() not formally expressed but to be expected
from SPS experience
6Expected orbit drifts
Phase Total drift / rms Time
scale Comment Injection
?2 mm 15 min Decay Start
ramp ?2 mm 20 sec Snapback Ramp
few mm 20 min SPS/LEP
experience Squeeze 2-20 mm few
min Depends on orbit
quality in insertions Collisions few
mm hours LEP orbit
- Some drifts (ramp, squeeze) are probably
sufficiently reproducible to use feed-forward
from one fill to the next for the bulk part. - Most drifts become critical on time scales gt 1-10
seconds.
7Ground motion at LEP
- f ? 0.1 Hz no problem expected
Average 1s
LEP rms orbit drifts in 1998 for 390 fills,
normalized to b1 m
- f gt 0.1 Hz
- Amplitudes ? O(few mm)
- ? should be OK
? If the LHC moves like LEP we are safe.
Note The large time constants of the orbit
corrector power converter (10-200 s) and the
available voltage limit useful orbit corrections
to f ? 1 Hz (at 7 TeV) !
8Orbit feedback overview
A global real-time orbit stabilization local
refinements is considered to satisfy all the
demands
- Sampling rate 5 25 Hz (design is 10 Hz) for
corrections at up to 0.2-1 Hz. - Upper limit is 50 Hz due to power converter
controls. - Data transmission from ? 70 front-end computers
(1000 readings/plane) to central feedback over
switched Gigabit Ethernet (LHC technical
network). - Central processing on Linux systems
(multi-processor) with (almost) hard real-time
capabilities. A total processing delay lt 40 ms is
feasible. - Fan-out of corrections to PC front-end systems
(500 correctors/plane). - If there are performance problems ? local loops
in cleaning insertions !
9b-beating
- With only 8 b-beating change tolerated, a good
correction of the optics is required at all
stages - Ramp (decay snapback seem OK).
- Squeeze
- Dynamic squeeze in collisions for LHCb.
- Fancy knobies (arrrgh !!).
-
- There are lots of distributed sources of b-beat
- Spool-piece corrector alignement.
- Orbit in sextupoles.
- Quadrupole calibrations (nominal accuracy 2 x
10-4 ? ?5 b-beat change during squeeze, Ok but
near the limit). -
- ? work ahead !
10b-beating measurement
- Careful optics adjustments will have to be made
- K-modulation available (as far as I know !) in
cleaning IRs - - control of hysteresis effects ? At 7 TeV the
quadrupoles will not be far from saturation. - - good measurements require continuous / PLL Q
measurements. Not expected to be available
before some months after startup. - Kicks / AC dipoles combined with multi-turn BPM
data - - beware of oscillation amplitude limits !
- This issue clearly deserves a closer look.
11On the road to a nominal LHC
- Beam cleaning offers new challenges for retired
LEP operation cowboys - lots of tuning ahead at least as far as the
tight tolerance allow it ! - The relatively tight orbit control in the
cleaning sections is manageable. - Tight optics control is much more tricky.
Deserves further studies and lots of work on
the beam !