Machine Tolerances in Cleaning Insertions - PowerPoint PPT Presentation

About This Presentation
Title:

Machine Tolerances in Cleaning Insertions

Description:

Operation without collimators ( All OUT') is only possible at the LHC with very ... Fancy knobies (arrrgh !!). There are lot's of distributed sources of b-beat ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 12
Provided by: jwe51
Category:

less

Transcript and Presenter's Notes

Title: Machine Tolerances in Cleaning Insertions


1
Machine Tolerances in Cleaning Insertions
J. Wenninger AB-OP SPS Beam Operation
  • Tolerances
  • Orbit stabilization
  • Beam optics

2
A world of collimators
  • Operation without collimators (All OUT) is only
    possible at the LHC with very low intensity and
    around injection
  • One pilot-ish bunch (5 109 p) ? no quench
    expected
  • One nominal bunch (1011 p) ? no damage, but
    risk of quench
  • At high energy use of collimators will be
    mandatory, but coarse settings are acceptable for
    low intensity and during the initial phases.
  • This is of course independent of the collimator
    design issue.

3
Getting started at injection
  • The available machine aperture at injection is
    8.5s with a margin of
  • ? 4 mm closed orbit 20 b-beat mom. offset
    mech. tolerances
  • Protection devices for injection will be set ? 7s
  • ? primary collimators will be set to 5.5-6s
  • Both absolute orbit excursions and b-beat must be
    under control, or else the collimator settings of
    5-6 s must be tightened even more !

4
Constraints on machine changes
  • The following machines changes (wrt a reference
    situation) lead to a 50 degradation of the
    nominal betatron cleaning efficiency
  • 8 b-beating
  • 0.6 s orbit shift
  • 50 mrad angle change

Collimation inefficiency versus position error
  • Tolerances are cleary tigher if there is a
    combined change of b-beat, orbit as is often
    the case !
  • ? may have to take a factor 2 off from those
    numbers !

Note the simulations were made for an older
version (2002) of the cleaning system !
5
Orbit tolerances for the LHC
  • With time demands for orbit stabilization have
    poped up everywhere around the LHC. A more or
    less exhaustive list
  • Cleaning section IR3/7 lt ? 0.3 s 70
    mm
  • TCDQ absorber in IR6 lt ? 0.5 s 200 mm
  • Q-meter and transverse damper in IR4 ?
    200 mm
  • Injection points IR2/IR8 200 mm
  • Injection protection devices IR2/IR8 lt ? 0.5
    s ? 500 mm (?)
  • Stabilization for collisions
  • TOTEM experiment IR5 20 mm (!!!)
  • Protection global orbit 500 mm
    rms
  • e-cloud() global orbit lt1000 mm
    rms ?

7 TeV
Note the expected BPM systematic errors
intensity (pilot ? nominal bunch) ?100
mm bunch length changes (injection flat top)
?100 mm ?
Presently studied at the SPS
() not formally expressed but to be expected
from SPS experience
6
Expected orbit drifts
Phase Total drift / rms Time
scale Comment Injection
?2 mm 15 min Decay Start
ramp ?2 mm 20 sec Snapback Ramp
few mm 20 min SPS/LEP
experience Squeeze 2-20 mm few
min Depends on orbit
quality in insertions Collisions few
mm hours LEP orbit
  • Some drifts (ramp, squeeze) are probably
    sufficiently reproducible to use feed-forward
    from one fill to the next for the bulk part.
  • Most drifts become critical on time scales gt 1-10
    seconds.

7
Ground motion at LEP
  • f ? 0.1 Hz no problem expected

Average 1s
LEP rms orbit drifts in 1998 for 390 fills,
normalized to b1 m
  • f gt 0.1 Hz
  • Amplitudes ? O(few mm)
  • ? should be OK

? If the LHC moves like LEP we are safe.
Note The large time constants of the orbit
corrector power converter (10-200 s) and the
available voltage limit useful orbit corrections
to f ? 1 Hz (at 7 TeV) !
8
Orbit feedback overview
A global real-time orbit stabilization local
refinements is considered to satisfy all the
demands
  • Sampling rate 5 25 Hz (design is 10 Hz) for
    corrections at up to 0.2-1 Hz.
  • Upper limit is 50 Hz due to power converter
    controls.
  • Data transmission from ? 70 front-end computers
    (1000 readings/plane) to central feedback over
    switched Gigabit Ethernet (LHC technical
    network).
  • Central processing on Linux systems
    (multi-processor) with (almost) hard real-time
    capabilities. A total processing delay lt 40 ms is
    feasible.
  • Fan-out of corrections to PC front-end systems
    (500 correctors/plane).
  • If there are performance problems ? local loops
    in cleaning insertions !

9
b-beating
  • With only 8 b-beating change tolerated, a good
    correction of the optics is required at all
    stages
  • Ramp (decay snapback seem OK).
  • Squeeze
  • Dynamic squeeze in collisions for LHCb.
  • Fancy knobies (arrrgh !!).
  • There are lots of distributed sources of b-beat
  • Spool-piece corrector alignement.
  • Orbit in sextupoles.
  • Quadrupole calibrations (nominal accuracy 2 x
    10-4 ? ?5 b-beat change during squeeze, Ok but
    near the limit).
  • ? work ahead !

10
b-beating measurement
  • Careful optics adjustments will have to be made
  • K-modulation available (as far as I know !) in
    cleaning IRs
  • - control of hysteresis effects ? At 7 TeV the
    quadrupoles will not be far from saturation.
  • - good measurements require continuous / PLL Q
    measurements. Not expected to be available
    before some months after startup.
  • Kicks / AC dipoles combined with multi-turn BPM
    data
  • - beware of oscillation amplitude limits !
  • This issue clearly deserves a closer look.

11
On the road to a nominal LHC
  • Beam cleaning offers new challenges for retired
    LEP operation cowboys
  • lots of tuning ahead at least as far as the
    tight tolerance allow it !
  • The relatively tight orbit control in the
    cleaning sections is manageable.
  • Tight optics control is much more tricky.
    Deserves further studies and lots of work on
    the beam !
Write a Comment
User Comments (0)
About PowerShow.com