INTO-PLANERISK ASSESMENT
  • DESC QM Conference
  • Lee Oppenheim
  • 18 Nov 2003

2
RISK ASSESSMENT
  • Background
  • DCMC wanted to eliminate the six month mandatory
  • Industry questioned frequency
  • DESC/DCMC/AF worked on guidance
  • Audit list developed first
  • Risk assessment then developed
  • DCMC Homestead was test location
  • DESC/AF approved 1997, DCMA changed

3
RISK ASSESSMENT
  • DESC assumes QA role
  • Re-institutes risk assessment as tested and
    approved
  • Requires QAR to perform audit of facility
  • Risk assessment rates processes
  • Gives overall score
  • Score used to determine frequency of visit

4
RISK ASSESSMENT
  • Process Areas
  • Product
  • Safety
  • Facilities
  • Documentation Records
  • Personnel
  • Operational Consideration

5
RISK ASSESSMENT
  • FACTORS
  • Four items have Inherent, Past and Future ratings
  • Documentation/Records and Personnel have only
    Past and Future

6
RISK ASSESSMENT
  • ISSUE
  • Use of Risk assessment requires manager
    intervention
  • QAR skews to medium risk
  • QM needs to review and make sure assessment being
    used correctly
  • Need to modify assessment when you feel medium is
    misused, redirect QAR

7
RISK ASSESSMENT
  • ISSUE
  • Difficult to produce a low risk facility
  • Is there another way to do risk assessment
  • DESC-AM proposed using
  • Likelihood of Occurrence
  • Consequence of Occurrence
  • Numerical rating and formula
  • ?

8
Risk Assessment
9
RISK ASSESSMENT
  • LIKELIHOOD
  • Numerical rating from near certainty to remote
  • Subjective
  • CONSEQUENCE
  • If goes wrong what will the effect be
  • Numerical rating 1 5 corresponding to complete
    failure to no impact
  • Can we get more specific in order to use

10
(No Transcript)
11
RISK ASSESSMENT
  • Should we look at using likelihood/consequence
    vice inherent/past/future?
  • Are there other issues that need to be addressed
    in the into-plane risk assessment?