WP4 Analogue Electronics - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

WP4 Analogue Electronics

Description:

ALUK Meeting, Glasgow 12th August. WP4 Analogue Electronics. Up-date on Work ... Preliminary Design ... Dave Hoyland, Stuart Aston and Clive Speake ... – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 12
Provided by: spacerese
Category:

less

Transcript and Presenter's Notes

Title: WP4 Analogue Electronics


1
WP4 Analogue Electronics Up-date on Work Plan
Progress C Castelli and D Hoyland
Document ID ALUKGLA0042aAUG03
2
Project Schedule Overview Milestone inputs from
EC2 and RAL WP3 schedule Controls prototype tests
(LASTI) Feb 05 Preliminary Design Review (PDR)
July 05 Noise prototype testing and cavity
tests June 06 to May 07 Production Readiness
Review (PRR) Nov 06 Final Design Review (FDR)
May 07 First Article Assembly Aug 07 IFO1
integration complete Dec 07 IFO 2 3
Integration complete June 08
3
  • WP4 Development approach
  • Early convergence on design concept for OSEMs
  • Freeze interfaces after detailed electronic and
    OSEM design
  • Manufacture in-house engineering model OSEM
    (possible use in controls prototype LASTI test?)
  • In-house build and testing of noise prototype
    OSEMs (269) and control electronics (200)
  • Selection of manufacturer for main productions
  • Final design and manufacturing studies
  • Place contract with industry for electronics and
    OSEMs
  • Contract management, unit level testing and
    delivery

4
GANTT for WP4 OSEM and Control Electronics
Production
5
Slightly late
6
  • Areas of Concern
  • Major concern is that outcome of LASTI tests are
    not compatible with the delivery dates for main
    electronics
  • 1 month separates end of LASTI tests and PRR
  • Need 4-5 months to prepare for industrial
    manufacture i.e. select contractor, finalize
    manufacturing data and prepare for PRR
  • OJEC (Official Journal for European Communities)
    rules for procurement using public sector funds
    for tenders over 160K 6 months
  • Problem for main production where costs 200K
    depending on how much WA is required

7
  • Overview of Progress
  • Coordinated development of OSEM between Glasgow,
    Strathclyde and Birmingham 19
  • Design team at Birmingham Dave Hoyland, Stuart
    Aston and Clive Speake
  • Two approaches being investigated in parallel
  • Imaging system
  • Interferometer concept for position sensing
    (Speake)
  • Vacuum compatibility, reliability and temperature
    stability of components

8
Position Sensing/imaging System (Baseline)
Birmingham exploring design concept based on BIPM
measurements Trade off studies looking at laser
diodes (cost, stability, power etc) and
photodiode characteristics (saturation
limits) Advantage in terms of laser power light
scattering
9
Interferometer readout system
O2
10
  • Interferometer Readout System
  • Cost of system with external optical coupling
  • Not a COTS unit yet so cost is a driver ?
  • Pig-tail coupling to diode (set-up alignment
    sensitivity)
  • DSP fringe counting electronics (real time s/w)
  • Demonstrated 5x10-13 m/?Hz at UCSD (requirement
    is gt10-11m/Hz)
  • Estimates indicate that maximum sensitivity for
    imaging system only just meets the requirement

11
  • Facilities at Birmingham
  • Group awarded 5M infrastructure development
    fund (SRIF)
  • New assembly and test facilities for space
    projects
  • New electronics clean room assembly and
    mechanical manufacturing
  • New design office suites
  • Precision optical facilities and metrology (CMM,
    interferometers, optics benches etc in clean
    stable environments)
Write a Comment
User Comments (0)
About PowerShow.com