Title: SST electrical cable qualification
1SST electrical cable qualification
- Simone Paoletti
- CERN, 11 July 2006
2Routing of the Power in the SST
- PSUs will be placed on balconies in the
experimental cavern (UXC), 10m (direct) distance
from the beams crossing point. From there - 35m of cables will be needed to reach the patch
panel 1 (PP1) - A Cu cable is to be used in this region, in order
to have better performances - 6m of cables will be needed to reach the tracker
internal structures from PP1. - An Al cable is to be used in this region, in
order to keep low the material budget.
Power cables will be used also to route signals
from T and H probes inside the tracker
Cu Cable - COST and PERFORMANCE -
Al Cable - MATERIAL BUDGET -
3short (? 6m) cables
4long (? 30 m) cables
5Quality Control
- All cables are checked upon reception before
being used for the experiment - LIC, PLCC, TIB/TID short cables ? automatic test
setup checking connections, isolation and
capacitance - TEC/TOB short cables ? Lyon box checking
connections and isolation. - Each cable is checked at production by the
connectorising firm - QC checks for PLCC and LIC after connectorisation
were agreed with us. - For the LIC cables additional QC tests are
performed by the cable producing firm, before
connectorisation, as specified in the tender. - Standard qualification tests on all produced
spools - Sampling destructive tests
6The LIC cable
7The LIC cable
- Two versions
- v1 for TIB/TID
- v3 for TEC/TOB
- the connectorisation of he two versions is
compatible (TEC/TOB may use LIC_v1 and
vice-versa)
- All relevant documentation (design, tests,
safety) is on EDMS https//edms.cern.ch/ - First steps of PRR passed
- the LIC cable was approved for safety
- we are allowed to buy the cables
- still missing cable lengths definition inside CMS
cabling database
LIC V1
LIC V3
8(No Transcript)
9(No Transcript)
10LIC QC before connectorisation
- The LIC is produced by Elettronica Conduttori
(Volpiano, TO) - Each production lot is certified by the firm
according to contract and to CERN-required
specifications - IEC 60317-0-1, IEC 60317/51, CEI 20-11, CEI
20-35, IEC 60332-1, 73/23/CEE, 93/68/CEE,
2002/95/CEE, TECH SPEC. LIC V1, LIC V3 - The manufacturer performs the following isolation
tests, on each spool, before cutting to
individual lengths - 3000 Vcc (between twisted pairs)
- 2000 Vcc (twisted versus shield braid)
- 3000 Vcc (twisted versus enamelled)
- 250 Vcc (enamelled vs enamelled)
- 250 Vcc (enamelled vs shield braid)
- The certified working voltages are
- 30 V for the enamelled wires (LV lines)
- 600 V for the twisted pairs (HV, LV senses and
T,H probes)
11Production lot certificate
12(No Transcript)
13Electrical test results
14LIC QC destructive tests
- Additional destructive tests are performed on
each production lot, on a sample basis, in order
to spot possible mechanical problems - These tests are not addressing any weakness
specific of the LIC cable, but were required as a
safety measure, since the LIC cable design is new
(use of enamel wire). - Traction
- 820 N / 60 s
- U bends
- 200 cycles (Rbend 75 mm) 5 cycles (Rbend 20
mm) - Crushing
- 150 kg on 80 mm length
- The electrical properties of the cable samples
are measured after the destructive tests and have
to be good within large safety margins
15Traction test
16Crush test
17Bending test
18Bending radius
- The LIC is certified for Rbend 8cm
- Rule of thumb (average manufacturer) Rbend
10 x ø - The QC procedure was agreed with the manufacturer
in order to allow us to lower Rbend in a few
difficult installation points - Once bent below 8 cm, any further movement of the
cable is strongly discouraged - We have to keep Rbend as large as we can during
the installation - It is a single-pose cable
- the characteristics and costs of movement cables
are different (cost higher by factor 3) - we can re-use this cable a limited number of
times, provided it is adequately handled and
never bent below 8 cm - some bad handlings which can damage the cable
(from my personal experience) - drop from height while fastened at the bottom
- wrong re-winding into drum
19Outer jacket
- The jacket material is ECCOH 3140 LS0H polyolefin
compound - satisfies CERN IS23 safety rules (fire and
radiation resistance) - similar compound (Megolon S-304) used in previous
LIC preproduction - polyolefin compounds used by several
sub-detectors - The jacket is 1mm thick
- adequate to the cable dimensions
- constraints
- occupancy on cable trays
- bending radius
- power consumption
20Connectorisation
- Connectorisation technique for enamel wires
developed - bath in tin/lead at 390C
- initial technical problems due to the constrained
dimensions in PP1 solved - molding technique developed using polyurethane
(Rampfs RAKO-PUR)
insertion key
21Connectorisation schemes
22Tests performed after connectorisation
- Continuity and isolation tests performed at the
firm using a programmable tester machine - SCHAFFNER ELECTROTEST TEST SYSTEM W427
- More refined tests (using the same instrument)
performed at CERN upon cable reception - four point R measurement allows to monitor the
quality of connections - capacitance measurements ensure the correct
twisted pair assignments
23Test performed by firm
24Test performed at CERN
SCHAFFNER ELECTROTEST TEST SYSTEM
W427 ------------------------------------------ P
rogramma di test LIC versione 3 (35 metri) Nome
del file LIC_V3-35mt Data/ora
06/06/2006 15.00.55 Seriale 213 Test
APERTI Parameter R8.500 Ohm I200.0mA
Tmin2.000ms Tmax2.000ms Test CORTI
Parameter R100.0kOhm U20.00V Tmin5.000ms
Tmax5.000ms Test HV-DC Parameter R1.500GOhm
U1000V Tempo salita1000V/Ms Tmin500.0ms
Tmax200.0ms
Test CORTI ---------- R100.0kOhm U20.00V
Tmin5.000ms Tmax5.000ms NCL
S gt100.00MOhm NCL
R
32.00MOhm NCL
B 6.106MOhm NCL
P 61.54MOhm
NCL X
gt100.00MOhm NCL
Y gt100.00MOhm NCL
V
gt100.00MOhm NCL
W 100.00MOhm NCL
T gt100.00MOhm
NCL U
gt100.00MOhm NCL
N gt100.00MOhm NCL
O
gt100.00MOhm NCL
L gt100.00MOhm NCL
M gt100.00MOhm
NCL J
gt100.00MOhm NCL
K gt100.00MOhm NCL
H
gt100.00MOhm NCL
I 100.00MOhm NCL
F gt100.00MOhm
NCL G
gt100.00MOhm NCL
D gt100.00MOhm NCL
E
gt100.00MOhm NCL
A gt100.00MOhm NCL
C 100.00MOhm
NCL FM36-CASE
gt100.00MOhm NCL
FM36-31 11.59MOhm NCL
FM36-30
100.00MOhm NCL
FM36-27 gt100.00MOhm NCL
FM36-12 gt100.00MOhm
NCL FM36-9
100.00MOhm NCL
FM36-10 gt100.00MOhm NCL
FM36-8
gt100.00MOhm NCL
FM36-4 100.00MOhm
tests against shorts (20V)
25Test APERTI Parameter R8.500 Ohm I200.0mA
Tmin2.000ms Tmax2.000ms Conn. J
FM36-2 4.770 Ohm 7
T2- Conn. K FM36-1
4.775 Ohm 8 T2 Conn. U
FM36-3 4.770 Ohm 9
T3 Conn. C FM36-6
4.750 Ohm 10 Vbias4 Conn. O
FM36-5 4.745 Ohm 11
Vbias1 Conn. H FM36-7
4.845 Ohm 12 Vbias7 Conn. G
FM36-11 4.712 Ohm 13
Vbrtn1 Conn. A FM36-14
4.772 Ohm 14 Vbias5 Conn. I
FM36-13 4.850 Ohm 15
Vbias2 Conn. N FM36-15
4.825 Ohm 16 Vbias8 Conn. Y
FM36-20 4.715 Ohm 17
Sense250- Conn. X FM36-19
4.760 Ohm 18 Sense250 Conn.
V FM36-22 4.735 Ohm
19 Sense125- Conn. W
FM36-21 4.717 Ohm 20
Sense125 Conn. L FM36-24
4.932 Ohm 21 T1- Conn. M
FM36-23 4.695 Ohm 22
T1 Conn. F FM36-26
4.727 Ohm 23 Vbrtn2 Conn. T
FM36-25 4.762 Ohm 24
T3- Conn. E FM36-28
4.797 Ohm 25 Vbias3 Conn. D
FM36-29 5.313 Ohm 26
Vbias6 Test APERTI Parameter R600.0mOhm
I200.0mA Tmin2.000ms Tmax2.000ms Conn.
FM36-CASE FM36-case 385.5mOhm
29 Case Conn. FM36-16
FM36-17 389.1mOhm 30 Drain2 Conn.
FM36-16 FM36-18
422.9mOhm 30 Drain2 Conn. FM36-16
FM36-31 557.0mOhm 30
Drain2 Conn. FM36-16 FM36-32
582.4mOhm 30 Drain2 Test APERTI
Parameter R60.00mOhm I200.0mA Tmin2.000ms
Tmax2.000ms Conn. B
FM36-A1 47.91mOhm 35 GND Test
APERTI Parameter R80.00mOhm I200.0mA
Tmin2.000ms Tmax2.000ms Conn. S
FM36-A2 64.94mOhm 37
V250 Test APERTI Parameter R170.0mOhm
I200.0mA Tmin2.000ms Tmax2.000ms Conn.
R FM36-A3 161.9mOhm
39 V125 Test APERTI Parameter R300.0mOhm
I200.0mA Tmin2.000ms Tmax2.000ms Conn.
P FM36-A4 231.9mOhm
41 Drain1
continuity tests (tw pairs)
drains
LVs
26isolation tests (1000V) one vs all others
DC-NCA J
17.91GOhm 47 T2- DC-NCA
K 14.58GOhm 48 T2 DC-NCA
U
99.34GOhm 49 T3 DC-NCA
C 17.21GOhm 50
Vbias4 DC-NCA O
14.28GOhm 51 Vbias1 DC-NCA
H 129.6GOhm 52
Vbias7 DC-NCA G
159.9GOhm 53 Vbrtn1 DC-NCA
A 24.26GOhm 54
Vbias5 DC-NCA I
20.46GOhm 55 Vbias2 DC-NCA
N 7.883GOhm 56
Vbias8 DC-NCA Y
16.13GOhm 57 Sense250- DC-NCA
X 12.66GOhm 58
Sense250 DC-NCA V
15.16GOhm 59 Sense125- DC-NCA
W 12.02GOhm
60 Sense125 DC-NCA L
11.72GOhm 61 T1- DC-NCA
M 9.986GOhm
62 T1 DC-NCA F
22.39GOhm 63 Vbrtn2 DC-NCA
T 18.43GOhm 64
T3- DC-NCA E
155.6GOhm 65 Vbias3 DC-NCA
D 130.0GOhm 66
Vbias6 Test HV-DC Parameter R10.00MOhm
U200.0V Tempo salita500V/s Tmin1.000 s
Tmax200.0ms DC-NCA B
419.7MOhm 69 GND DC-NCA
S 511.4MOhm 70
V250 DC-NCA R
1.430GOhm 71 V125 Test HV-DC
Parameter R1.500GOhm U1000V Tempo
salita1000V/Ms Tmin500.0ms Tmax200.0ms DC-NCA
FM36-4
20.38GOhm 74 Empty DC-NCA
FM36-8 22.76GOhm 75
Empty DC-NCA FM36-9
21.65GOhm 76 Empty DC-NCA
FM36-10 22.09GOhm 77
Empty DC-NCA FM36-12
22.74GOhm 78 Empty DC-NCA
FM36-27 22.18GOhm 79
Empty DC-NCA FM36-30
22.18GOhm 80 Empty
- C-Twist T01/T-01 FM36-23 FM36-24
3.029nF 84 - C-Twist T02/T-02 FM36-1 FM36-2
2.890nF 85 - C-Twist T03/T-03 FM36-3 FM36-25
3.327nF 86 - C-Twist Vbias1/Vbias4 FM36-5 FM36-6
3.256nF 87 - C-Twist Vbias2/Vbias3 FM36-13 FM36-28
3.417nF 88 - C-Twist Vbias5/Vbias6 FM36-14 FM36-29
3.313nF 89 - C-Twist Vbias7/Vbias8 FM36-7 FM36-15
3.393nF 90 - C-Twist Vbrtn1/Vbrtn2 FM36-11 FM36-26
3.190nF 91 - C-Twist S250/S250- FM36-19 FM36-20
3.593nF 93 - C-Twist S125/S125- FM36-21 FM36-22
3.464nF 94 - C-Twist Drain1/GND FM36-A4 FM36-A1
60.03nF 96 - C-Twist Drain2/GND FM36-31 FM36-A1
28.08nF 97 - Risultato del Test
- -------------------------------------
- Test APERTI B U O N O
- Test CORTI B U O N O
27First LIC_V1 sample
28first 35m LIC prod. deliveries
Summer !
29Experience with LIC cables
- LIC cable prototypes have been used to power our
detectors with our PS system since more than
three years - Around 270 LIC cables are in use
- 2003/2004 prototypes
- 2005 pre-production
- 2006 first deliveries
- Their performance is good
- several of them installed a lot of times and
survived bad handlings - test beams
- Louvain irradiation tests
- PSU test setup
- Few problems reported so far
- regarding damage of outer jacket (de-coloring,
perforation or peeling) - Proper handling procedure, according to the cable
specs, has to be adopted and trained manpower has
to handle the cables - never bend below nominal bending radius
- never pull over sharp edges
- use some specific (slippery) product to
de-install the cable - If not, we dont have cables for TIF ! (or for
CMS !)
30Experience with connectors
- One weakness of the FM36W4 (pp1) connectorisation
spotted after first prototypes - occasional contact of LVs, now solved
- Pins may occasionally get pushed inside the
bajonet connector - its not a damage they can be simply
repositioned with tweezers - Occasional difficulty in plugging the cable into
the PSU back-boards - limited experience with this kind of problems
too few and incomplete problem reports - from personal experience its better to follow
the natural torsion of the cable. Do not try to
exercise too much force in de-torsion - the thicker 40A pins may get distorted
- not a damage the pins get back into position
when the torsion force is released - General rule of thumb
- do not exaggerate with the force applied in
connecting the cables - never try to force the connectors guide
insertion key
31Power long control cables
32The PLCCs
- 20 PLCC_TIB/TID 20 PLCC_TOB prototypes produced
in 2005 - currently used in integration setups and MTCC
- production with final connectors just started
- PLCC_TIB/TID the first one to be produced
- Electrical tests (same kind as for LIC) performed
both by connectorising firm and at CERN, upon
reception
332020 PLCC test production
PLCC_TIB/TID
PLCC_TIB/TID
(151 Rconn. expected)
(92 Rconn. expected)
34Short cables
35TIB/TID cables
- Electrically tested (opens and shorts) at the
connectorising firm (ADAPT) - Tested upon reception at CERN with the usual
cable testing machine.
36typical CAB60 test
SCHAFFNER ELECTROTEST TEST SYSTEM
W427 ------------------------------------------ Pr
ogramma di test CAB 60 Nome del file
CAB_60 Data/ora 10/05/2006
14.26.14 Seriale 249-560 Test APERTI
Parameter R1.500 Ohm I200.0mA Tmin2.000ms
Tmax2.000ms Test CORTI Parameter R100.0kOhm
U20.00V Tmin5.000ms Tmax5.000ms Test HV-DC
Parameter R1.500GOhm U1000V Tempo
salita1000V/Ms Tmin500.0ms Tmax20.00ms Test
CORTI ---------- R100.0kOhm U20.00V
Tmin5.000ms Tmax5.000ms NCL
FM36-CASE gt100.00MOhm NCL
FM36-01
gt100.00MOhm NCL
FM36-02 gt100.00MOhm NCL
FM36-A2 gt100.00MOhm
NCL FM36-A3
gt100.00MOhm Conn. FM36-19
FM13-05 1.095 Ohm 7
Sense250 Conn. FM36-20 FM13-04
1.205 Ohm 8 Sense250- Conn.
FM36-21 FM13-10 1.007 Ohm
9 Sense125 Conn. FM36-22
FM13-09 1.028 Ohm 10
Sense125- Conn. FM36-05 FM13-01
1.083 Ohm 11 Vbias1 Conn.
FM36-28 FM13-02 1.092 Ohm
12 Vbias2 Conn. FM36-07
FM13-07 1.066 Ohm 13 Vbias3 Conn.
FM36-29 FM13-06 1.092
Ohm 14 Vbias4 Conn. FM36-11
FM13-08 1.044 Ohm 15 VbRTN1 Conn.
FM36-26 FM13-03 1.074
Ohm 16 VbRTN2
continuity tests (cut at R 1.5 W)
isolation tests (1000 V)
37 Test APERTI Parameter R800.0mOhm I200.0mA
Tmin2.000ms Tmax2.000ms Conn.
FM36-CASE FM36-case 368.9mOhm
19 CASE-FM36 Conn. FM36-16
FM36-17 385.9mOhm 20 Drain2 Conn.
FM36-16 FM36-18
386.9mOhm 20 Drain2 Conn. FM36-16
FM36-31 636.5mOhm 20
Drain2 Conn. FM36-16 FM36-32
642.0mOhm 20 Drain2 Conn.
FM36-16 FM13-CASE 570.1mOhm
20 Drain2 Conn. FM36-16
FM13-case 566.8mOhm 20 Drain2 Test
APERTI Parameter R100.0mOhm I200.0mA
Tmin2.000ms Tmax2.000ms Conn. FM36-A4
FM13-CASE 74.84mOhm 24
Drain1 Conn. FM36-A3 FM13-A3
84.08mOhm 25 V125 Test APERTI
Parameter R60.00mOhm I200.0mA Tmin2.000ms
Tmax2.000ms Conn. FM36-A2
FM13-A2 51.13mOhm 27 V250 Test
APERTI Parameter R40.00mOhm I200.0mA
Tmin2.000ms Tmax2.000ms Conn. FM36-A1
FM13-A1 32.78mOhm 29
GND DC-NCA FM36-19
103.2GOhm 33 Sense250
80 mW expected
53 mW expected
33 mW expected
38- DC-NCA FM36-20
23.26GOhm 34 Sense250- - DC-NCA FM36-21
25.16GOhm 35 Sense125 - DC-NCA FM36-22
93.02GOhm 36 Sense125- - DC-NCA FM36-05
85.11GOhm 37 Vbias1 - DC-NCA FM36-28
gt4000GOhm 38 Vbias2 - DC-NCA FM36-07
21.51GOhm 39 Vbias3 - DC-NCA FM36-29
26.89GOhm 40 Vbias4 - DC-NCA FM36-11
85.11GOhm 41 VbRTN1 - DC-NCA FM36-26
85.11GOhm 42 VbRTN2 - DC-NCA FM36-01
13.26GOhm 43 Empty - DC-NCA FM36-02
186.0GOhm 44 Empty - DC-NCA FM36-03
85.11GOhm 45 Empty - DC-NCA FM36-04
85.11GOhm 46 Empty - DC-NCA FM36-06
164.9GOhm 47 Empty - DC-NCA FM36-08
10.06GOhm 48 Empty - DC-NCA FM36-09
9.662GOhm 49 Empty - DC-NCA FM36-10
82.05GOhm 50 Empty - DC-NCA FM36-12
85.11GOhm 51 Empty - DC-NCA FM36-13
85.11GOhm 52 Empty
isolation tests
39TEC/TOB cables
- CAB60, CAB48, CAB36 and ctrl-pwr-s1
- The cable material is qualified at Habia visual
inspection, mechanical and geometrical checks,
resistance measurements - The cables are tested at ADAPT
- mechanical and geometrical checks
- pin-to-pin continuity test and short check
- hv test at 1KV (absorbed current and insulation
among HV wires) - visual inspection and electrical tests (Lyon test
box) at CERN - pin-to-pin continuity test and short check
- hv test at 600V (absorbed current and insulation
among HV wires)
(information from G. Magazzu)
40Data base
- Each cable used in CMS has to appear in the
cabling database - start point
- end point
- ID
- Each cable is labeled by firm after
connectorisation - type, date, length, serial number
- We intend to store general cable information
(production date, length, some of test results)
in our construction database - part of the structure already defined
- Cannot glue multiple labels on the same cable
- the IDs assigned by the cabling database have to
match those of the construction database, and
possibly resemble the serial number assigned by
the firm. - Two-D labels will be used for short cables
- We have to think carefully to which labels, and
where, should be stuck on long (LIC and PLCC)
cables.
41Further installation issues
- Do we check cables once they are installed in P5
? - topic still under discussion
- short cables no way, I guess
- long cables
- electrical tests with cable tester from the
balcony (short pairs of cables at PP1) - test complete LV and HV chain after the cable is
plugged into the PSU, using a test box in PP1 - we may benefit from the monitoring provided by
the PP1 interconnect board - is the installation scenario allowing to use
powered racks ? - Can we repair cables after installation ?
- PP1 forget it
- balcony it might be possible (depends on kind of
damage) - Cable spares
- we can foresee producing some spares
- we are heavily limited by space on cable trays
- have still to define the final cable distribution
- hope to place one or two spares per PP1
- at least PLCC spare