Title: Load Flow Modelling Service Project results 30 September 2002
1Load Flow Modelling ServiceProject results 30
September 2002
- Mick Barlow
- Srdjan Curcic
2Content
- Project objectives
- Modelling assumptions
- Some potential issues with the proposed
approaches to allocation of losses - Illustration of the key results
3Project objectives
- Power Technologies Int. has been commissioned to
assist the assessment procedure of modification
proposals P75 and P82, specifically - to perform calculations of TLFs TLMs for a
specified number of SPs for P75 P82 - to present the results in a form suitable for the
assessment procedure and - to draw attention to potential issues with the
fundamentals of the two marginal approaches
proposed (P75 P82) - This presentation contains an appropriate
selection of the project results
4Modelling assumptions
- MW injections are calculated from the metered
volumes assuming they are constant (average) - Power factors published in NGCs SYS are used to
calculate reactive power injections - It is assumed that offtake metered
volumes/injections are accurate and then the
delivery volumes/injections are calculated to
balance offtake metered volumes/injections and
calculated variable active power system losses,
while maintaining relative deliveries among the
generators (DICTATED BY DATA QUALITY)
5Modelling assumptions
- Load flow assumptions
- Generation P is calculated as described above
- Generation Q is calculated automatically by
setting voltage target to 1.03 p.u. - Load P is calculated from the metered volumes
- Load Q is calculated from typical power factors
given in the NGCs SYS - Transformer tap changer are set according to
information in the NGCs SYS for each voltage
level - Transformer target voltage is set to produce
reasonable voltage profile (between 0.97 and 1.03
p.u.) - SVCs target voltage is set to values recommended
in the NGCs SYS
6Modelling assumptions
- AC load flow calculations are using the standard
NGCs slack at Cowley - PTIs PSS/E-OPF is used for calculating marginal
TLFs - Out of TLFs obtained for active power injections
and reactive power injections, unique TLFs are
calculated that relate only to active power
injections, while providing for the total losses
incurred from a node - TLFij (TLFPij ? Pij TLFQij ? Qij) / Pij
7Modelling assumptions
- On the basis of information in the NGCs SYS, the
fixed losses are assumed to be 200MW (peak),
180MW (trough) and 190MW (other periods Autumn)
- For the purpose of calculating TLMs, these fixed
losses are smeared across generators,
proportionally to their power output
8Issues with proposed allocation of losses
- Slack node An issue with the marginal TLFs
approach
- The choice of the slack node potentially matters
more that initially expected
9Issues with proposed allocation of losses
Slack node
Network metered volumes are for 22 January
2002 Comparison is between slack node at Cowley
and at Thorpe Marsh
Illustrative example Assume a generation metered
volume of 1000MWh and a TLM of 0.94. That would
attribute 60MWh of losses to this generation.
Due to the indicated change in slack node this
60MWh of losses would change for 9.23, on
average.
10Issues with proposed allocation of losses
Power factor
- The sensitivity analysis to introduction/variation
of power factors has been done in an simple
exercise - For 02 January 2002 network and metered volumes
two cases were calculated - P.F. 1 for all demand nodes
- P.F. by NGCs SYS
11Issues with proposed allocation of losses
Power factor
- At the level of TLFs the effect was much more
tangible. This indicates - that reactive powers should not be ignored and
- a possible need for further consideration
12Summary Issues with proposed allocation of losses
- There are some issues arising from the modelling
- TLFMG, nevertheless, have confidence in the
modelling results
13Illustration of key resultsP75
14P75 (T1)Base cases02 Jan. 02 (SP36) - Peak01
Aug. 01 (SP8) - Trough10 Oct. 01 (SP25) Week
day daylight11 Oct. 01 (SP11) Week day night
13 Oct. 01 (SP25) Weekend daylight 14 Oct. 01
(SP11) Weekend night
15GSPG and TNUoS (gen) zones
16Change P75 introduces an example (based on
marginal, GSPG zone, ½ h TLFs)
02 January 2002
North
South
17Demand TLMs for P75 (based on marginal, GSPG
zone, ½ h TLFs)
North
South
18Change P75 introduces an example (based on
marginal, TNUoS (gen) zone, ½ h TLFs)
02 January 2002
North
South
19Generation TLMs for P75 (based on marginal, TNUoS
(gen) zone, ½ h TLFs)
North
South
20P75 (T1) - Summary
- Introduction of Modification Proposal P75 would
result in variable TLMs - over time and
- across country
- with an overall, indicative variation between
0.95 and 1.06 for demand and between 0.94 and
1.09 for generation
21P75 (T2)Variation of TLMs over time 02 Jan. 02
(SP8 SP36) Peak day01 Aug. 01 (SP8 SP36)
Trough day 10 Oct. 01 (SP1 SP48) Week day11
Oct. 01 (SP11) Week day night 13 Oct. 01
(SP25) Weekend daylight 14 Oct. 01 (SP11)
Weekend night
22P75 GSPG zone TLMs over sample time period -
demand
North
South
23P75 TNUoS (gen) zone TLMs over sample time
period - generation
North
South
24P75 GSPG zone TLMs over a day - Demand
10 October 2001
South
North
25P75 TNUoS (gen) zone TLMs over a day - Generation
10 October 2001
South
North
26P75 (T2) - Summary
- Introduction of Modification Proposal P75 would
result in daily variation in TLMs of up to
approximately 0.03 for demand and 0.045 for
generation (the exception is TNUoS zone 5 with
reversible hydro plants where the variation is up
to 0.065) on a typical autumn working day
27P75 (T3)Sensitivity to network
configurationIndicative/Intact/Representativenet
works for the following SPs 02 Jan. 02 (SP36) -
Peak01 Aug. 01 (SP8) - Trough10 Oct. 01 (SP25)
Week day daylight11 Oct. 01 (SP11) Week day
night 13 Oct. 01 (SP25) Weekend daylight 14
Oct. 01 (SP11) Weekend night
28P75 GSPG zone TLMs - Demandsensitivity to
network configuration
02 January 2002 (peak)
North
South
29P75 TNUoS (gen) zone TLMs - Generationsensitivit
y to network configuration
02 January 2002 (peak)
North
South
30P75 GSPG zone TLMs - Demandsensitivity to
network configuration
01 August 2002 (trough)
North
South
31P75 TNUoS (gen) zone TLMs - Generationsensitivit
y to network configuration
01 August 2002 (trough)
North
South
32P75 GSPG zone TLMs - Demandsensitivity to
network configuration
10 October 2001 (weekday daylight)
North
South
33P75 TNUoS (gen) zone TLMs - Generationsensitivit
y to network configuration
10 October 2001 (weekday daylight)
North
South
34P75 GSPG zone TLMs - Demandsensitivity to
network configuration
11 October 2001 (weekday night)
North
South
35P75 TNUoS (gen) zone TLMs - Generationsensitivit
y to network configuration
11 October 2001 (weekday night)
North
South
36P75 GSPG zone TLMs - Demandsensitivity to
network configuration
13 October 2001 (weekend daylight)
North
South
37P75 TNUoS (gen) zone TLMs - Generationsensitivit
y to network configuration
13 October 2001 (weekend daylight)
North
South
38P75 GSPG zone TLMs - Demandsensitivity to
network configuration
14 October 2001 (weekend night)
North
South
39P75 TNUoS (gen) zone TLMs - Generationsensitivit
y to network configuration
14 October 2001 (weekend night)
North
South
40P75 (T3) - Summary
- Network configuration can have an effect on TLMs
- while there is almost no difference between
intact and representative networks, - there is a tangible difference between indicative
and intact networks
41P75 (T4)Sensitivities to constraints02 January
2002 (base case)02 January 2002 (constrained
case)
5 double circuits restricted for 20 below the
flow level in base case
42P75 GSPG zone TLMs - Demandsensitivity to
constraints
Losses 758.5MW (base case), 573 (constrained
case)
North
South
43P75 TNUoS zone TLMs - Generation sensitivity to
constraints
Losses 758.5MW (base case), 573 (constrained
case)
North
South
44P75 (T4) - Summary
- Constraints may have an impact on TLMs
45P75 (T5)Comparison of Generation TLFs/TLMs and
Demand TLFs/TLMs at the same node
46P75 Comparison of Generation/Demand Zonal
TLFs/TLMs
Node Rye House GSPG zone 7 TNUoS
zone 10 SP 02 January 2002, SP36
47P75 (T5) - Summary
- Discrepancies between TLMs for generation and
demand at a node are not greatly exacerbated if
generation and demand zones are different from
one another - Only one node has been assessed and this may not
be representative
48P75 (T6)Comparison of Nodal TLFs/TLMs with Zonal
TLFs/TLMs
49P75 Comparison of Nodal/Zonal TLMs (Demand)
02 January 2002
Winter peak (SP36)
50P75 Comparison of Nodal/Zonal TLMs (Generation)
02 January 2002
Winter peak (SP36)
51P75 Comparison of Nodal/Zonal TLMs (Demand)
01 August 2001
Summer trough (SP8)
52P75 Comparison of Nodal/Zonal TLMs (Generation)
01 August 2001
Summer trough (SP8)
53P75 (T6) - Summary
- Introduction of Modification Proposal P75 and its
zonal TLMs (GSPG zones for demand and TNUoS (gen)
zones for generation) would result in nodal TLMs
for some nodes being closer to neighbouring zonal
TLMs
54P75 (T7)Model performance characteristics
55P75 Input data
- Data capture depends on the source systems
- Data capture will be greatly improved once NGCs
state estimator is fully operational - Amount, duration and quality of data depends on
the source systems and the TLF modification
applied - The quality and consistency of the data determine
the time and effort required to establish
acceptable loadflow conditions
56P75 Processing and output data
- Once a suitable loadflow data set has been
obtained it should take less than 10 seconds to
obtain TLFs for all considered generation/demand
points for a SP - The output would be suitably structured list of
TLFs - Further post processing could be established to
automatically produce a higher level of the
output data
57P75 (T8)Sensitivities to flows on French
Inter-connector31 October 2001 (importing)07
November 2001 (exporting)
58P75 GSPG zone TLMs -sensitivity to flows on
French Inter-connector
Losses 377.1MW (importing), 533.3 (exporting)
North
South
59P75 TNUoS zone TLMs -sensitivity to flows on
French Inter-connector
Losses 377.1MW (importing), 533.3 (exporting)
North
South
60P75 (T910)Examples of moving generation
deliveries for the selected nodes
Greystones
Barking Power
61P75 GSPG zone TLMs -sensitivity to plant
outages / response to signals
02 January 2002
North
South
62P75 TNUoS (gen) zone TLMs -sensitivity to plant
outages / response to signals
02 January 2002
North
South
63For the base case of 02 January 2002 500MW were
moved from Dinorwig to 5 different places
P75 (T11) Sensitivity to intermittent generation
Blyth
Harker
Norwich
Dinorwig
Grain
Indian Queens
64P75 GSPG zone TLMs - Demandsensitivity to
intermittent generation
02 January 2002
North
South
65P75 TNUoS zone TLMs - Generationsensitivity to
intermittent generation
02 January 2002
North
South
66P75 (T8 to T11) - Summary
- TLMs in Modification Proposal P75 are only
locally sensitive to plant withdrawal or plant
relocation or to intermittent generation - Note that for Task 8 (sensitivity to flow on
French inter-connector) the effect is complicated
as we have two different dates and SPs with
different generation and demand profiles
67Illustration of key resultsP82
68P82 (T1)Variation of scaled TLFs over time02
Jan. 02 (SP8 SP36) Peak day01 Aug. 01 (SP8
SP36) Trough day 10 Oct. 01 (SP1 SP48)
Week day11 Oct. 01 (SP11) Week day night 13
Oct. 01 (SP25) Weekend daylight 14 Oct. 01
(SP11) Weekend night
69P82 GSPG zone ½ h TLMs over sample time period -
Demand
North
South
70P82 GSPG zone ½ h TLMs over sample time period -
Generation
North
South
71P82 GSPG zone ½ h TLMs over a day - Demand
10 October 2001
South
North
72P82 GSPG zone ½ h TLMs over a day - Generation
10 October 2001
South
North
73P82 (T1) - Summary
- Before implementing the averaging of TLFs, the
variation in TLMs for P82 would be up to
approximately 0.016 for demand and 0.017 for
generation on a typical autumn working day
74P82 (T2)Base cases 02 Jan. 02 (SP36) - Peak01
Aug. 01 (SP8) - Trough10 Oct. 01 (SP25) Week
day daylight11 Oct. 01 (SP11) Week day night
13 Oct. 01 (SP25) Weekend daylight 14 Oct. 01
(SP11) Weekend night
75GSPG and TNUoS (gen) zones
76Change P82 introduces an example (based on
scaled, GSPG zone, averaged TLFs)
02 January 2002
North
South
77Demand TLMs for P82 (based on scaled, GSPG zone,
averaged TLFs)
North
South
78Change P82 introduces an example (based on
scaled, GSPG zone, averaged TLFs)
02 January 2002
North
South
79Generation TLMs for P82 (based on scaled, GSPG
zone, averaged TLFs)
North
South
80P82 (T2) - Summary
- Introduction of Modification Proposal P82 would
result in variable TLMs - over time and
- across country
- with an overall variation between 0.99 and 1.03
for demand and between 0.975 and 1.015 for
generation, where spatial variations are larger
than temporal variations
81P82 (T3)Variation of TLMs over time(based on
average scaled TLFs)02 Jan. 02 (SP8 SP36)
Peak day01 Aug. 01 (SP8 SP36) Trough day 10
Oct. 01 (SP1 SP48) Week day11 Oct. 01 (SP11)
Week day night 13 Oct. 01 (SP25) Weekend
daylight 14 Oct. 01 (SP11) Weekend night
82P82 GSPG zone TLMs over sample time period -
Demand
North
South
83P82 GSPG zone TLMs over sample time period -
Generation
North
South
84P82 GSPG zone TLMs over a day - Demand
10 October 2001
South
North
85P82 GSPG zone TLMs over a day - Generation
10 October 2001
South
North
86P82 (T3) - Summary
- Introduction of Modification Proposal P82 would
result in almost non-existent daily variations in
TLMs (up to approximately 0.004 for demand and
0.004 for generation) on a typical autumn working
day
87P82 (T4)Sensitivity of TLFs TLMs to choice of
historic data and weightings
88P82 Sensitivity of TLFs TLMs to historic data
and weighting coefficients
- This task has not been completed as the required
input data have not been provided
89P82 (T5)Sensitivities to constraints02 January
2002 (base case)02 January 2002 (constrained
case)
5 double circuits restricted for 20 below the
flow level in base case
90P82 GSPG zone TLMs - Demandsensitivity to
constraints
Losses 758.5MW (base case), 573 (constrained
case)
North
South
91P82 TNUoS zone TLMs - Generation sensitivity to
constraints
Losses 758.5MW (base case), 573 (constrained
case)
North
South
92P82 (T5) - Summary
- TLMs in Modification Proposal P82 are almost
insensitive to constraints because the effects
of such events would be averaged in the following
year
93P82 (T6)Comparison of Nodal TLFs/TLMs with Zonal
TLFs/TLMs
94P82 Comparison of Nodal/Zonal TLMs Generation
02 January 2002
Winter peak (SP36)
95P82 Comparison of Nodal/Zonal TLMs - Demand
02 January 2002
Winter peak (SP36)
96P82 Comparison of Nodal/Zonal TLMs Generation
01 August 2001
Summer trough (SP8)
97P82 Comparison of Nodal/Zonal TLMs - Demand
01 August 2001
Summer trough (SP8)
98P82 (T6) - Summary
- Introduction of Modification Proposal P82 and its
zonal TLMs (GSPG zones only for both demand and
generation) would result in nodal TLMs for some
nodes being closer to neighbouring zonal TLMs
99P82 (T7)Sensitivities to flows on French
Inter-connector31 October 2001 (importing)07
November 2001 (exporting)
100P82 GSPG zone TLMs - Demandsensitivity to flows
on French Inter-connector
Losses 377.1MW (importing), 533.3 (exporting)
North
South
101P82 GSPG zone TLMs - Generationsensitivity to
flows on French Inter-connector
Losses 377.1MW (importing), 533.3 (exporting)
North
South
102P82 (T7) - Summary
- TLMs in Modification Proposal P82 are almost
insensitive to direction of flows on the French
inter-connector because the effects of such
events would be averaged in the following year
103P82 (T8) Degree to which a scaling factor of 0.5
recovers heating losses 02 Jan. 02 (SP36) -
Peak01 Aug. 01 (SP8) - Trough10 Oct. 01 (SP25)
Week day daylight11 Oct. 01 (SP11) Week day
night 13 Oct. 01 (SP25) Weekend daylight 14
Oct. 01 (SP11) Weekend night
104P82 Comparison between flat 0.5 scaling factor
and the actual reconciliation factors
105P82 Nodal TLFs recovery of heating losses with
scaling factor 0.5 and the actual reconciliation
factors
106P82 (T8) - Summary
- Scaling factor of 0.5 does not precisely recover
heating losses but appears to be a reasonable
approximation
107P82 (T910)Examples of moving generation
deliveries for the selected nodes
Greystones
Barking Power
108P82 GSPG zone TLMs - Demand sensitivity to
plant outages / response to signals
02 January 2002
North
South
109P82 GSPG zone TLMs - Generation sensitivity to
plant outages / response to signals
02 January 2002
North
South
110For the base case of 02 January 2002 500MW were
moved from Dinorwig to 5 different places
P82 (T11) Sensitivity to intermittent generation
Blyth
Harker
Norwich
Dinorwig
Grain
Indian Queens
111P82 GSPG zone TLMs - Demandsensitivity to
intermittent generation
02 January 2002
North
South
112P82 GSPG zone TLMs - Generationsensitivity to
intermittent generation
02 January 2002
North
South
113P82 (T9 to T11) - Summary
- TLMs in Modification Proposal P82 are almost
insensitive to plant withdrawal or move or to
intermittent generation because the effects of
such events would be averaged in the following
year
114END OF PRESENTATION