Oregon GHG X pilot - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

Oregon GHG X pilot

Description:

Re-characterized a task in an existing EN Grant (due to lost sponsor) Started to detail the scope for GHG Exchange ... Battled scope creep working with internal needs ... – PowerPoint PPT presentation

Number of Views:37
Avg rating:3.0/5.0
Slides: 14
Provided by: exchangene
Category:
Tags: ghg | battled | oregon | pilot

less

Transcript and Presenter's Notes

Title: Oregon GHG X pilot


1
Oregon GHG X pilot
  • Won Kim, Glen Carr
  • Oregon DEQ
  • Exchange Network National Meeting
  • April 28-30, 2009

2
Presentation Outline
  • Introduction
  • Project Contents
  • Goals
  • Western Climate Initiative (WCI)
  • Logistics
  • Risks
  • Approach
  • Conclusion

3
Introduction
  • Re-characterized a task in an existing EN Grant
    (due to lost sponsor)
  • Started to detail the scope for GHG Exchange
  • Collaborated with internal Air Quality program,
    EPA, ECOS and TCR

4
Project - Goals
  • Program leverage
  • Existing AQ program
  • Tracking Reporting and Administration of Air
    Contaminant Sources (TRAACS)
  • The Climate Registry (TCR)
  • Emissions Inventory System (EIS)
  • Portability-Sharability
  • Respond to Western Climate Initiative (WCI)
    actions
  • Ease of Use

5
Project WCI
  • Collaboration of 7 US governors and 4 Canadian
    Premiers
  • Oregon is a participating state establishes
    some precedence in GHG Exchange.
  • WCI was created to identify, evaluate, and
    implement collective and cooperative ways to
    reduce greenhouse gases in the region, focusing
    on a market-based cap-and-trade system. (source
    www.westernclimateinitiative.org)

6
Project Logistics
  • 8 month timeline
  • Limited Budget
  • AQ program buy in they pay for their work
    share.
  • Local work session to outline scope and
    roles/responsibility

7
Project - Risks
  • Reporting rule changes
  • EPA and WCI decision timeframe
  • Guessing games
  • Seamless integration with EPA, WCI, TCR, EIS,
    ODEQ, etc.
  • AQ program expectations vs. what is delivered
  • Scope creep

8
Project - Approach
  • Flexible needs flexible design
  • Workable model CERS
  • Ability to leverage product
  • Scalable/Portable model
  • Paradigm shift in design approach

9
Project - Approach
  • Cross program applications (GHG, EIS, FRS, etc)
  • Synchronize with TCR, EPA, WCI and ODEQ - stand
    alone user to broad audience (sources)
  • Standards based solution
  • Object orientated approach
  • Inter-changeable style and design
  • Table Controls Business rule object
  • Load back end data view with GHG front end or
    direct data entry

10
A Team mantra
EIS
11
Data Flow
TCR/EPA
Approved
12
Lessons Learned/Conclusion
  • Battled scope creep working with internal needs
  • Dynamic nature of program results in dynamic
    designs
  • Up front work pays off
  • Part of work is done for EIS
  • (criteria air pollutants, etc)

13
Questions?
  • Won Kim
  • Oregon DEQ
  • kim.won_at_deq.state.or.us