Bridge Rehabilitation - PowerPoint PPT Presentation

1 / 90
About This Presentation
Title:

Bridge Rehabilitation

Description:

Bridge Rehabilitation – PowerPoint PPT presentation

Number of Views:4193
Avg rating:5.0/5.0
Slides: 91
Provided by: bol8
Category:

less

Transcript and Presenter's Notes

Title: Bridge Rehabilitation


1
Bridge Rehabilitation
  • BSI Bridge site investigation
  • Strength Analysis
  • Concrete Repairs
  • Steel Repairs
  • Bridge Decks
  • Joint Beam End Modifications
  • Integral Semi-integral Conversions
  • Widening

2
Bridge Site Investigation
  • Existing Plans
  • Reality
  • Man-made changes
  • Natural changes

3
(No Transcript)
4
(No Transcript)
5
(No Transcript)
6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
(No Transcript)
11
(No Transcript)
12
54-0 per plans, 50-0 actual


13
(No Transcript)
14
Bridge Rehabilitation Existing Bridge Structural
Requirements
  • Strength
  • Bridge Design Manual HS-20 with 60 psf FWS
  • As scoped
  • Generally HS-25 with 60 psf FWS, especially for
    mainline bridges
  • HS-20 may be accepted
  • Fatigue
  • New policy pending

15
Existing Bridge Structural Requirements Fatigue
Analysis
Method B
Method A
16
Bridge Rehabilitation Submittal
RequirementsStructure Type Study
  • Fatigue and/or load evaluation (if scoped)
  • Color photographs
  • Summary of field investigation
  • Preliminary rehab details

17
Bridge Rehabilitation Concrete Repair
  • Item 519 Concrete Patching
  • Item 520 Pnuematically placed mortar
  • Item Special Shotcreting Concrete Structures
  • Trowelable mortar

18
Concrete RepairThick, formable, and structural
patches
  • Item 519 Concrete Patching
  • Formed and poured
  • Repair depth 3 inches or greater
  • Best choice if applicable
  • Abutment pier seats, curbs, sidewalks, parapet
    tops

19
Concrete RepairThin patches
  • Item 520 Pnuematically placed mortar
  • Repair depth 3 inches or less
  • Applied with spray equipment
  • Recommended for between 150 and 350 sq. ft.

20
Concrete RepairThin patches
  • Item Special - Shotcreting concrete structures
  • Repair depth 3 inches or less
  • Recommended for greater than 350 sq. ft.
  • Stringent testing and performance specs.

21
Concrete RepairThin patches
  • Item Special Trowelable mortar
  • Supplemental Specification 843
  • Repair depth 3 inches or less
  • Recommended for less than 150 sq. ft.

22
Concrete Repair
23
Concrete RepairGeneral Recommendations
  • Use sounding and not visual
  • Perform sounding close to sale date
  • Use plan quantity 2 to 3 times sounded area, more
    if not close to sale date
  • Do not patch deck bottoms over traveled lanes
  • Consider concrete removal and use of solvent free
    epoxy resin and urethane topcoat if area is not
    visible to public

24
Concrete Repair Summary of Total Common
Concrete Repair Quantities 2002-2004
  • Patching Concrete Structures 268,128
    S.F.
  • Pnuematically Placed Mortar/
  • Shotcreting Concrete Structures 11,629
    S.F.
  • Patching Concrete Structures with Trowelable
    Mortar


  • 27,466 S.F.

25
Bridge Rehabilitation Steel Repairs Fatigue
Issues
26
Bridge Rehabilitation Steel Repairs Fatigue
Issues
  • Problem ? Solution
  • Stress induced fatigue crack
  • Distortion induced fatigue crack

27
Bridge Rehabilitation Steel Repairs Fatigue
IssuesStress Induced Fatigue
28
Bridge Rehabilitation Steel Repairs Fatigue
Issues
Stress Induced Fatigue
29
(No Transcript)
30
Bridge Rehabilitation Steel Repairs Fatigue
IssuesDistortion Induced Fatigue
31
Bridge Rehabilitation Steel Repairs Fatigue
Issues
Distortion Induced Fatigue
32
Bridge Rehabilitation Steel Repairs Fatigue
Issues
Distortion Induced Fatigue
33
Bridge Rehabilitation Steel Repairs Fatigue
Repairs
Solution A Free it up
34
Bridge Rehabilitation Steel Repairs Fatigue
Repairs
35
Steel Repairs Fatigue Repairs
Solution B Lock it up
36
Bridge Rehabilitation Fatigue Repairs
37
(No Transcript)
38
(No Transcript)
39
Bridge Rehabilitation Bridge Decks
  • Closure pours construction joints
  • Haunch issues

40
Bridge Rehabilitation Bridge Decks Closure
Pours
41
Bridge Rehabilitation Bridge Decks Closure
Pours
42
Bridge Rehabilitation Bridge Decks Closure
Pours
43
Bridge Rehabilitation Bridge Decks Closure
Pours
44
Bridge Rehabilitation Bridge Decks Closure
Pours
Crossframes welded later
45
Bridge Rehabilitation Bridge Decks Closure
Pours
Crossframes welded later
46
Bridge Rehabilitation Bridge Decks Closure
Pours
47
Bridge Rehabilitation Bridge Decks Closure
Pours
Release crossframes
48
Bridge Rehabilitation Bridge Decks Closure
Pours
Release crossframes
49
Bridge Rehabilitation Bridge Decks Closure
Pours
50
Bridge Rehabilitation Bridge Decks Closure
Pours
Reinstall crossframes
51
Bridge Rehabilitation Bridge Decks Closure
Pours
The closure pour may be eliminated for this
condition if the designer can show that the
outside existing member, now being attached to
the new member, is not restrained from returning
to its original unloaded position by the new
cross frames (designated D1in Figure 409-D).
52
Bridge Rehabilitation Bridge Decks Closure
Pours
Closure pours may be eliminated if the
differential deflection is expected to be less
than ¼ inch regardless of superstructure type.
53
Bridge Rehabilitation Bridge Decks Closure
Pours
54
Bridge Decks Cut Lines
55
Bridge Decks Profile Issues
  • Survey of Existing Beams Required by the BDM
  • Give clear instructions to surveyors

56
Bridge Decks Profile Issues
  • Maximum haunch 12 inches
  • Reinforce haunch if 5 inches
  • Use 9 inch wide haunch

57
Bridge Decks Profile Issues
58
Bridge Rehabilitation Beam Ends and Deck Joints
59
(No Transcript)
60
(No Transcript)
61
Bridge Rehabilitation Jointless Conversions
62
Integral Conversion
63
Integral Conversion
64
Jointless Conversions
65
Jointless Conversions
After
Before
66
Jointless Conversions
67
Jointless Conversions
Bridge Plan View
68
Bridge Rehabilitation Widening Issues
69
(No Transcript)
70
(No Transcript)
71
409.5 PIER COLUMNS New pier columns added for
the purpose of widening shall be tied into the
existing pier if the pier type is cap and column.
Individual freestanding columns are not
permitted. When the existing piers are either
T-type or wall-type piers, the designer should
evaluate whether the new individual column should
be tied back into the existing substructure unit
or remain free standing. Two or more adjacent
freestanding individual columns without a cap are
not permitted.
72
(No Transcript)
73
(No Transcript)
74
(No Transcript)
75
(No Transcript)
76
(No Transcript)
77
(No Transcript)
78
(No Transcript)
79
(No Transcript)
80
(No Transcript)
81
(No Transcript)
82
Bridge Rehabilitation Widening Sheeting and
Shoring
Plan Design Required if height 8 feet
Two PE Stamps Required
83
Bridge Rehabilitation Widening Sheeting and
Shoring
84
Bridge Rehabilitation Widening Sheeting and
Shoring
85
Sheeting and Shoring
86
(No Transcript)
87
Bridge Rehabilitation Widening Sheeting and
Shoring
88
Bridge Rehabilitation Widening Sheeting and
Shoring
89
Bridge Rehabilitation Widening Sheeting and
Shoring
90
Questions ???
Write a Comment
User Comments (0)
About PowerShow.com