Title: Bridge Rehabilitation
1Bridge Rehabilitation
- BSI Bridge site investigation
- Strength Analysis
- Concrete Repairs
- Steel Repairs
- Bridge Decks
- Joint Beam End Modifications
- Integral Semi-integral Conversions
- Widening
2Bridge Site Investigation
- Existing Plans
- Reality
- Man-made changes
- Natural changes
3(No Transcript)
4(No Transcript)
5(No Transcript)
6(No Transcript)
7(No Transcript)
8(No Transcript)
9(No Transcript)
10(No Transcript)
11(No Transcript)
12 54-0 per plans, 50-0 actual
13(No Transcript)
14Bridge Rehabilitation Existing Bridge Structural
Requirements
- Strength
- Bridge Design Manual HS-20 with 60 psf FWS
- As scoped
- Generally HS-25 with 60 psf FWS, especially for
mainline bridges - HS-20 may be accepted
- Fatigue
- New policy pending
15Existing Bridge Structural Requirements Fatigue
Analysis
Method B
Method A
16Bridge Rehabilitation Submittal
RequirementsStructure Type Study
- Fatigue and/or load evaluation (if scoped)
- Color photographs
- Summary of field investigation
- Preliminary rehab details
17Bridge Rehabilitation Concrete Repair
- Item 519 Concrete Patching
- Item 520 Pnuematically placed mortar
- Item Special Shotcreting Concrete Structures
- Trowelable mortar
18Concrete RepairThick, formable, and structural
patches
- Item 519 Concrete Patching
- Formed and poured
- Repair depth 3 inches or greater
- Best choice if applicable
- Abutment pier seats, curbs, sidewalks, parapet
tops
19Concrete RepairThin patches
- Item 520 Pnuematically placed mortar
- Repair depth 3 inches or less
- Applied with spray equipment
- Recommended for between 150 and 350 sq. ft.
20Concrete RepairThin patches
- Item Special - Shotcreting concrete structures
- Repair depth 3 inches or less
- Recommended for greater than 350 sq. ft.
- Stringent testing and performance specs.
21Concrete RepairThin patches
- Item Special Trowelable mortar
- Supplemental Specification 843
- Repair depth 3 inches or less
- Recommended for less than 150 sq. ft.
22Concrete Repair
23Concrete RepairGeneral Recommendations
- Use sounding and not visual
- Perform sounding close to sale date
- Use plan quantity 2 to 3 times sounded area, more
if not close to sale date - Do not patch deck bottoms over traveled lanes
- Consider concrete removal and use of solvent free
epoxy resin and urethane topcoat if area is not
visible to public
24Concrete Repair Summary of Total Common
Concrete Repair Quantities 2002-2004
- Patching Concrete Structures 268,128
S.F. - Pnuematically Placed Mortar/
- Shotcreting Concrete Structures 11,629
S.F. - Patching Concrete Structures with Trowelable
Mortar -
27,466 S.F.
25Bridge Rehabilitation Steel Repairs Fatigue
Issues
26Bridge Rehabilitation Steel Repairs Fatigue
Issues
- Problem ? Solution
- Stress induced fatigue crack
- Distortion induced fatigue crack
27Bridge Rehabilitation Steel Repairs Fatigue
IssuesStress Induced Fatigue
28Bridge Rehabilitation Steel Repairs Fatigue
Issues
Stress Induced Fatigue
29(No Transcript)
30Bridge Rehabilitation Steel Repairs Fatigue
IssuesDistortion Induced Fatigue
31Bridge Rehabilitation Steel Repairs Fatigue
Issues
Distortion Induced Fatigue
32Bridge Rehabilitation Steel Repairs Fatigue
Issues
Distortion Induced Fatigue
33Bridge Rehabilitation Steel Repairs Fatigue
Repairs
Solution A Free it up
34Bridge Rehabilitation Steel Repairs Fatigue
Repairs
35Steel Repairs Fatigue Repairs
Solution B Lock it up
36Bridge Rehabilitation Fatigue Repairs
37(No Transcript)
38(No Transcript)
39Bridge Rehabilitation Bridge Decks
- Closure pours construction joints
- Haunch issues
40Bridge Rehabilitation Bridge Decks Closure
Pours
41Bridge Rehabilitation Bridge Decks Closure
Pours
42Bridge Rehabilitation Bridge Decks Closure
Pours
43Bridge Rehabilitation Bridge Decks Closure
Pours
44Bridge Rehabilitation Bridge Decks Closure
Pours
Crossframes welded later
45Bridge Rehabilitation Bridge Decks Closure
Pours
Crossframes welded later
46Bridge Rehabilitation Bridge Decks Closure
Pours
47Bridge Rehabilitation Bridge Decks Closure
Pours
Release crossframes
48Bridge Rehabilitation Bridge Decks Closure
Pours
Release crossframes
49Bridge Rehabilitation Bridge Decks Closure
Pours
50Bridge Rehabilitation Bridge Decks Closure
Pours
Reinstall crossframes
51Bridge Rehabilitation Bridge Decks Closure
Pours
The closure pour may be eliminated for this
condition if the designer can show that the
outside existing member, now being attached to
the new member, is not restrained from returning
to its original unloaded position by the new
cross frames (designated D1in Figure 409-D).
52Bridge Rehabilitation Bridge Decks Closure
Pours
Closure pours may be eliminated if the
differential deflection is expected to be less
than ¼ inch regardless of superstructure type.
53Bridge Rehabilitation Bridge Decks Closure
Pours
54Bridge Decks Cut Lines
55Bridge Decks Profile Issues
- Survey of Existing Beams Required by the BDM
- Give clear instructions to surveyors
56Bridge Decks Profile Issues
- Maximum haunch 12 inches
- Reinforce haunch if 5 inches
- Use 9 inch wide haunch
57Bridge Decks Profile Issues
58Bridge Rehabilitation Beam Ends and Deck Joints
59(No Transcript)
60(No Transcript)
61Bridge Rehabilitation Jointless Conversions
62Integral Conversion
63Integral Conversion
64Jointless Conversions
65Jointless Conversions
After
Before
66Jointless Conversions
67Jointless Conversions
Bridge Plan View
68Bridge Rehabilitation Widening Issues
69(No Transcript)
70(No Transcript)
71409.5 PIER COLUMNS New pier columns added for
the purpose of widening shall be tied into the
existing pier if the pier type is cap and column.
Individual freestanding columns are not
permitted. When the existing piers are either
T-type or wall-type piers, the designer should
evaluate whether the new individual column should
be tied back into the existing substructure unit
or remain free standing. Two or more adjacent
freestanding individual columns without a cap are
not permitted.
72(No Transcript)
73(No Transcript)
74(No Transcript)
75(No Transcript)
76(No Transcript)
77(No Transcript)
78(No Transcript)
79(No Transcript)
80(No Transcript)
81(No Transcript)
82Bridge Rehabilitation Widening Sheeting and
Shoring
Plan Design Required if height 8 feet
Two PE Stamps Required
83Bridge Rehabilitation Widening Sheeting and
Shoring
84Bridge Rehabilitation Widening Sheeting and
Shoring
85Sheeting and Shoring
86(No Transcript)
87Bridge Rehabilitation Widening Sheeting and
Shoring
88Bridge Rehabilitation Widening Sheeting and
Shoring
89Bridge Rehabilitation Widening Sheeting and
Shoring
90Questions ???