Title: Jonas Pearce November 19, 1999
11999 Grand Target Mine Feasibility Study
- Jonas Pearce November 19, 1999
2Project Overview
- General Mine Site Information
- Reserve Estimation
- Mining
- Financial Analysis
3LOCATION
Kartar Road
GRAND TARGET MINE
4Environmental Concerns
EIS 700,000 31/2 Years Baseline
Studies 191,000 11/2 Years Archeology Water
Permitting 98,100 1 Year Engineering 500,
000 1 Year Total 1.5 million over 4 to
4-1/2 Years
5Environmental Concerns
- Reclamation Bond Sinking Fund 79,500 over 10
year mine life
6Reserve Estimation
- 309 Drill Holes
- 23,287 Assay Values
- No Distribution
- ID2 Estimation Method
- Horizontal search radius 100 ft
- Vertical search radius 150 ft
- Block Size 100 X 100 X 100 ft
7Reserve Estimation
- Reserve Estimate
- Cut Off Grade 1.0 oz/ton
- 90 blocks
- 7.5 Million Tons
- 1.84 oz/ton Average Grade
- Resource Estimate
- 635 Blocks
- 53 Million Tons
- .503 oz/ton Ave. Grade
8(No Transcript)
9Total Mineable Reserves
8.25 Million Tons 1.68 oz/ton Average Grade 13.8
million ounces Au
10Mining
- First Year of Production - 2006
- Mine Life - 10 Years
- Mining Method - Vertical Crater Retreat
- Mining Levels Range from 1300 to 2700 ft Above
Sea Level - Production Begins on 2100 Level
- Mining Progresses Upward
11Main Decline Plan View
12Main Decline Long Section View
13Main Decline Section View
14Underground Development
15Primary Development to Ventilation Raises
16Typical Level
17Stoping
- 100 ft long X 100 ft high X 25 ft wide Stopes
- 15 Days to Mine One Stope
- 20,900 Tons Per Stope
18Step 1 Drive top and bottom sill drifts
19Step 2 Drill 36 - 6.5 inch diameter blast holes
20Step 3 Blast and muck the 1st 14-ft slab of ore
21Step 4 Blast and muck the 2nd 14-ft round
22Step 4 Blast and muck the 3rd 14-ft round
23Step 5 Blast and muck the 4th and final 28-ft of
ore
24Backfill
- Paste Backfill
- 55 Mill Tails
- 8 Cement
- 41 Tails to Sand Ratio
- Waste Rock
- 7 Days to Backfill 1 Stope
25Ventilation
- Primary
- 1,500 hp Exhausting Fan in Ventilation Raise 2
- 425,000 cfm
- Secondary
- 15 hp Auxiliary Fans
26Auxiliary Ventilation on Working Levels
27Major Equipment
- 2 LHDs - 4.4 yd3 Bucket, Remote Control
- 4 (6) Haul Truck - 31 Ton Capacity
- 2 In-The-Hole Drills - Large Diameter Holes
- 2 Jumbo Drills - Twin Boom
- 1 Rock Bolter
- 2 ANFO Loader
28Auxiliary Equipment
- Surface
- 1 Bulldozer
- 1 Front End Loader
- 1 Grader
- 1 Water Truck
- 1 Haul Pack
- Underground
- 1 Scissor Lift
- 1 Road Builder (Grader)
- 1 Lube Truck
- 1 Utility Truck
- 1 Air Compressor - 1500 cfm
- 1 14 Man Personnel Carrier
- 7 Transport Tractors
29Production
- 2360 Tons Per Day
- 350 Days Per Year
- 2 Shifts Per Day
- 10 Hours Per Shift
30Processing
- Carbon in Pulp Mill
- 95 Recovery
- 98 Pure Gold Bullion
- Water Balance
- Water Treatment Plant
- Tailings Disposal
31Infrastructure
- Power
- Nespelem Valley Electric Co-op
- .047 kWh
- 115 kV Power Line to Mine Site
- Substation
- Compressed Air - 1500 cfm
- Diesel Fuel Price - .68/gallon
- Potable Water - Fresh Water Well
32Employment
Hourly 52 Underground Miners and Laborers 52
Surface Workers 40 Mill and Lab Personnel 5
Service Employees Average Hourly Wage 17/hr
Benefits and Bonus Salary 50 Salaried
Personnel Average Salary 68,000/year
including benefits 199 Total Employees
33Financial Analysis
Gold Price 275/oz Transportation Cost .16
per 100 lbs. Per Mile Discount Hurdle
Rate 15 Royalties 10 Gross Revenue
34Costs
- Capital Costs
- Buildings and Surface Facilities 41 million
- Equipment 2.3 million
- Studies and Permits 1.5 million
- Operating Costs
- Stoping 1.74/ton
- Development 192.80/ft
35(No Transcript)
36Cost Summary
37Refining
- Johnson Mathey Refiners in Salt Lake City, Utah
- 99.99 Pure Gold Returned
- 1.00 per Troy Ounce
38Loan
- 44.5 Million Loan
- 7 Interest Rate
- Two Installments 2 Years Before Production Begins
- Payment Begins When Production Begins
39(No Transcript)
40Economic Analysis
- 15 Hurdle Rate
- NPV 382 Million
- IRR 140
- Break Even Price of Gold 50/oz
41Recommendations
- Scrutinize Reserve Estimation
- Geology and Rock Mechanics
- Lower Cut Off Grade
- Production Shaft
- Other Mining Methods