Crystal Falls Township Water System Improvements Project - PowerPoint PPT Presentation

1 / 96
About This Presentation
Title:

Crystal Falls Township Water System Improvements Project

Description:

Crystal Falls Township Water System Improvements Project – PowerPoint PPT presentation

Number of Views:143
Avg rating:3.0/5.0
Slides: 97
Provided by: STS19
Category:

less

Transcript and Presenter's Notes

Title: Crystal Falls Township Water System Improvements Project


1
(No Transcript)
2
Crystal Falls Township / Crystal Falls CityWater
System Improvement Projects
Crystal Falls Township Water System Improvements
Project
  • Presented by Jeff Bal
  • at the
  • 59th Annual U.P. Water Institute Conference

3
Crystal Falls Township Hall and Public Works
Garage
4
(No Transcript)
5
Water Infrastructure Projects in the U.P.
  • Crystal Falls Township - Typical Community
  • Influenced by Mining Industry
  • Aging Water System
  • Did not meet Water System Reliability Standards
  • Small Customer Base
  • Needed to Reduce/Control Costs and Increase
    Customer Base to Generate and Preserve Revenue

6
Crystal Falls Township Water System Improvements
  • Need for Project
  • Firm Capacity / System Reliability
  • Leakage (60-70)
  • Fire Flows (Minimal or Non-existent)
  • Widespread Pressure Fluctuations
  • - Little or no pressure at some homes during
    peak daily demand periods
  • - Commercial Demands Could Not be Satisfied
  • Large Need for System Updates and Mainline
    Replacement
  • Wells
  • Tanks
  • Booster Pumps
  • Etc.

7
Large Widespread Service Areas
  • Rehabilitation
  • Need for Funding Assistance
  • USDA-RD, EPA, MEDC, other

8
City of Crystal Falls
9
City of Crystal Falls Faced Similar Issues
  • Influenced Mining Industry
  • Aging Water System
  • Aging Wells and Water Treatment System
  • Shrinking Customer Base
  • Needed to Reduce/Control Costs

10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
City of Crystal Falls
  • Needed to either
  • Develop New Water Supply Source or
  • Construct New Treatment Plant due to High Iron
    and Manganese concentrations
  • City also needs to upgrade distribution Piping
  • All Costly Alternatives
  • During 2004 - City was Unsuccessful in Finding
    new source for water of Suitable Quality
  • City desired considering water agreement with
    Township

18
Ultimately Cost Savings thru a Water Purchase
Agreement Would Provide Benefits to Both
Sidesbut it wouldnt be that easy
19
City Township Water Agreement Negotiations
began March 25, 2005
20
Crystal Falls Township Project Development
  • 1998-2002 Preliminary Engineering
  • 2002 Grant/Loan Application USDA-RD
  • - 3,271,000 Grant (56)
  • - 2,588,000 Loan 4.5 _at_ 40 Years
  • 2002-05 RD Funding Delayed
  • 2005 Township Received Special Appropriations
    Grant for 385,000
  • 2005 RD Adjust Grant/Loan Offering to 2.27 Mil
    Grant / 3.59 Mil Loan
  • 2005 RD Funding was Secured and Preliminary
    Design Work Began in Spring for 6 Million
    Township only Water Project
  • Township Willing to discuss Water Agreement with
    City in Part due to Grant / Loan Revisions

21
Crystal Falls Township Project Included
  • Original Design Basis
  • 250 GPM Firm Pumping Requirement for Lind System
  • (1) Well Rehabilitation for Lind System
  • (1) 50,000 Elevated tank to be removed
  • (1) New Well For Townline Rd System for
    Reliability
  • (1) New 200,000 Gallon Elevated Tank
  • (2) Tanks Rehabilitated
  • Approximately 70,000 Feet of New Water Main

22
Township City Negotiations Intensify
  • April 5, 2005
  • April 28, 2005
  • May 6, 2005
  • July 19, 2005
  • Draft Terms of Agreement Reached in August 2005
  • Firm Capacity Requirements Established for Each
    Community
  • Water Agreement Contingent upon Aquifer Testing
  • Final Terms of Agreement Negotiated November 2005
    thru October 2006
  • Agreement Signed October 3, 2006

23
Crystal Falls Township Project Development
  • Township/City Water Agreement (Deal of the
    Century)
  • - City Agrees to Contribute 1.4 Million toward
    Township Project for Improvements Necessary to
    meet City Flow Requirements
  • - All New Design Basis Developed 2006-07

24
Crystal Falls Township Crystal Falls City
  • Design Basis Includes
  • 800 GPM Firm Pumping Requirement for Lind System
  • (2) Wells Rehabilitation for Lind System
  • (2) New Wells for Lind System
  • (1) 50,000 Elevated tank to be removed
  • (1) New Well For Townline Rd System for
    Reliability
  • (1) New 500,000 Gallon Ground Storage Tank
  • (2) Tanks Rehabilitated
  • Approximately 72,000 Feet of New Water Main
  • Master Control Meter Station to Control Flow to
    City
  • Radio SCADA System
  • Master Meter Station to Measure Flow Out of City

25
(No Transcript)
26
City of Crystal Falls also Did Several Projects
at This Time
  • Main Street Sewer Separation and Water Main
    Replacement 800,000
  • City Transmission Main Upgrades 1,408,000
  • Meter Installations for All Customers 500,000
  • Projects Funded thru RD Loan and MEDC Grant

27
Crystal Falls Township Water System
  • 660 Customers
  • 196,000 Feet of Pipe (37 Miles)
  • 18 Customers per Mile of Piping
  • 2 Completely Separated Systems

28
Crystal Falls Township Water System
  • 3 Well Fields
  • Provides Service to Wholesale Customers
  • - Hematite Township
  • - Mastodon Township
  • - City of Crystal Falls

29
Some of the Challenges
  • Schedule Majority of work needed to be
    designed, constructed and started up within 12
    months of the City/Township Agreement
  • Coordination of Township project with on-going
    City Contractor
  • Increasing capacity by three-fold to satisfy City
    demand.
  • Start-up, disinfection of system tanks, wells,
    pumps and control systems.
  • .and Deer Season.

30
Project Components
  • Three Separate Construction Contracts
  • Contract I Water Storage Tanks
  • Contract II Booster Pump Station/Wells
  • Contract III Distribution System Piping

31
Contract I - Taniks
32
Project Components Continued
  • Contract I Tanks
  • New 500,000 gallon ground storage tank
  • Rehabilitate 75,000 gallon Elevated North End
    Tank
  • Rehabilitate 150,000 gallon Elevated Lind System
    Tank
  • Demolition of 50,000 gallon Tank

33
Contract II Booster Station and Wells
34
Project Components Continued
  • Contract II Booster Pump Station/Wells
  • New Booster Pump Station w/(2) - 1,000 GPM pumps
  • New North End Well/Controls/Well House Expansion
  • New Lind System Wells/Controls/Well House
    Expansion

35
Project Components Continued
  • Kuivila Well House and Pump Improvements
  • SCADA System Centralizing Controls from about a
    119 Square Mile Area
  • - All Water System Controls and Operating Data
    Trending
  • - Some Sewer System Controls and Operating Data
    Trending

36
Contract III - Piping
37
Project Components Continued
  • Contract III Distribution
  • 72,000 feet of new pipe
  • 5,000 feet of directional borings (wetlands,
    streams, highways and railroads)
  • New Customer Water Meters with Vehicle Equipped
    Automatic Radio Meter Reading Equipment

38
Contract III Piping Continued
39
Contract III Piping Continued
40
Wells and Well House Construction Photos
41
Expanded Lind Well House for New Well
42
Lind Well House and New Well
43
Expanded Townline Road Well House for New Well
44
Ground Storage Tank Construction Photos
45
Ground Storage Tank Inlet/Outlet Piping Designed
for Mixing
46
New 500,000 Gallon Ground Storage Tank
47
(No Transcript)
48
Pipe Laying Challenges
49
Rock Excavation Along Highway US-2
  • 6,500 cyd of rock removed on the project

50
Rock Blasting/Dual Pipe Installation Through
Private Property
51
Dual 16 Watermain Installation Rock/Groundwater
52
Booster Pump Station Photos
53
New Booster Pump Station
54
(No Transcript)
55
(No Transcript)
56
Booster Pump Station Controls
57
(No Transcript)
58
Townships US-2 Elevated Tank
  • Receives Water from Ground Storage Tank from
    Booster Pump Station

59
Booster Pump and Existing Elevated Tank
60
The Death of Smiley
  • ...he was a good tank

61
Existing 50,000 Gallon Smiley Tank Replaced by
500,000 Gallon Ground Storage Tank
62
The Death of Smiley
63
.yes, a sad day...
but wait, Terry can fix em
64
Smiley lives onon top of the New Ground
Storage Tank. A memento of the past
65
Contract II New Radio Controls and SCADA System
  • Uniquely Procured Prior to Bidding Project
  • Contractors used Dollar Allowance on their Bid
    Form
  • Hired Controls Integrator Selected by STS/Township

66
Contract II Controls and SCADA System
  • Provides Sustainable Design Features Integrated
    into Project.

67
(No Transcript)
68
(No Transcript)
69
(No Transcript)
70
(No Transcript)
71
(No Transcript)
72
(No Transcript)
73
City Flow Control Valve and Controls
74
City Master Flow Control Valve Assembly
75
City Master Flow Control Valve Vault In Progress
76
(No Transcript)
77
(No Transcript)
78
Existing Sewer Lift Station with New Radio
Integrated into Township SCADA System
79
(No Transcript)
80
Dont let this relaxed, happy look fool you.
81
(No Transcript)
82
Conclusion
  • A Long Term Agreement and Cost Effective Solution
    Was Achieved by All Parties Involved, including
  • Crystal Falls Township Customers
  • Hematite Township Customers
  • Mastodon Township Customers
  • and Customers of City of Crystal Falls

83
Conclusion Continued
  • Funding Summary
  • RD Grant 2.27M
  • RD Loan 3.589M
  • EPA Grant 386K
  • Crystal Falls Township Road Fund 183K
  • City of Crystal Falls 1.407M
  • Hematite Township Road Fund 14,700
  • Total Cost 7.85M

84
The End
85
(No Transcript)
86
(No Transcript)
87
(No Transcript)
88
Proposed Steps for Next Year
  • Grant Application
  • Wellhead Team Agreements Needed for Application
  • Final Wellhead Delineation Report and Maps
  • Contaminant Source Inventory
  • Develop Wellhead Management Plan for existing and
    future wells
  • 5. Development of a public education program

89
Review of 2007 Draft Wellhead Delineation Report
  • Surveyed existing wells and developed groundwater
    contour map (Potentiometric Surface Map).
  • Conceptual Model
  • To determine aquifer parameters
  • Identified draft wellhead delineation areas.

90
Lind System Potentiometric Map
91
(No Transcript)
92
(No Transcript)
93
North System Potentiometric Map
94
(No Transcript)
95
(No Transcript)
96
(No Transcript)
97
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com