Title: Crystal Falls Township Water System Improvements Project
1(No Transcript)
2Crystal Falls Township / Crystal Falls CityWater
System Improvement Projects
Crystal Falls Township Water System Improvements
Project
- Presented by Jeff Bal
- at the
- 59th Annual U.P. Water Institute Conference
3Crystal Falls Township Hall and Public Works
Garage
4(No Transcript)
5Water Infrastructure Projects in the U.P.
- Crystal Falls Township - Typical Community
- Influenced by Mining Industry
- Aging Water System
- Did not meet Water System Reliability Standards
- Small Customer Base
- Needed to Reduce/Control Costs and Increase
Customer Base to Generate and Preserve Revenue
6Crystal Falls Township Water System Improvements
- Need for Project
- Firm Capacity / System Reliability
- Leakage (60-70)
- Fire Flows (Minimal or Non-existent)
- Widespread Pressure Fluctuations
- - Little or no pressure at some homes during
peak daily demand periods - - Commercial Demands Could Not be Satisfied
- Large Need for System Updates and Mainline
Replacement - Wells
- Tanks
- Booster Pumps
- Etc.
7Large Widespread Service Areas
- Rehabilitation
- Need for Funding Assistance
- USDA-RD, EPA, MEDC, other
8City of Crystal Falls
9City of Crystal Falls Faced Similar Issues
- Influenced Mining Industry
- Aging Water System
- Aging Wells and Water Treatment System
- Shrinking Customer Base
- Needed to Reduce/Control Costs
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16(No Transcript)
17City of Crystal Falls
- Needed to either
- Develop New Water Supply Source or
- Construct New Treatment Plant due to High Iron
and Manganese concentrations - City also needs to upgrade distribution Piping
- All Costly Alternatives
- During 2004 - City was Unsuccessful in Finding
new source for water of Suitable Quality - City desired considering water agreement with
Township
18Ultimately Cost Savings thru a Water Purchase
Agreement Would Provide Benefits to Both
Sidesbut it wouldnt be that easy
19City Township Water Agreement Negotiations
began March 25, 2005
20Crystal Falls Township Project Development
- 1998-2002 Preliminary Engineering
- 2002 Grant/Loan Application USDA-RD
- - 3,271,000 Grant (56)
- - 2,588,000 Loan 4.5 _at_ 40 Years
- 2002-05 RD Funding Delayed
- 2005 Township Received Special Appropriations
Grant for 385,000 - 2005 RD Adjust Grant/Loan Offering to 2.27 Mil
Grant / 3.59 Mil Loan - 2005 RD Funding was Secured and Preliminary
Design Work Began in Spring for 6 Million
Township only Water Project - Township Willing to discuss Water Agreement with
City in Part due to Grant / Loan Revisions
21Crystal Falls Township Project Included
- Original Design Basis
- 250 GPM Firm Pumping Requirement for Lind System
- (1) Well Rehabilitation for Lind System
- (1) 50,000 Elevated tank to be removed
- (1) New Well For Townline Rd System for
Reliability - (1) New 200,000 Gallon Elevated Tank
- (2) Tanks Rehabilitated
- Approximately 70,000 Feet of New Water Main
22Township City Negotiations Intensify
- April 5, 2005
- April 28, 2005
- May 6, 2005
- July 19, 2005
- Draft Terms of Agreement Reached in August 2005
- Firm Capacity Requirements Established for Each
Community - Water Agreement Contingent upon Aquifer Testing
- Final Terms of Agreement Negotiated November 2005
thru October 2006 - Agreement Signed October 3, 2006
23Crystal Falls Township Project Development
- Township/City Water Agreement (Deal of the
Century) - - City Agrees to Contribute 1.4 Million toward
Township Project for Improvements Necessary to
meet City Flow Requirements - - All New Design Basis Developed 2006-07
24Crystal Falls Township Crystal Falls City
- Design Basis Includes
- 800 GPM Firm Pumping Requirement for Lind System
- (2) Wells Rehabilitation for Lind System
- (2) New Wells for Lind System
- (1) 50,000 Elevated tank to be removed
- (1) New Well For Townline Rd System for
Reliability - (1) New 500,000 Gallon Ground Storage Tank
- (2) Tanks Rehabilitated
- Approximately 72,000 Feet of New Water Main
- Master Control Meter Station to Control Flow to
City - Radio SCADA System
- Master Meter Station to Measure Flow Out of City
25(No Transcript)
26City of Crystal Falls also Did Several Projects
at This Time
- Main Street Sewer Separation and Water Main
Replacement 800,000 - City Transmission Main Upgrades 1,408,000
- Meter Installations for All Customers 500,000
- Projects Funded thru RD Loan and MEDC Grant
27Crystal Falls Township Water System
- 660 Customers
- 196,000 Feet of Pipe (37 Miles)
- 18 Customers per Mile of Piping
- 2 Completely Separated Systems
28Crystal Falls Township Water System
- 3 Well Fields
- Provides Service to Wholesale Customers
- - Hematite Township
- - Mastodon Township
- - City of Crystal Falls
29Some of the Challenges
- Schedule Majority of work needed to be
designed, constructed and started up within 12
months of the City/Township Agreement - Coordination of Township project with on-going
City Contractor - Increasing capacity by three-fold to satisfy City
demand. - Start-up, disinfection of system tanks, wells,
pumps and control systems. - .and Deer Season.
30Project Components
- Three Separate Construction Contracts
- Contract I Water Storage Tanks
- Contract II Booster Pump Station/Wells
- Contract III Distribution System Piping
31Contract I - Taniks
32Project Components Continued
- Contract I Tanks
- New 500,000 gallon ground storage tank
- Rehabilitate 75,000 gallon Elevated North End
Tank - Rehabilitate 150,000 gallon Elevated Lind System
Tank - Demolition of 50,000 gallon Tank
33Contract II Booster Station and Wells
34Project Components Continued
- Contract II Booster Pump Station/Wells
- New Booster Pump Station w/(2) - 1,000 GPM pumps
- New North End Well/Controls/Well House Expansion
- New Lind System Wells/Controls/Well House
Expansion
35Project Components Continued
- Kuivila Well House and Pump Improvements
- SCADA System Centralizing Controls from about a
119 Square Mile Area - - All Water System Controls and Operating Data
Trending - - Some Sewer System Controls and Operating Data
Trending
36Contract III - Piping
37Project Components Continued
- Contract III Distribution
- 72,000 feet of new pipe
- 5,000 feet of directional borings (wetlands,
streams, highways and railroads) - New Customer Water Meters with Vehicle Equipped
Automatic Radio Meter Reading Equipment
38Contract III Piping Continued
39Contract III Piping Continued
40Wells and Well House Construction Photos
41Expanded Lind Well House for New Well
42Lind Well House and New Well
43Expanded Townline Road Well House for New Well
44Ground Storage Tank Construction Photos
45Ground Storage Tank Inlet/Outlet Piping Designed
for Mixing
46New 500,000 Gallon Ground Storage Tank
47(No Transcript)
48Pipe Laying Challenges
49Rock Excavation Along Highway US-2
- 6,500 cyd of rock removed on the project
50Rock Blasting/Dual Pipe Installation Through
Private Property
51Dual 16 Watermain Installation Rock/Groundwater
52Booster Pump Station Photos
53New Booster Pump Station
54(No Transcript)
55(No Transcript)
56Booster Pump Station Controls
57(No Transcript)
58Townships US-2 Elevated Tank
- Receives Water from Ground Storage Tank from
Booster Pump Station
59Booster Pump and Existing Elevated Tank
60The Death of Smiley
61Existing 50,000 Gallon Smiley Tank Replaced by
500,000 Gallon Ground Storage Tank
62The Death of Smiley
63.yes, a sad day...
but wait, Terry can fix em
64Smiley lives onon top of the New Ground
Storage Tank. A memento of the past
65Contract II New Radio Controls and SCADA System
- Uniquely Procured Prior to Bidding Project
- Contractors used Dollar Allowance on their Bid
Form - Hired Controls Integrator Selected by STS/Township
66Contract II Controls and SCADA System
- Provides Sustainable Design Features Integrated
into Project.
67(No Transcript)
68(No Transcript)
69(No Transcript)
70(No Transcript)
71(No Transcript)
72(No Transcript)
73City Flow Control Valve and Controls
74City Master Flow Control Valve Assembly
75City Master Flow Control Valve Vault In Progress
76(No Transcript)
77(No Transcript)
78Existing Sewer Lift Station with New Radio
Integrated into Township SCADA System
79(No Transcript)
80Dont let this relaxed, happy look fool you.
81(No Transcript)
82Conclusion
- A Long Term Agreement and Cost Effective Solution
Was Achieved by All Parties Involved, including - Crystal Falls Township Customers
- Hematite Township Customers
- Mastodon Township Customers
- and Customers of City of Crystal Falls
83Conclusion Continued
- Funding Summary
- RD Grant 2.27M
- RD Loan 3.589M
- EPA Grant 386K
- Crystal Falls Township Road Fund 183K
- City of Crystal Falls 1.407M
- Hematite Township Road Fund 14,700
- Total Cost 7.85M
84The End
85(No Transcript)
86(No Transcript)
87(No Transcript)
88Proposed Steps for Next Year
- Grant Application
- Wellhead Team Agreements Needed for Application
- Final Wellhead Delineation Report and Maps
- Contaminant Source Inventory
- Develop Wellhead Management Plan for existing and
future wells - 5. Development of a public education program
89Review of 2007 Draft Wellhead Delineation Report
- Surveyed existing wells and developed groundwater
contour map (Potentiometric Surface Map). - Conceptual Model
- To determine aquifer parameters
- Identified draft wellhead delineation areas.
90Lind System Potentiometric Map
91(No Transcript)
92(No Transcript)
93North System Potentiometric Map
94(No Transcript)
95(No Transcript)
96(No Transcript)
97(No Transcript)