Lantech Case Study - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Lantech Case Study

Description:

saved from the brink of bankruptcy by multiple Kaizen events. Kaizen's have resulted in increased productivity and profitability: ... – PowerPoint PPT presentation

Number of Views:200
Avg rating:3.0/5.0
Slides: 16
Provided by: Pra21
Category:
Tags: brink | case | lantech | study

less

Transcript and Presenter's Notes

Title: Lantech Case Study


1
Lantech Case Study
Presented by Ray Essig Natalie
Lavergne Karine Lavoie-Tremblay
2
Background Information
  • Lantech is a Kentucky based wrapping machine
    manufacturer
  • saved from the brink of bankruptcy by multiple
    Kaizen events
  • Kaizens have resulted in increased productivity
    and profitability
  • went from 50 employees turning out 8 machines/day
    to 20 people turning out 14 machines/day
  • order processing time went from 5 wks to 14 hrs
  • sales increased by 3 1/2 times

3
Abstract
4
The Kaizen Process
  • Kaizen means continuous, incremental
    improvement in an activity, to create more value
    with less waste.
  • A Kaizen Event is a process that a company
    orchestrates to try to improve their specific
    manufacturing operations.
  • Carried out in a real time enviroment
  • Held towards end of improvement process

5
(No Transcript)
6
  • Team should include
  • workers who work in current system
  • workers who will work in new system
  • experienced kaizen facilitators
  • management who can implement changes
  • Steps
  • problem identification
  • gather information
  • analyze information
  • determine root cause
  • generate ideas to solve problems
  • utilize simulation software
  • implement agreed upon solutions
  • check results

7
Assumptions
  • In order to be able to perform an analysis of the
    Lantech systems, some assumptions had to be made
    where actual data was not available
  • the same assumptions were used in all 4 analysis
    techniques

8
Queuing Theory
  • Utilized following equations to improve
    throughput time
  • P(0) Probability system is empty 1- ?
  • Wq expected time in line ?/?(1-?)
  • L time in system ?/(1-?)
  • W Total time in system 1/?(1-?)
  • Where ? ?/c? , ? average arrival rate, c
    number of servers, and ? average service rate.
  • Current Gear drive assembly takes 6 hours
  • 1 machine, 6 hours, 1.5 machine, 9 hours.
  • Current Demand is 1.5 / 8 hour day
  • Using queuing theory, reduced throughput time to
    1 machine, 5 hours

9
Queuing Theory Results, before Kaizen
10
Queuing Theory Results, after Kaizen
11
Flow shop sequencing
  • Created a precedence structure and sequence the
    departments accordingly 38 gain in efficiency
    from original case
  • Multi-task resources in addition to the
    precedence structure 69 gain in efficiency from
    original case

12
Facility Layout
  • Built a REL chart
  • TCR based on new layout 33 savings on total
    flow cost

13
ProModel Analysis
  • Several analyses were run using ProModel
  • limiting factor on analysis was model size
  • ProModel helped identify areas of bottleneck
    where re-allocation of resources could improve
    throughput - specifically areas with high cycle
    time

14
Discussion
  • 4 different tools Queuing Theory, Flow shop
    sequencing, Facility Layout and Pro-Model.
  • Each tool improves a different element of the
    Lantech manufacturing system
  • total flow cost
  • resources
  • throughput time
  • layout
  • sequencing
  • efficiency/profitability

15
Conclusion
  • A company initially needs to identify which
    elements of their system they would like to
    optimize.
  • The company should then proceed to use a
    combination of the different tools in order to
    maximize their respective strengths and provide
    an overall system benefit.
Write a Comment
User Comments (0)
About PowerShow.com