1North Main Street Improvements
- BID Meeting
- Wednesday, October 29, 2008
2Project Team Introductions
- WisDOT
- Bill Bertrand, P.E. Project Manager
- Jill Michaelson, P.E. Project Supervisor
- City of Oshkosh, Dept. of Public Works
- David Patek, P.E. Director
- Steve Gohde, P.E. Assistant Director
- MSA Professional Services Design Consultants
- Mike Statz, P.E. Project Manager
- Jason DiPiazza, P.E. Project Engineer
- Ken Saiki Design Landscape Architects
- Shane Bernau
- Ken Saiki, A.S.L.A.
- Heritage Research Historical Consultants
3Meeting Agenda
- Presentation
- Project overview
- Schedule
- Scope
- Project details
- Geometry
- Staging
- Streetscape
- Open House
- Displays
- Aerial photos
- Project plan View
- Typical sections
- Streetscape elements
- Questions and answers
- With project staff
4Project Overview - Schedule
- Public information meeting 2 November 13, 2008
- (60 Design Phase)
- Submit Final Plans April, 2009
- Construction 2010
- Full construction season (Spring through Fall)
5Project Overview Scope
- Produce construction plans from the LDR Concept
Plan
6Project Overview - Scope
- Replace the aging infrastructure
- Pavement
- Curb and gutter
- Sidewalk
- Utilities
- Sewer, water etc.
- Streetscape
- Lights, amenities etc.
- Add safety enhancements
- Bump outs etc.
7Project Details Limits
- Fox River Bridge to Irving Avenue
- Cross streets
- Reconstructed to N. Main Street Right-of-Way
(typical)
8Project Details - Geometry
Ceape Avenue 2 southbound lanes 1 northbound lane
Otter Avenue 2 southbound lanes (south of
Otter) 1 northbound lane
9Project Details - Geometry
Algoma Boulevard 2 travel lanes 2 parking lanes
400 Block Bump outs Parking lanes
10Project Details - Geometry
- Typical section
- Wider sidewalks and terraces
- More room for
- Pedestrians
- Trees
- Street lights
- Amenities
- Merchants
11Project Details - Staging
- N. Main Street closed during construction
- Access
- Parking lots behind buildings
- Pedestrian access to building fronts
- Cross street traffic
- Maintained for some intersections staged
- Regular construction progress meetings
- Keep businesses informed
12Project Details - Streetscape
13Project Details Streetscape
- Street trees strategically located in front of
building corners, blank walls, and parking lots. - Tree grates are used along Main St. with
exception of bump out areas - Tree layout carefully considers underground
utilities, façade signage, signal poles, light
pole layout.
14Project Details - Streetscape
- Streetscape incorporates design cues from Opera
House Square (LDR plan). Features include
half-circle tree pits, brick banding, trash
receptacles, bike racks, and benches.
FLUSH CONCRETE EDGE
- Modified street tree planter detail reduces snow
plow damage by replacing the raised concrete edge
w/ a flush edge.
MAIN ST.
15Thank You