Summary: ABB Suite of Power Transmission Test Cases - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Summary: ABB Suite of Power Transmission Test Cases

Description:

Tap Changer Tries to Restore Voltage. Generator field limit activated at ... Capacitor and tap changer control can be used freely 'Medium Scale' ABB Test Case ... – PowerPoint PPT presentation

Number of Views:86
Avg rating:3.0/5.0
Slides: 16
Provided by: ABB75
Category:

less

Transcript and Presenter's Notes

Title: Summary: ABB Suite of Power Transmission Test Cases


1
SummaryABB Suite of Power Transmission Test
Cases
Mats Larsson Corporate Research ABB Switzerland
Ltd. Jan 19, 2004
2
Collapse Scenario
  • Line tripping (L3) after 100 s
  • Inherent Load Recovery
  • Tap Changer Tries to Restore Voltage
  • Generator field limit activated at 286 s
  • Collapse

3
Control Objectives
  • Stabilize all voltages within 0.9 - 1.1 p.u.
  • Use minimal amount of load shedding
  • Control voltage at bus 4 as close as possible to
    1 p.u.
  • Capacitor and tap changer control can be used
    freely

4
Medium Scale ABB Test Case
  • Three copies of small case
  • Similar control objectives
  • Recovery dynamics in
  • load (continuous)
  • Transformers (discrete)
  • Inputs
  • Line impedances (disturbance)
  • 3 Capacitors
  • 3 Voltage Refs. Transformer (optional)
  • 3 Load shedding
  • Outputs
  • 3 Load voltages
  • 2 Generator field voltages

5
Case 1 Tripping of Lines
Vload2
Vload3
1
0.9
0
100
200
300
400
GEfd2
GEfd3
1.8
1.7
1.6
0
100
200
300
400
pos2
pos3
15
10
5
0
0
100
200
300
400
  • Collapse in 400 secs

6
Case 2 Cap Switch in Area 2
Vload2
Vload3
1.05
1
0.95
0.9
0
100
200
300
400
GEfd2
GEfd3
1.8
1.7
1.6
0
100
200
300
400
pos2
pos3
6
4
2
0
100
200
300
400
System.C2.step
1
0
  • Cap switch at 100 secs stabilizes

0
100
200
300
400
7
Case 3 Tap Reference Change (-5)
Vload2
Vload3
1
0.98
0.96
0.94
0
100
200
300
400
GEfd1
GEfd2
1.8
1.7
1.6
0
100
200
300
400
pos2
pos3
6
4
2
0
0
100
200
300
400
  • Tap reference at 100 secs stabilizes

8
Case 4 Second line trip
Vload2
Vload3
1
0.8
0.6
0.4
0
100
200
300
400
GEfd1
GEfd2
1.8
1.75
1.7
1.65
1.6
0
100
200
300
400
pos2
pos3
12
8
4
0
100
200
300
400
  • No longer stable ...

9
Case 5 Added load shedding at bus 3
Vload2
Vload3
1
0.96
0.92
0
100
200
300
400
GEfd1
GEfd2
1.8
1.7
1.6
1.5
0
100
200
300
400
pos2
pos3
4
2
0
0
100
200
300
400
  • Additional load shedding stabilizes

10
Model Complexity
  • 6 disturbance inputs - (0,1,2)
  • Control inputs
  • 3 capacitors - (0,1)
  • 3 load shedding (0,1,2,3)
  • 3 tap voltage refs (0.81.2)
  • Continuous dynamics
  • 3 loads (2 dynamic states each)
  • Discrete dynamics
  • 3 transformers (3 states each)
  • 2 generator limiters (2 states each)

11
Possible work on new model
  • Scaling of Model-predictive approaches (ETH,
    Grenoble?)
  • Testing of decentralized schemes (Lund, Grenoble)
  • Requests for customized versions welcome ...

12
Large scale case CIGRE Nordic 32
  • 52 Discrete control inputs
  • Load shedding
  • Generator voltage setpoints
  • Tap changers
  • 10 Controlled outputs
  • Load voltages
  • 67 Constrained outputs
  • All voltages, generator currents
  • State-space 1041 nodes

13
Generator Trip No Emergency Control
  • At 10 s Gen 4062 Trips
  • Lost generation compensated by hydro units in the
    north
  • Increased losses in transmission corridor, lower
    voltage in southern region
  • Generators in the south increase reactive power
    production

4012
  • At 30 s Gen 1043 and 4042 at limit
  • Voltage support lost in middle and southern parts

4042
  • At 50 s Tap changers restore load
  • Further voltage decrease
  • Collapse at 180 s

1043
4062
14
Generator Trip Model Predictive Control
Generator trip
1
0.95
Voltage (p.u.)
0.9
0.85
V1043
V4012
V4042
0.8
0
100
200
300
400
500
Time (sec)
15
Constraint Management
1.1
1.05
1
Armature Currents
0.95
0.9
0.85
200
400
600
800
1000
Write a Comment
User Comments (0)
About PowerShow.com