Title: Data Center Partner Selection
1Data Center Partner Selection
- Town Hall Discussions
- 31 January 2007
- Al Kellie
- Tim Killeen
- Krista Laursen
- Jeff Reaves
2NCARs Fundamental Responsibility
- Provide the greatest possible computational
capability to the national community, at the
lowest possible cost, with realistic options for
further expansions - The faster we add capability, the greater the
scientific benefits we provide
The Wyoming offer provides more computing,
sooner, and at lower cost
3Path to the Partnership
- Exploration of several options to secure a new
facility (including leasing space, re-fitting an
existing data center, pursuing new construction)
initiated by a team of NCAR and UCAR personnel
roughly two years ago - New construction with the involvement of a
partner identified as the most viable and cost
effective option discussions initiated with a
variety of potential Front Range partners (CSU,
CSM, IBM, CU, and Wyoming) - NSF, a Blue Ribbon Panel (BRP), and the UCAR
Board of Trustees (BOT) engaged throughout the
project discovery phase to ensure appropriate
community guidance and support for the endeavor - Project vision broadened approximately one year
ago to focus not just on the construction of a
new NCAR supercomputing facility but on the
development of a larger geosciences
cyber-collaboratory framework - With NSF and community support, decision made in
Fall 2006 to pursue construction of a new NCAR
supercomputing facility and the development of a
geosciences cyber-collaboratory in parallel - Negotiations with two final partner candidates
(CU and Wyoming) completed in early January
4Partnership Highlights
- As the facility partner, Wyoming agrees to
- Provide a shovel-ready site in the North Range
Business Park (Cheyenne LEADS) - Provide additional required physical
infrastructure (e.g., site connection to fiber
optics network) - Utilize State Treasurer Industrial Revenue Bond
program for funding of the construction effort
(community issues bonds, Treasurer purchases
them, paid off by NCAR) - Provide necessary electrical infrastructure to
guarantee transmission level power of 24 MW to
the facility (Cheyenne Light Fuel and Power) - Provide 20M from Univ. of Wyoming endowment fund
for construction - Provide 1M annually for facility operations
(Univ. of Wyoming) - Additional partnerships with Wyoming, CU, CSU,
CSM, NREL, and others will be explored as part of
effort to develop a Front Range
Cyber-Collaboratory - NCAR is continuing discussions with CU to
identify a meaningful, founding partnership role
for CU in the initial build-out of the data
center and creation of the FRCC
5Opportunities
Challenges
- Strong NCAR/UCAR ownership land, facility, and
project management - Optimization of early science, with significantly
larger initial computer purchase allowing NCAR to
return to leadership class computing in 2010 - Significant flexibility Cheyenne site ideally
suited for straightforward facility expansion in
the future, 5 initial faculty joint appointments - Lower cost of construction
- Long-term financial savings, lower annual debt
service approx. 8M over 20 years - Unique and transformative partnership
- Lack of proximity to other NCAR facilities
- Impact of moving a major NCAR facility to another
state - Requirement for staff relocation
- Complexity of splitting off and moving some
NCAR/CISL staff to Wyoming and managing personnel
in two locations - Increased staffing costs additional staff
needed and relocation costs - Fewer options for showcasing the new facility
- Project management complications overseeing
construction activities in a more removed
location
6Facility Basics
- Selected site covers 24 acres in the North Range
Business Park (see below) - Modular facility design to be implemented, with
initial size to be 108,000 sq. ft. with
15,000-25,000 sq. ft. of raised floor - Initial power build-out to 8 MW, with 4-5 MW for
computing and 3-4 MW for cooling
- Facility power to primarily come from clean
coal - NCAR is working aggressively to secure the
provision of wind energy as well - Design, construction, and operation of the data
center as a high performance green building will
be pursued via LEED (Leadership in Energy and
Environmental Design) certification
7Next Steps
- Establishment of Data Center Project Office as
quickly as possible fund in 2007 in order to
pursue an aggressive project start-up - Assist Wyoming with preparation and presentation
of required legislative materials (process
currently underway) - Proceed with partnership formalization and NSF
approval steps (preparation of MOU, NSF approval
package, etc.) - Pending approval of funding by Wyoming
legislature, initiate architecture and
engineering (design) work
Targeted milestones Construction initiation
(shovels in the ground) Within one
year Facility open for operation Late
2010/early 2011
8Thank You
- To Lawrence Buja and Peter Fox for leading the
data center project over the past year - To the many people who have helped bring about
this exciting new partnership - Aaron Andersen, Rick Anthes, Peter Backlund, Tom
Bettge, Rena Brasher-Alleva, Guy Brasseur, Frank
Bryan, Lawrence Buja, Peter Fox, Al Kellie,
Janice Kauvar, Krista Laursen, Rich Loft, Gary
New, Annick Pouquet, Jeff Reaves, Katy Schmoll,
Henry Tufo, Olga Wilhelmi, Mike Wiltberger,
Larry Winter and the many other people
throughout CISL, NCAR, and UCAR who have
provided critical support
9Questions?
- Krista Laursen (krista_at_ucar.edu, x2003) Data
Center Project Office Director
Please refer inquiries from the media to Krista,
Jeff Reaves (jreaves_at_ucar.edu), or David Hosansky
(UCAR Head of Media Relations, hosansky_at_ucar.edu)